Construction Supervision of Mass Transit System Project in Bangkok (Red Line) Bang Sue-Rangsit Section
Main Menu About the Project Project Development Public Relations Contact
Public Relations
Progress
Activity Photos

 

  Progress
 

 

Project Progress as of January 2017

 

Contract 1

          Accumulative progress of complete task is 55.91 % from the planned target of 99.92 %, or 44.01 % behind the schedule.

Details of the tasks are provided hereunder:

No. Activity Status
1 Elevated and at Grade Railway Work
  Installed 2,255 from 3,282 columns for the structure of the elevated rail track In operation
  Installed 840 from 2,749 beams for the structure of the elevated rail track In operation
  Installed 97 from 932 main precast concrete spans of the elevated rail track In operation
  Demolition of premises In operation
  Relocation of infrastructural systems, i.e. electricity posts, telegraph posts, etc. In operation
2 Stations
  Land excavation of 254,496 cu.m from the target of 293,314 cu.m for foundation works of the Bang Sue Grand Station In operation
  Installed 1,109 from 1,232 bored piles (diameter = 1,000 mm) (including piles for approach) at the Bang Sue Grand Station construction site In operation
  Lean concrete pouring of 158 from 160 footings at the Bang Sue Grand Station construction site In operation
  Concrete pouring (Type F1A) of 622 from 632 footings at the Bang Sue Grand Station construction site In operation
  Installed 770 structural columns (from the total 800) and 1,715 beams (from the total 1,907) at the Bang Sue Grand Station construction site In operation
  Installed concrete components of elevated structures (103 spans from the total 305 spans) In operation
  Ground and wall concrete pouring for the basement of the Bang Sue Grand Station construction site In operation
3 LD Train Maintenance Depot Work
  Wall masonry and plastering at the Daily Maintenance construction site In operation
  Installed steel structure at the hallway of the Daily Maintenance building In operation
  Installed 1,547 from 1,596 driven piles (0.40x0.40 m) at the Passenger Coach construction site In operation
  Installed column and roof steel structures at the Passenger Coach construction site In operation
  Concrete pouring at the Passenger Coach construction site In operation
  Wall masonry and plastering at the Passenger Coach construction site In operation
4 CT Train Maintenance Depot Work
  Installed the total 266 structural columns at the Main Workshop construction site In operation
  Installed precast beams and concrete pouring at the Main Workshop construction site In operation
  Installed column steel structures at the Main Workshop construction site In operation
  Installed culverts at the Infrastructure Workshop construction site In operation
  Installed precast slabs and wall masonry at the Infrastructure Workshop construction site Completed
  Installed 2,102 from 2,384 driven piles (0.18x0.18 m) at the Train Stabling construction site In operation
  Finished 741 from 1,168 footings at the Train Stabling construction site In operation
  Installed 1,234 from 2,384 structural columns at the Train Stabling construction site In operation
  Installed platforms at the Train Stabling construction site In operation
5 Local Road and Road Flyover Work
  Earth filling work for local road In operation
  Installed U-ditches at the construction site In operation

 

 

Summary Report of The Execution of Contract 1 for January 2017

Contract 1: Civil Works for Bang Sue Grand Station and Depots
Bill No. Description Contract Amount  (Baht) % Progress as of 25 January 2017 Status
planned actual
1 General Requirements 266,482,434 99.31% 96.48% -2.82%
2 Track Work 11,422,571,521 99.87% 68.42% -31.45%
3 Stations 14,247,067,853 99.96% 42.90% -57.06%
4 LD Train Depots and CT Train Depots 1,604,023,818 100.00% 95.15% -4.85%
5 Local Road and Road Flyover 1,410,141,074 99.99% 48.30% -51.69%
6 Provisional sums and Provisional Items 672,130,000 100.00% 26.69% -73.31%
7 Day-Work Schedule 17,823,300 96.15% 0.00% -96.15%
Total 29,640,240,000 99.92% 55.91% -44.01%

 

 

Summary Table of Construction Plan and Progress of Contract 1 for January 2017

 

 

Contract 2

         Accumulative progress of complete task is 81.48 % from the planned target of 87.65 %, or 6.17 % behind the schedule

Details of the tasks are provided hereunder:

No. Activity Status
1 Elevated and at Grade Railway Work
  Installed 10,060 from 14,303 segments for elevated railway In operation
  Installation of boundary fences In operation
2 Station Work
  Installed aerated concrete walls on ticket hall floor at Wat Samian Nari Station In operation
  Flooring tiling work at Wat Samian Nari Station In operation
  Installed steel structure for entrance staircases at Wat Samian Nari Station In operation
  Installed elevators and escalators at Wat Samian Nari Station In operation
  Installed electricity and mechanical systems at Wat Samian Nari Station In operation
  Installed aerated concrete walls on ticket hall floor at Bang Khen Station In operation
  Flooring tiling work at Bang Khen Station In operation
  Installed elevators and escalators at Bang Khen Station In operation
  Installed electricity and mechanical systems at Bang Khen Station In operation
  Installed aerated concrete walls on ticket hall floor at Thung Song Hong Station In operation
  Flooring tiling work at Thung Song Hong Station In operation
  Installed electricity and mechanical systems at Thung Song Hong Station In operation
  Installed aerated concrete walls on ticket hall floor at Lak Si Station In operation
  Installed steel structure for entrance staircases at Lak Si Station In operation
  Installed electricity and mechanical systems at Lak Si Station In operation
  Installed elevators and escalators at Lak Si Station In operation
  Installed aerated concrete walls on ticket hall floor at Kan Kheha Station In operation
  Installed steel structure for entrance staircases at Kan Kheha Station In operation
  Installed elevators and escalators at Kan Kheha Station In operation
  Concrete pouring for construction of ticket hall floor at Don Mueang Station In operation
  Installed steel roof structure at Don Mueang Station In operation
  Installed steel structure for entrance staircases at Don Mueang Temple Station In operation
  Installed elevators and escalators at Don Mueang Station In operation
  Installed steel structure for entrance staircases at Lak Hok Station In operation
  Installed aerated concrete walls on ticket hall floor at Lak Hok Station In operation
  Installed elevators and escalators at Lak Hok Station In operation
  Installed steel structure for entrance staircases at Rangsit Station In operation
  Installed aerated concrete walls on ticket hall floor at Rangsit Station In operation
  Installed elevators and escalators at Rangsit Station In operation
3 Local Road and Road Flyover Work
  Earth filling work for local road In operation
  Construction of drainage system for local road In operation

 

 

Summary Report of The Execution of Contract 2 for January 2017

Contract 2: Civil Works for Bang Sue-Rangsit Railway
Bill No. Description Contract Amount  (Baht) % Progress as of              25 January 2017 Status
planned actual
1 General Requirements 272,629,119 94.81% 95.11% 0.30%
2 Track work 12,431,497,987 93.86% 88.33% -5.53%
3 Stations 9,957,755,499 78.32% 72.19% -6.13%
4 Local Road and Road Flyover 1,263,337,028 98.60% 84.37% -14.23%
5 Provisional Sums and Provisional Items - - - -
Total 23,925,219,633 87.65% 81.48% -6.17%

 

 

Summary Table of Construction Plan and Progress of Contract 2 for January 2017

Contract 3

Accumulative progress of complete task is 7.94 % from the planned target of 12.61 % (early plan) and of 6.40 % (late plan), or 4.67 % and 1.54 % behind the early plan and the late plan, respectively

Details of the tasks are provided hereunder:

No. Activity Status
A 3A Bang Sue-Rangsit
1 Engineering Work  
1.1 Railway Track  
Preparation of information, preliminary design, and submission of revised information for approval In progress
Production, preparation, and submission of design details In progress
1.2 Design of Overhead Contact System (OCS)  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
1.3 Design of Electrical Power System  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
1.4 Design of Operation Control Center (OCC) and Centralized Traffic Control (CTC) system  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
1.5 Design of Computer Based Interlocking (CBI) System  
Preparation of information, preliminary design, and submission of revised information for approval In progress
Production, preparation, and submission of design details In progress
1.6 Design of Automatic Train Protection (ATP)/ Automatic Train Operation (ATO) System  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
1.7 Design of Wayside Equipment (Signal) System  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
1.8 Design of Data Transmission System (DTS)  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
1.9 Design of Radio System  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
1.10 Design of  Master Clock (MC) System  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
1.11 Design of CCTV System  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
1.12 Design of Passenger Information Display System (PIDS)  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
1.13 Design of Public Address (PA) System  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
1.14 Design of Station Management System (SMS)  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
1.15 Design of Train-Borne Communication System (TCS)  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
1.16 Design of telephone system  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
1.17 Design of Automatic Fare Collection (AFC) System  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
1.18 Design of Depot Machinery and Equipment  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
1.19 Design of Other Associated Systems, including Collision Avoidance System (CAS), Quality Assurance (QA) and Train Information (TI) system  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
1.20 Design of Train Car Body  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
2 Procurement of materials and manufacturers  
  Survey, data collection, negotiation and contract signing In progress
  Track fasteners, track ballast, turnouts, bumpers and concrete sleepers  
3 Provision of standard construction machinery and equipment and submission for approval In progress
4 Preparation and submission of information in term of standard of Overhead Catenary System (OCS) works In operation
B 3B Bang Sue-Taling Chan  
1 Survey of construction site for Bang Sue-Taling Chan railway track In operation

 
 