Construction Supervision of Mass Transit System Project in Bangkok (Red Line) Bang Sue-Rangsit Section
Main Menu About the Project Project Development Public Relations Contact
Public Relations
Progress
Activity Photos

 

  Progress
 

 

Project Progress as of January 2018

 

Contract 1

         Accumulative progress of complete task is 65.20 % from the planned target of 65.30 %, or 0.10% ahead of the schedule.

         Details of the tasks are provided hereunder:

 
No. Activity Status
1 Elevated and at Grade Railway Work
  Installed a total of 3,282 columns for the structure of the elevated rail track Completed
  Installed 2,682 from 2,749 beams for the structure of the elevated rail track In operation
  Installed 365 from 932 main precast concrete spans of the elevated rail track In operation
  Demolition of premises In operation
  Relocation of infrastructural systems, i.e. electricity posts, telegraph posts, etc. In operation
2 Stations
  Installed a total of 1,232 bored piles (diameter = 1,000 mm) (including piles for approach) at the Bang Sue Grand Station construction site Completed
  Concrete pouring (Type F1A) of 638 from 753 footings at the Bang Sue Grand Station construction site In operation
  Installed 245 from 305 main precast concrete spans of the elevated rail track at the Bang Sue Grand Station construction site In operation
  Ground and wall concrete pouring for the basement of the Bang Sue Grand Station construction site In operation
  Concrete pouring on ticket hall and platform floors at the Bang Sue Grand Station construction site In operation
  Installed steel roof structure at the Bang Sue Grand Station construction site In operation
3 LD Train Maintenance Depot Work
  Interior finishing at the Daily Maintenance Building construction site In operation
  Concrete pouring at the Passenger Coach Building construction site In operation
  Interior finishing at the Passenger Coach Building construction site In operation
4 CT Maintenance Depot Work
  Interior finishing at the Main Workshop construction site In operation
  Interior finishing at the Infrastructure Workshop construction site In operation
  Installed platforms at the Train Stabling construction site In operation
     
5 Local Road and Road Flyover Work
  Earth filling work for local road In operation
  Installed U-ditches at the construction site In operation

 

 

Summary Report of the Execution of Contract 1 for January 2018 (Early Plan)

Contract 1: Civil Works for Bang Sue Grand Station and Depots
Bill No. Description Contract Amount  (Baht) % Progress as of
25 January 2018
Status
planned actual
1 General Requirements 266,482,434 100.00% 97.89% -2.11%
2 Track Work 11,422,571,521 100.00% 95.33% -4.67%
3 Stations 14,247,067,853 100.00% 53.56% -46.44%
4 LD Train Depots and CT Depots 1,604,023,818 100.00% 83.67% -16.33%
5 Local Road and Road Flyover 1,410,141,074 100.00% 67.88% -32.12%
6 Provisional sums and Provisional Items 672,130,000 100.00% 18.59% -81.41%
7 Day-Work Schedule 17,823,300 100.00% 0.00% -100.00%
Total 29,640,240,000 100.00% 74.58% -25.42%

 

Summary Report of the Execution of Contract 1 for January 2018 (Late Plan)

Contract 1: Civil Works for Bang Sue Grand Station and Depots
Bill No. Description Contract Amount  (Baht) % Progress as of
25 January 2018
Status
planned actual
1 General Requirements 266,482,434 97.62% 97.89% 0.27%
2 Track Work 12,127,119,738 83.98% 89.79% 5.81%
3 Stations 16,823,702,974 52.18% 45.36% -6.82%
4 LD Train Depots and CT Depots 1,604,023,818 100.00% 85.49% -14.51%
5 Local Road and Road Flyover 2,393,497,138 46.41% 39.99% -6.42%
6 Provisional sums and Provisional Items 672,130,000 29.88% 18.59% -11.29%
7 Day-Work Schedule 17,823,300 4.35% 0.00% -4.35%
Total 33,904,779,402 65.30% 65.20% -0.10%

 

 

 Summary Table of Construction Plan and Progress of Contract 1 for January 2018

 

 

Contract 2

       Accumulative progress of complete task is 95.46% from the planned target of 99.95%, or 4.49% behind the schedule

Details of the tasks are provided hereunder:

No. Activity Status
1 Elevated and at Grade Railway Work
  Installed 13,639 from 14,303 segments for elevated railway In operation
  Installation of boundary fences In operation
2 Station Work
  Interior finishing at Wat Samian Nari Station In operation
  Installed elevators and escalators at Wat Samian Nari Station In operation
  Installed electricity and mechanical systems at Wat Samian Nari Station In operation
  Interior finishing at Bang Khen Station In operation
  Installed elevators and escalators at Bang Khen Station In operation
  Installed electricity and mechanical systems at Bang Khen Station In operation
  Interior finishing at Thung Song Hong Station In operation
  Installed electricity and mechanical systems at Thung Song Hong Station In operation
  Installed elevators and escalators at Thung Song Hong Station In operation
  Interior finishing at Lak Si Station In operation
  Installed electricity and mechanical systems at Lak Si Station In operation
  Installed elevators and escalators at Lak Si Station In operation
  Interior finishing at Kan Kheha Station In operation
  Installed electricity and mechanical systems at Kan Kheha Station In operation
  Installed elevators and escalators at Kan Kheha Station In operation
  Concrete pouring for construction of ticket hall floor at Don Mueang Station In operation
  Installed steel roof structure at Don Mueang Station In operation
  Installed aerated concrete walls on ticket hall floor at Don Mueang Station In operation
  Installed steel structure for entrance staircases at Don Mueang Station In operation
  Installed electricity and mechanical systems at Don Mueang Station In operation
  Installed elevators and escalators at Don Mueang Station In operation
  Installed aerated concrete walls on ticket hall floor at Lak Hok Station In operation
  Installed electricity and mechanical systems at Lak Hok Station In operation
  Installed elevators and escalators at Lak Hok Station In operation
  Installed steel structure for entrance staircases at Rangsit Station In operation
  Installed aerated concrete walls on ticket hall floor at Rangsit Station In operation
  Installed electricity and mechanical systems at Rangsit Station In operation
  Installed elevators and escalators at Rangsit Station In operation
3 Local Road and Road Flyover Work
  Local road construction In operation
  Construction of drainage system for local road In operation

 

 

Summary Report of the Execution of Contract 2 for January 2018

Contract 2: Civil Works for Bang Sue-Rangsit Railway
Bill No. Description Contract
Amount  (Baht)
% Progress as of
25 January 2018
Status
planned actual
1 General Requirements 272,629,119 100.00% 96.43% -3.57%
2 Track Work 12,431,497,987 100.00% 98.86% -1.14%
3 Stations 9,957,755,499 99.88% 91.42% -8.46%
4 Local Road and Road Flyover 1,263,337,028 100.00% 93.69% -6.31%
5 Provisional Sums and Provisional Items - - - -
Total 23,925,219,633 99.95% 94.65% -4.49%

 

 

 Summary Table of Construction Plan and Progress of Contract 2 for January 2018

Contract 3

Accumulative progress of complete task is 19.57% from the planned target of 38.68% (early plan) and of 29.44% (late plan), or 19.11% and 9.87% behind the early plan and the late plan, respectively.

Details of the tasks are provided hereunder:

No. Activity Status
A 3A Bang Sue-Rangsit and 3B Bang Sue-Taling Chan
1 General Requirements
1.1 Management
1.1.1 Risk analysis and management In progress
2 Engineering Work
2.1 Railway Track  
Production, preparation, and submission of design details In progress
Production and submission of revised information for approval In progress
Production, preparation, and submission of testing steps In progress
2.2 Electrical System
2.2.1 Design of Overhead Catenary System (OCS)  
Preparation of information, preliminary design, and submission of revised information for approval In progress
Production and submission of revised information for approval In progress
Production, preparation, and submission of testing steps In progress
2.2.2 Design of Power Supply and Distribution System (PDS)  
Preparation of information, preliminary design, and submission of revised information for approval In progress
Production and submission of revised design for approval In progress
2.3 Railway Signaling and Control Systems
2.3.1 Operation Control Center (OCC) and Centralized Traffic Control (CTC) system  
Preparation and submission of information and preliminary design In progress
Preparation and submission of information and  revised preliminary design for approval In progress
2.3.2 Computer Based Interlocking (CBI)  
Preparation and submission of information and preliminary design In progress
Preparation and submission of information and  revised preliminary design for approval In progress
2.3.3 Automatic Train Protection (ATP) and Automatic Train Operation (ATO)  
Preparation and submission of information and preliminary design In progress
Preparation and submission of information and  revised preliminary design for approval In progress
2.3.4 Wayside Equipment (Signal)
Preparation and submission of information and preliminary design In progress
Preparation and submission of information and  revised preliminary design for approval In progress
Production, preparation, and submission of design details In progress
2.4 Telecommunication System
2.4.1 Design of Data Transmission System (DTS)  
Production and submission of revised design for approval In progress
2.4.2 Design of Radio System  
Preparation and submission of information and  revised preliminary design for approval In progress
Production and submission of revised design details for approval In progress
2.4.3 Design of  Master Clock (MC) System  
Production and submission of revised design for approval In progress
2.4.4 Design of CCTV System  
Production and submission of revised design for approval In progress
2.4.5 Design of Passenger Information Display System (PIDS)
Production and submission of revised design for approval In progress
2.4.6 Design of Public Address (PA) System
Production and submission of revised design for approval In progress
2.4.7 Design of Station Management System (SMS)  
Production and submission of revised design for approval In progress
2.4.8 Design of Train-Borne Communication System (TCS)  
Production and submission of revised design for approval In progress
2.4.9 Design of Telephone System  
Production and submission of revised design for approval In progress
2.5 Automatic Fare Collection (AFC) System
Preparation and submission of information and revised preliminary design for approval In progress
Production, preparation, and submission of design details In progress
Production and submission of revised design details for approval In progress
2.6 Depot Machinery and Equipment
2.6.1 Design of LD Train Depot Machinery and Equipment  
Preparation and submission of information and revised preliminary design for approval In progress
Production, preparation, and submission of design details In progress
2.6.2 Design of CT Depot Machinery and Equipment  
Preparation and submission of information and revised preliminary design for approval In progress
Production, preparation, and submission of design details In progress
Production and submission of revised design details for approval In progress
2.7 Other Systems
2.7.1 Design of Control Access Security System (CASS)  
Production and submission of revised design details for approval In progress
2.7.2 Design of Operation Automation and Information Technology System (OA&IT)  
Production and submission of revised design details for approval In progress
2.8 Design of Train Car Body
Preparation of preliminary design details In progress
Preparation and submission of information and revised preliminary design for approval In progress
Production and preparation of design details In progress
Production and submission of revised design details for approval In progress
2.9 Construction Planning and Design
Production of preliminary design of electric power substation and submission of revised design for approval In progress
3 Procurement of Manufacturers
3.1 Railway Track
Manufacturer examination and railway testing In progress
Rail transport operations In progress
Manufacturer examination and track fastener testing In progress
Track fastener transport In progress
Manufacturer examination and ballast stone testing In progress
Manufacturer examination and testing of railway turnouts, expansion joints, compromise rails In progress
Manufacturer examination and rubber pad testing In progress
Preparation of information, manufacturer examination and testing, negotiation, and contract signing In progress
Manufacturer examination and testing for provision of concrete sleepers for non-ballasted track system In progress
Manufacturer examination and testing for provision of concrete sleepers for ballasted track system In progress
3.2 Electrical System
3.2.1 Overheard Catenary System (OCS)  
Preparation of information, manufacturer examination and testing, negotiation, and contract signing for provision of Overheard Catenary System (OCS) equipment and beams In progress
Preparation of information, manufacturer examination and testing, negotiation, and contract signing for provision of signal posts In progress
Preparation of information, manufacturer examination and testing, negotiation, and contract signing for associated works In progress
Preparation of information, manufacturer examination and testing, negotiation, and contract signing for provision of associated OCS works In progress
3.2.2 Power Supply and Distribution System (PDS)
Manufacturer examination and 115-kV system testing In progress
Preparation of information, manufacturer examination and testing, negotiation, and contract signing for provision of 115/25 traction transformer In progress
Preparation of information, manufacturer examination and testing, negotiation, and contract signing for provision of 115/24 traction transformer In progress
Manufacturer examination and 25-kV Gas-insulated Switchgear (GIS) testing In progress
Preparation of information, manufacturer examination and testing, negotiation, and contract signing for provision of 24 kV Switchgear In progress
Preparation of information, manufacturer examination and testing, negotiation, and contract signing for provision of 25 kV Auto Transformer In progress
Preparation of information, manufacturer examination and testing, negotiation, and contract signing for provision of 25 kV AT Switching Station In progress
Manufacturer examination and 24/0.4 kV Dry-type Transformer testing In progress
Preparation of information, manufacturer examination and testing, negotiation, and contract signing for provision of 400V Emergency Diesel Generator In progress
Procurement of agents, negotiation, and contract signing for provision of power cables In progress
3.2.3 Supervisory Control and Data Acquisition (SCADA)
Preparation of information, manufacturer examination and testing, negotiation, and contract signing for provision of Supervisory Control and Data Acquisition (SCADA) In progress
Preparation of information, manufacturer examination and testing, negotiation, and contract signing for provision of cables In progress
3.3 Telecommunication System
3.3.1 Data Transmission System (DTS)  
Manufacturer examination and system testing In progress
3.3.2 Radio System  
Manufacturer examination and system testing In progress
3.3.3 Master Clock (MC) System  
Manufacturer examination and system testing In progress
3.3.4 CCTV System  
Manufacturer examination and system testing In progress
3.3.5 Passenger Information Display System (PIDS)
Manufacturer examination and system testing In progress
3.3.6 Public Address (PA) System
Manufacturer examination and system testing In progress
3.3.7 Station Management System (SMS)
Manufacturer examination and system testing In progress
3.3.8 Train-borne Communication System (TCS)
Manufacturer examination and system testing In progress
3.3.9 Telephone System
Manufacturer examination and system testing In progress
3.4 Automatic Fare Collection (AFC) System
Preparation for procurement, manufacturer examination, and testing In progress
3.5 Depot Machinery and Equipment
3.5.1 LD Train Depot Machinery and Equipment
Preparation of information, manufacturer examination and testing, negotiation, and contract signing In progress
3.5.2 CT Depot Machinery and Equipment
Preparation for procurement, manufacturer examination and testing In progress
3.6 Other Associated Systems, including Control Access Security System (CASS), Operation Automation and Information Technology System (OA&IT)
Preparation of information, manufacturer examination and testing, negotiation, and contract signing In progress
3.7 Train Car Body
3.7.1 Materials and Equipment  
Preparation of train car body construction standard In progress
Agent procurement, negotiation, and contract signing for train car body In progress
Preparation of brake and air distribution system construction standard In progress
Agent procurement, negotiation, and contract signing for brake and air distribution system In progress
3.8 Construction Machinery and Tools
Manufacturer examination and testing In progress

 

Summary Table of Construction Plan and Progress of Contract 3 for January 2018

 


 
 