Construction Supervision of Mass Transit System Project in Bangkok (Red Line) Bang Sue-Rangsit Section
Main Menu About the Project Project Development Public Relations Contact
Public Relations
Progress
Activity Photos
  Progress
 

 

January 2014

 

Contract 1

Tasks that have been implemented included clearing, grubbing and land levelling of area in zone 1 and zones 3-5 and stabling yards of the long-distant maintenance depot); land excavation for foundation works of the Grand Station, installation of bored piles for the construction of station building, and long-distant maintenance depot; demolition of structures at stabling yard, and removal of railway tracks at the Bang Sue Station, demolition of Hopewell structure (at zone 4 phase 1 at the western portion and zone 5 phase 3 and at the northern portion); traffic management for rail track removal in zone 4A; construction of site access road in zone 1 and zone 2 of the Bang Sue Grand Station; construction of permanent stabling yards for freight trains; survey of flyover near the Bang Sue Grand Station, main operating building and stabling yards of commuter train;land reclamation for stabling yard of commuter train and long-distant maintenance depots. Other activities were indicated in the Index B. Accumulative progress of complete task is 4.47% from the planned target of 10.49%, or 6.02% behind the schedule. Plus many others tasks as detailed hereunder:

No. Activity Status
1 Control surveys Completed
2 Land Levelling In operation
3 Preparation of mobilization work (Site office, vehicles and equipment) Completed
4 Land excavation for foundation works of the Grand Station In operation
5 Demolition of Hopewell’s 1744 structural columns(Type 1A Case 1 = 44 columns/2A Case 1 = 4 columns/Type 2B Case 1 = 2 columns/ Type 3A Case 1 = 45 columns/ Type 3B Case 1 = 10 columns/Type 4 Case 1 = 3 columns/ Type 12 Case 2 = 18 columns/ Type 13 Case 2 = 16 columns/ Type 14 Case 3 = 29 columns/ Type 15 Case 3 = 3 columns) In operation
6 Testing work of 3 Pilot piles (diameter = 1,500 mm) (at TerdDamri RoadatMRTA parking lot and at local road near SamianNari Temple). Completed
7 Testing work of Pilot pile (diameter = 1,200 mm) at the construction site of the Bang Sue Grand Station. Completed
8 Testing work of Pilot pile (diameter = 500 mm) at the construction site of the LD Depots. In operation
9 Pile testing of the existing Hopewell structures at local road near SamianNari Temple. Completed
10 Batching Plant investigation. In operation
11 Concrete Mixed Designinvestigation. In operation
12 Aggregate source investigation. In operation
13 Bored pile plant investigation. In operation
14 Demolition of premises. In operation
15 Relocation of infrastructural systems, i.e. electricity posts, telegraph posts, etc. In operation
16 Removal of concrete surface. In operation
17 Construction of 1,075 bored piles (diameter = 1,500 mm) at the Bang Sue Grand Station site. In operation
18 Removal of railway tracksat the Bang Sue Grand Station site. In operation
19 Construction of 9bored piles (diameter = 2,000mm) atthe Bang Sue Grand Station construction site. In operation
20 Soil excavation, sand bedding and lean concrete pouring, steel reinforcement of 18 footings atthe Bang Sue Grand Station construction site. In operation
21 Lean concrete pouring, steel reinforcement of one footing atthe Bang Sue Grand Station construction site. In operation
22 Construction of 938 driven piles (diameter = 0.18x0.18 m) atTrain Stabling construction site. In operation
23 Land reclamation for local road. In operation

 

Contract 2

The tasks include: land levelling for the construction of flyover at Sta. 24+910; relocation of infrastructural amenities belonged to the MWA, MEA, and TOT; installation of bored piles for the construction of elevated railway (for piles No. 044-086, 101-130, 237-266); foundation works in the areas between columns No. 054-078, 111-131, 132-150, 151-165 and237-266of the construction of elevated rail structure; demolition of Hope well structures; construction of columns (lower part of the superstructure No. 054-178 and 111-131).Demolition of existing station building and construction of temporary site office of Lak Si Station; bored pile work for foundation of Thung Song Hong and Rangsit stations; driven pile work for connecting point of the at-grade rail track before reaching the LakHok Station from Sta. 25+232.5 to Sta. 29+245 and at the flyover of Sta. 24+910; removal of oil pipeline and demolition of existing station buildings at Lak Si and Bang Khen. Other activities were indicated in the Index B. Accumulative progress of complete task is 4.27% from the planned target of 26.82%, or 22.55% behind the schedule.Details of the tasks are provided hereunder:

No. Activity Status
1 Control surveys Completed
2 Land Levelling In operation
3 Preparation of mobilization work (Site office, vehicles and equipment) In operation
4 Demolition of Hopewell’s 423 structural columns
(Type 1 Case 1 = 1 column/ Type 1A Case 1 = 28 columns/ Type 2A Case 1 = 3 columns/ Type 2B Case 1 = 1column/ Type 3A Case 1 = 83 columns/ Type 4 Case 1 = 18 columns/ Type 6 Case 1 = 1 column/ Type 5A Case 2 = 3 columns/ Type 5B Case 2 = 1 column/ Type 7 Case 2 = 7columns/ Type 8 Case 2 = 70  columns/ Type 9 Case 2 = 9columns/ Type 10 Case 2 = 6columns/  Type 11 Case 2 = 84columns/Type 14A Case 3 = 36 columns/ Type 16 Case 2 = 42 columns/Type 16A Case 2 = 18 columns/ Type 16B Case 2 = 9 columns/ Type 19 Case 2 = 3 columns)
In operation
5
  • Testing work of Pilot pile (diameter = 1,500 mm) at 4 areas: 1) Lak Si area (Sta. 17+500), 2) Near Don Muang District Office (Sta. 20+600), 3) Near the entrance of Grand Canal Village (Sta. 24+600), and 4) at Rangsit Railway Station (Sta. 29+800).
  • Testing work of Pilot pile (diameter = 1,200 mm) near the entrance of Grand Canal Village (Sta. 24+600).
Completed
6 Pile testing of the existing Hopewell structures at local road near Chulabhorn Research Institute (CRI). Completed
7 Installation of 442 bored piles (diameter = 1,500 mm) In operation
8 Installation of 57 bored piles (diameter = 1,800 mm) In operation
9 Construction of 38footing works for the elevated railway(P115,  P120, P116,  P123, P125, P056, P059, P060, P061, P154, P129, P131, P064, P133, P156, P063, P135, P158, P064, P127, P249, P251, P253, P160, P69, P248, P118, P62, P162, P124, P282, P70, P163, P136, P72, P283, P250, P126). In operation
10 Construction of 25 columns for elevated railway (P115L/R,   P116L/R, P120L/R, P56L/R, P123L/R, P059L/R, P125L/R, P60L/R, P117L/R, P156L, P61L, P127R, P162L, P063R, P129R, P063L). In operation
11 Batching plant investigation. In operation
12 Concrete Mixed Design investigation. In operation
13 Aggregate source investigation. In operation
14 Asphalt plant investigation. In operation
15 Bored pile plant investigation. In operation
16 Demolition of existing railway stations (Bang Khen and Lak Si). Completed
17 Work on 1,025 driven piles (0.35 x 0.35 meters) from Sta.24+830 to Sta.25+152. In operation
18 Work on 5,517 driven piles (0.22 x 0.22 meters) for at-grade railway trackfrom Sta.25+210 to Sta.27+518. In operation
19 Earth filling work for at-grade railway track. In operation
20 Reinforced concrete work for at-grade railway track. In operation
21 Installation of 16 bored piles (dia. 1.50 meters) and 12 Barrette piles at Thung Song Hong Station. In operation
22 Removal of railway trackat the Rangsit Station site. In operation
23 Installation 41 16 bored piles (dia. 1.50 meters) at Rangsit Station. In operation
24 Earth filling work for local roads. In operation
25 Work on 424 driven piles (0.22 x 0.22 meters and 0.26 x 0.26 meters) for the foundation of flyover from Sta.25+201 to Sta.25+253. In operation
26 Work on 77 driven piles (0.80 x 0.80 metersfor the construction of flyover. In operation
27 Installation of three Cross Beams for the structure of elevated railway tracks. In operation

 
 