Construction Supervision of Mass Transit System Project in Bangkok (Red Line) Bang Sue-Rangsit Section
Main Menu About the Project Project Development Public Relations Contact
Public Relations
Progress
Activity Photos

 

  Progress
 

 

February 2015

 

 

Contract 1

           Other activities were indicated in the Index. Accumulative progress of complete task is 19.68% from the planned target of 34.58%, or 14.90% behind the schedule.

Details of the tasks are provided hereunder:

No. Activity Status
1 Elevated and at Grade Railways Work
  Testing of 3 pilot piles (diameter = 1,500 mm) (at Terd Damri Road at MRTA parking lot and at local road near Samian Nari Temple). Completed
  Testing of pilot piles (diameter = 1,200 mm) at the construction site of the Grand Station. Completed
  Testing of pilot piles (diameter = 800 mm) at the construction site of road flyover. Completed
  Pile testing of the existing Hopewell structures at local road near Samian Nari Temple. Completed
  Demolition of 237 from 239 Hopewell’s structural columns (Type 1A Case 1 = 65 columns/ Type 2A, 2B Case 1 = 11 columns/ Type 3A, 3B Case 1 = 60 columns/ Type 4 Case 1 = 5 columns/ Type 12 Case 2 = 29 columns/ Type 13 Case 2 = 32 columns/ Type 14 Case 3 = 32 columns/ Type 15 Case 3 = 3 columns) In operation
  Installed 71 from 214 (diameter = 1,200 mm) bored piles for the structure of the elevated rail track. In operation
  Installed 931 from 2,596 bored piles (diameter = 1,500 mm) for the structure of the elevated rail track. In operation
  Installed 76 from 114 bored piles (diameter = 2,000 mm) for the structure of the elevated rail track. In operation
  Installed 7 from 16 barrette piles (diameter = 1,000x3,000 mm) for the structure of the elevated rail track. In operation
  Concrete pouring of 98 footings for elevated railway In operation
  Demolition of premises. In operation
  Relocation of infrastructural systems, i.e. electricity posts, telegraph posts, etc. In operation
  Removal of concrete surface. In operation
2 Station Work
  Land excavation of 254,496 cu.m from the target of 293,314 cu.m for foundation works of the Grand Station. In operation
  Installed 467 from 623 bored piles (diameter = 800 mm) at the Bang Sue Grand Station construction site. In operation
  Installed 736 from 1,232 bored piles (diameter = 1,000 mm) (including piles for approach) at the Bang Sue Grand Station construction site. In operation
  Installed 189 from 231 bored piles (diameter = 1,200 mm) at the Bang Sue Grand Station construction site. In operation
  Installed 1,689 from 1,706 bored piles (diameter = 1,500 mm) at the Bang Sue Grand Station construction site. In operation
  Installed 91 from 123 bored piles (diameter = 2,000 mm) at the Bang Sue Grand Station construction site. In operation
  Lean concrete pouring of 118 from 160 footings at the Bang Sue Grand Station construction site. In operation
  Concrete pouring (Type F1A) of 127 from 632 footings at the Bang Sue Grand Station construction site. In operation
  Removal of railway tracks at the Bang Sue Grand Station construction site. In operation
  Installation of fuel oil pipeline of FPT In operation
3 Long-Distant Maintenance Depot Work
  Installed 1,426 driven piles (0.40x0.40 m) and construction of 234 bored piles (diameter 0.50 m) at the Daily Maintenance construction site. Completed
  Finished 606 from 709 footings at the Daily Maintenance construction site. In operation
  Installed 557 from 4,991 structural columns at the Daily Maintenance construction site. In operation
  Installed pre cast beams at the Daily Maintenance construction site. In operation
  Installed 1,491 from 1,596 driven piles (0.40x0.40 m) at the Passenger Coach construction site. In operation
4 CT Train Maintenance Depot Work
  Installed 1,405 from 1,559 driven piles (0.40x0.40 m) at the Main Workshop construction site. In operation
  Finished 190 from 328 footings at the Main Workshop construction site. In operation
  Installed 166 structural columns at the Main Workshop construction site. In operation
  Installed pre cast beams at the Main Workshop construction site. In operation
  Installed 582 driven piles (0.40x0.40 m) at the Infrastructure Workshop construction site. Completed
  Finished 243 from 244 footings at the Infrastructure Workshop construction site. In operation
  Installed 243 from 244 structural columns at the Infrastructure Workshop construction site. In operation
  Installed pre cast beams at the Infrastructure Workshop construction site. In operation
  Installed columns and superstructure at the Infrastructure Workshop construction site. In operation
  Installed 1,796 from 2,384 driven piles (0.18x0.18 m) at the Train Stabling construction site. In operation
  Finished 741 from 1,168 footings at the Train Stabling construction site. In operation
  Installed 1,234 from 2,384 structural columns at the Train Stabling construction site. In operation
5 Local Road and Road Flyover Work
  Earth filling work forlocal road. In operation
  Installed 504 from 816 driven piles (0.22x0.22 m) for road flyover. In operation
  Installed 234 from 306 driven piles (0.26x0. 26 m) for road flyover. In operation
  Installed 209 from 282 bored piles (diameter = 0.80 m). In operation
  Finished 21 from 33 footings for road flyover. In operation
  Installed 19 from 33 structural columns for road flyover. In operation
  Installed 14 from 33 beams for road flyover. In operation
  Installed U-ditches at the construction site In operation

 

 

Summary Report of The Execution of Contract 1 for February 2015

Contract 1 : Civil Works for Bang Sue Grand Station and Depots
Bill No. Description Contract Amount (BahT) % Progress as of
25-FEBRUARY-15
Status
Planned Actual
1 General Requirements 266,482,434 50.49% 59.24% 8.751%
2 Track work 11,422,571,521 30.70% 12.08% -18.62%
3 Stations 14,247,067,853 25.59% 18.99% -6.60%
4 LD-Train Depots and CT-Train Depots 1,604,023,818 81.99% 67.16% -14.82%
5 Local Road and Road Flyover 1,410,141,074 90.24% 23.70% -66.54%
6 Provisional Sums and Provisional Items 672,130,000 55.43% 26.69% -28.74%
7 Day-Work Schedule 17,823,300 7.69% 0.00% -7.69%
Total 29,640,240,000 34.58% 19.68% -14.90%

 

Summary Table of Construction Plan and Progress of Contract 1 for February 2015

 

 

Contract 2

           Other activities were indicated in the Index. Accumulative progress of complete task is 34.45% from the planned target of 77.27%, or 42.82% behind the schedule.

Details of the tasks are provided hereunder:

No. Activity Status
1 Elevated and at Grade Railways Work  
  Demolition of Hopewell’s 553 structural columns
(Type 1 Case 1 = 1 column, Type 1A Case 1 = 31 columns, Type 2A Case 1 = 5 columns, Type 2B  Case 1 = 1 column, Type 3A Case 1 = 83 columns, Type 4 Case 1 = 18 columns, Type 6 Case 1 = 1 column, Type 5A Case 2 = 3 columns, Type 5B Case 2 = 1 column, Type 7 Case 2 = 7 columns, Type 8 Case 2 = 75 columns, Type 9 Case 2 = 10 columns, Type 10 Case 2 = 6 columns, Type 11 Case 2 = 84 columns, Type 14 Case 3 = 138 columns, Type 15 = 6 columns, Type 16 Case 2 = 42 columns, Type 16A Case 2 = 18 columns, Type 16B Case 2 = 9 columns, Type 18 Case 2 = 11 columns, Type 19 Case 2 = 3 columns).
Completed
  Testing work of pilot pile (diameter = 1,500 mm) in 4 areas: 1) Lak Si area (Sta. 17+500), 2) Near Don Muang District Office (Sta. 20+600), 3) Near the entrance of Grand Canal Village (Sta. 24+600), and 4) at Rangsit Railway Station (Sta. 29+800). Completed
  Testing work of pilot pile (diameter = 1,200 mm) near the entrance of Grand Canal Village (Sta. 24+600). Completed
  Pile testing of the existing Hopewell structures at local road near Chulabhorn Research Institute (CRI). Completed
  Installation of 2,040 bored piles (diameter = 1,200, 1,500, and 1,800 mm) for elevated railway. Completed
  Installed 86 barrette piles for elevated railway. Completed
  Finished 455 footings for elevated railway In operation
  Installed 466 structural columns for elevated railway. In operation
  Installed 163 from 428 cross beams for the structure of elevated railway. In operation
  Installed 1,427 from 14,303 segments for elevated railway. In operation
  Installed 1,600 from 1,604 driven piles (0.35x0.35 m) at Sta. 24+830 to Sta. 25+152. In operation
  Installation of 18,853 driven piles (0.22x0.22 m) from 28,571 driven piles at Sta. 25+210 to Sta. 28+900. In operation
  Earth filling, sand embankment and subballast for at-grade railway track. In operation
  Reinforced concrete work for at-grade railway track. In operation
2 Station Work
  Demolition of existing railway stations (Bang Khen and Lak Si). Completed
  Installation of 66 bored piles (diameter = 1,500 mm) and 44 barrette piles at Samian Nari Temple Station. Completed
  Finished 22 footings for elevated railway at Samian Nari Temple Station. Completed
  Installed 28 from 44 structural columns for elevated railway at Samian Nari Temple Station. In operation
  Installation of cross beams for elevated railway at Samian Nari Temple Station. In operation
  Installation of 66 bored piles (diameter = 1,500 mm) and 44 barrette piles at Bang Khen Station. Completed
  Finished 22 footings for elevated railway at Bang Khen Station. Completed
  Installed 28 from 44 structural columns for elevated railway at Bang Khen Station. In operation
  Installation of 66 bored piles (diameter = 1,500 mm) and 44 barrette piles at Thung Song Hong Station. Completed
  Finished 22 footings for elevated railway at Thung Song Hong Station. Completed
  Installed 40 from 44 structural columns for elevated railway at Thung Song Hong Station. In operation
  Installation of cross beams for elevated railway at Thung Song Hong Station. In operation
  Installation of 132 bored piles (diameter = 1,500 mm) at Lak Si Station. Completed
  Finished 22 footings for elevated railway at Lak Si Station. Completed
  Installed 34 from 44 structural columns for elevated railway at Lak Si Station. In operation
  Installation of cross beams for elevated railway at Lak Si Station. In operation
  Installation of 128 bored piles (diameter = 1,500 mm) (including 4 existing Hopewell structures (total 132 structures) at Kan Kheha Station. Completed
  Finished 22 footings for elevated railway at Khan Keha Station. Completed
  Installed 36 from 44 structural columns for elevated railway at Kan Kheha Station. In operation
  Installation of cross beams for elevated railway at Khan Keha Station. In operation
  Installed 171 barrette piles at Don Muang Station. Completed
  Finished 19 from 34 footings for elevated railway at Don Muang Station. In operation
  Installed 11 from 34 structural columns for elevated railway at Don Muang Station. In operation
  Installation of 108 bored piles (diameter = 1,000 mm) at Lak Hok Station. Completed
  Finished 18 footings for elevated railway at Lak Hok Station. Completed
  Installed 18 structural columns for elevated railway at Lak Hok Station. Completed
  Installation of 470 bored piles (diameter = 1,500 mm) at Rangsit Station. Completed
  Finished 50 footings for elevated railway at Rangsit Station. Completed
  Installed 39 from 50 structural columns for elevated railway at Rangsit Station. In operation
3 Local Road and Road Flyover Work
  Construction of 528 driven piles (0.22 x 0.22 m and 0.26 x 0.26 m) for road flyover from Sta. 25+201 to Sta. 25+253. Completed
  Installation of 122 bored piles for road flyover (diameter = 800 mm). Completed
  Foundation work of 14 footings for road flyover at Sta. 24+910. Completed
  Installation of 14 structural columns for road flyover at Sta. 24+910. Completed
  Installation of substructure for road flyover at Sta. 24+910. Completed
  Installation of superstructure for road flyover at Sta. 24+910. Completed
  Installed 594 driven piles (0.22 x 0.22 m and 0.26 x 0.26 m) for road flyover at Sta. 27+650. Completed
  Installation of 66 bored piles (diameter = 800 mm) for road flyover at Sta. 27+650. Completed
  Finished 7 footings for road flyover at Sta. 27+650. Completed
  Installation of 7 structural columns for road flyover at Sta. 27+650. Completed
  Installation of substructure for road flyover at Sta. 27+650. Completed
  Installation of superstructure for road flyover at Sta. 27+650. In operation
  Earth filling work for local road In operation

 

Summary Report of The Execution of Contract 2 for February 2015

Contract 2 : Civil Works for Bang Sue - Rangsit Railway
Bill No. Description Contract Amount (BahT) %Progress as of
25-FEBRUARY-15
Status
Planned Actual
1 General Requirements 272,629,120 66.73% 56.81% 61.34%
2 Track work 10,514,931,561 79.34% 53.91% 38.80%
3 Stations 8,558,445,112 77.39% 35.78% 28.46%
4 Local Road and Road Flyover 1,264,542,043 61.56% 22.13% 20.27%
5 Provisional Sums and Provisional Items - - - -
Total 20,610,547,836 77.27% 34.45% -42.82%

 

Summary Table of Construction Plan and Progress of Contract 2 for February 2015

 
 