Construction Supervision of Mass Transit System Project in Bangkok (Red Line) Bang Sue-Rangsit Section
Main Menu About the Project Project Development Public Relations Contact
Public Relations
Progress
Activity Photos

 

  Progress
 

 

Project Progress as of February 2017

 

Contract 1

         Accumulative progress of complete task is 57.31 % from the planned target of 100.00 %, or 42.69 % behind the schedule.

Details of the tasks are provided hereunder:

No. Activity Status
1 Elevated and at Grade Railway Work
  Installed 2,388 from 3,282 columns for the structure of the elevated rail track In operation
  Installed 947 from 2,749 beams for the structure of the elevated rail track In operation
  Installed 134from 932 main precast concrete spans of the elevated rail track In operation
  Demolition of premises In operation
  Relocation of infrastructural systems, i.e. electricity posts, telegraph posts, etc. In operation
2 Stations
  Land excavation of 254,496 cu.m from the target of 293,314 cu.m for foundation works of the Bang Sue Grand Station In operation
  Installed 1,109 from 1,232 bored piles (diameter = 1,000 mm) (including piles for approach) at the Bang Sue Grand Station construction site In operation
  Lean concrete pouring of 160 footings at the Bang Sue Grand Station construction site Completed
  Concrete pouring (Type F1A) of 622 from 632 footings at the Bang Sue Grand Station construction site In operation
  Installed 770 structural columns (from the total 800) and 1,744 beams (from the total 1,907) at the Bang Sue Grand Station construction site In operation
  Installed concrete components of elevated structures (103 spans from the total 305 spans) In operation
  Installed I-girder beams at the Bang Sue Grand Station construction site In operation
  Ground and wall concrete pouring for the basement of the Bang Sue Grand Station construction site In operation
3 LD Train Maintenance Depot Work
  Wall masonry and plastering at the Daily Maintenance construction site In operation
  Installed steel structure at the hallway of the Daily Maintenance building In operation
  Installed 1,547 from 1,596 driven piles (0.40x0.40 m) at the Passenger Coach construction site In operation
  Installed column and roof steel structures at the Passenger Coach construction site In operation
  Concrete pouring at the Passenger Coach construction site In operation
  Wall masonry and plastering at the Passenger Coach construction site In operation
4 CT Train Maintenance Depot Work
  Installed the total 266 structural columns at the Main Workshop construction site In operation
  Installed precast beams and concrete pouring at the Main Workshop construction site In operation
  Installed column steel structures at the Main Workshop construction site In operation
  Installed culverts at the Infrastructure Workshop construction site In operation
  Installed precast slabs and wall masonry at the Infrastructure Workshop construction site Completed
  Installed 2,384 driven piles (0.18x0.18 m) at the Train Stabling construction site Completed
  Finished 741 from 1,168 footings at the Train Stabling construction site In operation
  Installed 1,234 from 2,384 structural columns at the Train Stabling construction site In operation
  Installed platforms at the Train Stabling construction site In operation
5 Local Road and Road Flyover Work
  Earth filling work for local road In operation
  Installed U-ditches at the construction site In operation

 

 

Summary Report of The Execution of Contract 1 for February 2017

Contract 1: Civil Works for Bang Sue Grand Station and Depots
Bill No. Description Contract Amount  (Baht) % Progress as of
   25 February 2017
Status
planned actual
1 General Requirements 266,482,434 100.00% 97.85% -2.15%
2 Track Work 11,422,571,521 100.00% 71.15% -28.85%
3 Stations 14,247,067,853 100.00% 43.57% -56.43%
4 LD Train Depots and CT Train Depots 1,604,023,818 100.00% 95.31% -4.69%
5 Local Road and Road Flyover 1,410,141,074 100.00% 48.47% -51.53%
6 Provisional sums and Provisional Items 672,130,000 100.00% 26.69% -73.31%
7 Day-Work Schedule 17,823,300 100.00% 0.00% -100.00%
Total 29,640,240,000 100.00% 57.31% -42.69%

 

 

Summary Table of Construction Plan and Progress of Contract 1 for February 2017

 

 

Contract 2

         Accumulative progress of complete task is 83.06 % from the planned target of 89.67 %, or 6.61 % behind the schedule.

Details of the tasks are provided hereunder:

No. Activity Status
1 Elevated and at Grade Railway Work
  Installed 10,060 from 14,303 segments for elevated railway In operation
  Installation of boundary fences In operation
2 Station Work
  Installed aerated concrete walls on ticket hall floor at Wat Samian Nari Station In operation
  Flooring tiling work at Wat Samian Nari Station In operation
  Installed steel structure for entrance staircases at Wat Samian Nari Station In operation
  Installed elevators and escalators at Wat Samian Nari Station In operation
  Installed electricity and mechanical systems at Wat Samian Nari Station In operation
  Installed aerated concrete walls on ticket hall floor at Bang Khen Station In operation
  Flooring tiling work at Bang Khen Station In operation
  Installed elevators and escalators at Bang Khen Station In operation
  Installed electricity and mechanical systems at Bang Khen Station In operation
  Installed aerated concrete walls on ticket hall floor at Thung Song Hong Station In operation
  Flooring tiling work at Thung Song Hong Station In operation
  Installed electricity and mechanical systems at Thung Song Hong Station In operation
  Installed electricity and mechanical systems at Thung Song Hong Station In operation
  Installed aerated concrete walls on ticket hall floor at Lak Si Station In operation
  Installed steel structure for entrance staircases at Lak Si Station In operation
  Installed electricity and mechanical systems at Lak Si Station In operation
  Installed elevators and escalators at Lak Si Station In operation
  Installed aerated concrete walls on ticket hall floor at Kan Kheha Station In operation
  Installed steel structure for entrance staircases at Kan Kheha Station In operation
  Installed elevators and escalators at Kan Kheha Station In operation
  Concrete pouring for construction of ticket hall floor at Don Mueang Station In operation
  Installed steel roof structure at Don Mueang Station In operation
  Installed steel structure for entrance staircases at Don Mueang Station In operation
  Installed elevators and escalators at Don Mueang Station In operation
  Installed steel structure for entrance staircases at Lak Hok Station In operation
  Installed aerated concrete walls on ticket hall floor at Lak Hok Station In operation
  Installed elevators and escalators at Lak Hok Station In operation
  Installed steel structure for entrance staircases at Rangsit Station In operation
  Installed aerated concrete walls on ticket hall floor at Rangsit Station In operation
  Installed aerated concrete walls on ticket hall floor at Lak Hok Station In operation
3 Local Road and Road Flyover Work
  Earth filling work for local road In operation
  Construction of drainage system for local road In operation

 

 

Summary Report of The Execution of Contract 2 for February 2017

Contract 2: Civil Works for Bang Sue-Rangsit Railway
Bill No. Description Contract Amount  (Baht) % Progress as of 
       25 February 2017
Status
planned actual
1 General Requirements 272,629,119 95.89% 95.88% -0.01%
2 Track work 12,431,497,987 96.18% 89.65% -6.53%
3 Stations 9,957,755,499 80.16% 73.80% -6.36%
4 Local Road and Road Flyover 1,263,337,028 99.27% 88.53% -10.74%
5 Provisional Sums and Provisional Items - - - -
Total 23,925,219,633 89.67% 83.06% -6.61%

 

 

Summary Table of Construction Plan and Progress of Contract 2 for February 2017

Contract 3

Accumulative progress of complete task is 8.72 % from the planned target of 15.72 % (early plan) and of 7.92 % (late plan), or 7.00 % behind the early plan and 0.80 % ahead of the late plan.

Details of the tasks are provided hereunder:

No. Activity Status
A 3A Bang Sue-Rangsit
1 Management  
1.1 Preparation of disbursement plan, preparation and submission In progress
1.2 Planning the submission of construction design, preparation and submission In progress
1.3 Risk analysis and prevention, preparation and submission In progress
2 Engineering Work  
2.1 Railway Track  
Preparation of information, preliminary design, and submission of revised information for approval In progress
Production, preparation, and submission of design details In progress
2.2 Design of Overhead Contact System (OCS)  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
2.3 Design of Electrical Power System  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
2.4 Design of Data Transmission System (DTS)  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
2.5 Design of Radio System  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
2.6 Design of  Master Clock (MC) System  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
2.7 Design of CCTV System  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
2.8 Design of Passenger Information Display System (PIDS)  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
2.9 Design of Public Address (PA) System  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
2.10 Design of Station Management System (SMS)  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
2.11 Design of Train-Borne Communication System (TCS)  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
2.12 Design of telephone system  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
2.13 Design of Automatic Fare Collection (AFC) System  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
2.14 Design of Depot Machinery and Equipment  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
2.15 Design of Other Associated Systems, including Collision Avoidance System (CAS), Quality Assurance (QA) and Train Information (TI) system  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
2.16 Design of Train Car Body  
  Production, preparation, and submission of design details In progress
  Preparation of information, preliminary design, and submission of revised information for approval In progress
3 Procurement of materials and manufacturers  
  Survey, data collection, factory test and inspection, negotiation and contract signing for procurement of track fasteners, track ballast, turnouts, bumpers and concrete sleepers, and factory test In progress
4 Preparation and submission of information in term of standard of Overhead Catenary System (OCS) works In progress
5 Communication system  
5.1 Design of Data Transmission System (DTS)  
  Preparation of information, factory test and inspection, negotiation and contract signing In progress
5.2 Radio System  
  Preparation of information, factory test and inspection, negotiation and contract signing In progress
5.3 Master Clock (MC) System  
  Preparation of information, factory test and inspection, negotiation and contract signing In progress
5.4 CCTV System  
  Preparation of information, factory test and inspection, negotiation and contract signing In progress
5.5 Passenger Information Display System (PIDS)  
  Preparation of information, factory test and inspection, negotiation and contract signing In progress
5.6 Public Address (PA) System  
  Preparation of information, factory test and inspection, negotiation and contract signing In progress
5.7 Station Management System (SMS)  
  Preparation of information, factory test and inspection, negotiation and contract signing In progress
5.8 Train-Bome Communication System (TCS)  
  Preparation of information, factory test and inspection, negotiation and contract signing In progress
5.9 Design of telephone system  
  Preparation of information, factory test and inspection, negotiation and contract signing In progress
5.10 Automatic Fare Collection (AFC) System  
  Preparation of information, factory test and inspection, negotiation and contract signing In progress
6 Other Associated Systems, including Collision Avoidance System (CAS), Quality Assurance (QA) and Train Information (TI) system  
  Preparation of information, factory test and inspection, negotiation and contract signing In progress
7 Machinery and equipment  
  Procurement of distributor In progress
B 3B Bang Sue-Taling Chan  
1 Submission of survey findings In progress

 
 