Construction Supervision of Mass Transit System Project in Bangkok (Red Line) Bang Sue-Rangsit Section
Main Menu About the Project Project Development Public Relations Contact
Public Relations
Progress
Activity Photos

 

  Progress
 

 

Project Progress as of March 2018

 

Contract 1

         Accumulative progress of complete task is 66.47 % from the planned target of 67.06 %, or 0.59 % behind the schedule.

         Details of the tasks are provided hereunder:

 
No. Activity Status
1 Elevated and at Grade Railway Work
  Installed 2,710 from 2,749 beams for the structure of the elevated rail track In operation
  Installed 474 from 932 main precast concrete spans of the elevated rail track In operation
  Demolition of premises In operation
  Relocation of infrastructural systems, i.e. electricity posts, telegraph posts, etc. In operation
2 Stations
  Concrete pouring (Type F1A) of 680 from 753 footings at the Bang Sue Grand Station construction site In operation
  Installed 268 from 305 main precast concrete spans of the elevated rail track at the Bang Sue Grand Station construction site In operation
  Ground and wall concrete pouring for the basement of the Bang Sue Grand Station construction site In operation
  Concrete pouring on ticket hall and platform floors at the Bang Sue Grand Station construction site In operation
  Installed steel roof structure at the Bang Sue Grand Station construction site In operation
  Installed aerated concrete walls on ticket hall floor the Bang Sue Grand Station construction site In operation
3 LD Train Maintenance Depot Work
  Interior finishing at the Daily Maintenance Building construction site In operation
  Concrete pouring at the Carriage Shop Building construction site In operation
  Interior finishing at the Passenger Coach Building construction site In operation
4 CT Maintenance Depot Work
  Interior finishing at the Main Workshop construction site In operation
  Interior finishing at the Infrastructure Workshop construction site In operation
  Installed platforms at the Train Stabling construction site In operation
5 Local Road and Road Flyover Work
  Earth filling work for local road In operation
  Installed U-ditches at the construction site In operation

 

 

Summary Report of the Execution of Contract 1 for March 2018 (Early Plan)

Contract 1: Civil Works for Bang Sue Grand Station and Depots
Bill No. Description Contract Amount (Baht) % Progress as of
25 March 2018
Status
planned actual
1 General Requirements 266,482,434 100.00% 97.89% -2.11%
2 Track Work 11,422,571,521 100.00% 98.27% -1.73%
3 Stations 14,247,067,853 100.00% 56.60% -43.40%
4 LD Train Depots and CT Depots 1,604,023,818 100.00% 87.15% -12.85%
5 Local Road and Road Flyover 1,410,141,074 100.00% 68.59% -31.41%
6 Provisional sums and Provisional Items 672,130,000 100.00% 18.59% -81.41%
7 Day-Work Schedule 17,823,300 100.00% 0.00% -100.00%
Total 29,640,240,000 100.00% 77.33% -22.67%

 

Summary Report of the Execution of Contract 1 for March 2018 (Late Plan)

Contract 1: Civil Works for Bang Sue Grand Station and Depots
Bill No. Description Contract Amount (Baht) % Progress as of
25 March 2018
Status
planned actual
1 General Requirements 266,482,434 97.83% 97.89% 0.06%
2 Track Work 12,127,119,738 85.68% 92.56% 6.88%
3 Stations 16,823,702,974 57.12% 47.93% -9.19%
4 LD Train Depots and CT Depots 1,604,023,818 100.00% 87.15% -12.85%
5 Local Road and Road Flyover 2,393,497,138 51.28% 40.41% -10.87%
6 Provisional sums and Provisional Items 672,130,000 36.25% 18.59% -17.66%
7 Day-Work Schedule 17,823,300 13.04% 0.00% -13.04%
Total 33,904,779,402 68.84% 67.60% -1.24%

 

 

 Summary Table of Construction Plan and Progress of Contract 1 for March 2018

 

 

Contract 2

       Accumulative progress of complete task is 97.16% from the planned target of 99.06%, or 1.90% behind the schedule

Details of the tasks are provided hereunder:

No. Activity Status
1 Elevated and at Grade Railway Work
  Installed 14,283 from 14,303 segments for elevated railway In operation
  Installation of boundary fences In operation
2 Station Work
  Interior finishing at Wat Samian Nari Station In operation
  Installed elevators and escalators at Wat Samian Nari Station In operation
  Installed electricity and mechanical systems at Wat Samian Nari Station In operation
  Interior finishing at Bang Khen Station In operation
  Installed elevators and escalators at Bang Khen Station In operation
  Installed electricity and mechanical systems at Bang Khen Station In operation
  Interior finishing at Thung Song Hong Station In operation
  Installed electricity and mechanical systems at Thung Song Hong Station In operation
  Installed elevators and escalators at Thung Song Hong Station In operation
  Interior finishing at Lak Si Station In operation
  Installed electricity and mechanical systems at Lak Si Station In operation
  Installed elevators and escalators at Lak Si Station In operation
  Interior finishing at Kan Kheha Station In operation
  Installed electricity and mechanical systems at Kan Kheha Station In operation
  Installed elevators and escalators at Kan Kheha Station In operation
  Concrete pouring for construction of ticket hall floor at Don Mueang Station In operation
  Installed steel roof structure at Don Mueang Station In operation
  Installed aerated concrete walls on ticket hall floor at Don Mueang Station Completed
  Installed steel structure for entrance staircases at Don Mueang Station In operation
  Installed electricity and mechanical systems at Don Mueang Station In operation
  Installed elevators and escalators at Don Mueang Station In operation
  Installed aerated concrete walls on ticket hall floor at Lak Hok Station Completed
  Installed electricity and mechanical systems at Lak Hok Station In operation
  Installed elevators and escalators at Lak Hok Station In operation
  Installed steel structure for entrance staircases at Rangsit Station In operation
  Installed aerated concrete walls on ticket hall floor at Rangsit Station Completed
  Installed electricity and mechanical systems at Rangsit Station In operation
  Installed elevators and escalators at Rangsit Station In operation
3 Local Road and Road Flyover Work
  Local road construction In operation
  Construction of drainage system for local road In operation

 

 

Summary Report of the Execution of Contract 2 for March 2018

Contract 2: Civil Works for Bang Sue-Rangsit Railway
Bill No. Description Contract
Amount  (Baht)
% Progress as of             
25 March 2018
Status
planned actual
1 General Requirements 272,629,119 99.19% 97.86% -1.33%
2 Track Work 12,431,497,987 99.99% 99.43% -0.56%
3 Stations 9,957,755,499 99.46% 94.75% -4.71%
4 Local Road and Road Flyover 1,263,337,028 99.92% 93.69% -6.24%
5 Provisional Sums and Provisional Items - - - -
Total 23,925,219,633 99.06% 97.16% -1.90%

 

 

 Summary Table of Construction Plan and Progress of Contract 2 for March 2018

Contract 3

Accumulative progress of complete task is 25.59% from the planned target of 49.74% (early plan) and of 40.70% (late plan), or 24.15% and 15.11% behind the early plan and the late plan, respectively.

 

Details of the tasks are provided hereunder:

No. Activity Status
A 3A Bang Sue-Rangsit and 3B Bang Sue-Taling Chan
1 Engineering Work
1.1 Railway Track  
Production, preparation, and submission of design details In progress
Production and submission of revised information for approval In progress
Production, preparation, and submission of testing steps In progress
Production, preparation, and submission of field testing steps In progress
1.2 Electrical System
1.2.1 Design of Overhead Catenary System (OCS)
Preparation of information, preliminary design, and submission of revised information for approval In progress
Production and submission of revised information for approval In progress
Production, preparation, and submission of testing steps In progress
1.2.2 Design of Power Supply and Distribution System (PDS)
Preparation of information, preliminary design, and submission of revised information for approval In progress
Production and submission of revised information for approval In progress
Production, preparation, and submission of testing steps In progress
1.3 Railway Signaling and Control Systems
1.3.1 Operation Control Center (OCC) and Centralized Traffic Control (CTC) system  
Production and submission of revised information for approval In progress
1.3.2 Computer Based Interlocking (CBI)  
Production and submission of revised information for approval In progress
     
1.3.3 Automatic Train Protection (ATP) and Automatic Train Operation (ATO)  
Preparation and submission of information and preliminary design In progress
Production and submission of revised information for approval In progress
1.3.4 Wayside Equipment (Signal)  
Preparation and submission of information and preliminary design In progress
Preparation of information, preliminary design, and submission of revised information for approval In progress
Production, preparation, and submission of design details In progress
Production and submission of revised information for approval In progress
1.4 Telecommunication System
1.4.1 Design of Data Transmission System (DTS)  
Production and submission of revised information for approval In progress
Production, preparation, and submission of testing steps In progress
1.4.2 Design of Radio System  
Preparation of information, preliminary design, and submission of revised information for approval In progress
Production, preparation, and submission of testing steps In progress
1.4.3 Design of  Master Clock (MC) System  
Production and submission of revised information for approval In progress
Production, preparation, and submission of testing steps In progress
1.4.4 Design of CCTV System  
Production and submission of revised information for approval In progress
Production, preparation, and submission of testing steps In progress
1.4.5 Design of Passenger Information Display System (PIDS)  
Production and submission of revised information for approval In progress
Production, preparation, and submission of testing steps In progress
1.4.6 Design of Public Address (PA) System  
Production and submission of revised information for approval In progress
Production, preparation, and submission of testing steps In progress
1.4.7 Design of Station Management System (SMS)  
Production and submission of revised information for approval In progress
Production, preparation, and submission of testing steps In progress
1.4.8 Design of Train-Borne Communication System (TCS)  
Production and submission of revised information for approval In progress
Production, preparation, and submission of testing steps In progress
1.4.9 Design of Telephone System  
Production and submission of revised information for approval In progress
Production, preparation, and submission of testing steps In progress
1.5 Automatic Fare Collection (AFC) System
Production and submission of revised information for approval In progress
Production, preparation, and submission of testing steps In progress
1.6 Depot Machinery and Equipment
1.6.1 Design of LD Train Depot Machinery and Equipment
Production, preparation, and submission of design details In progress
1.6.2 Design of CT Depot Machinery and Equipment  
Preparation of information, preliminary design, and submission of revised information for approval In progress
Production, preparation, and submission of design details In progress
Production and submission of revised information for approval In progress
1.7 Other Systems
1.7.1 Design of Control Access Security System (CASS)  
Production and submission of revised information for approval In progress
1.7.2 Design of Operation Automation and Information Technology System (OA&IT)  
Production and submission of revised information for approval In progress
1.8 Design of Train Car Body
Preparation of information, preliminary design, and submission of revised information for approval In progress
Production and preparation of design details In progress
Production and submission of revised information for approval In progress
1.9 Construction Planning and Design
Production of preliminary design of electric power substation and submission of revised design for approval In progress
2 Procurement of Manufacturers
2.1 Railway Track
Manufacturer examination and railway testing In progress
Railway track transport In progress
Railway transport to the LD Train Depot construction site In progress
Railway transport to the CT Depot construction site In progress
Manufacturer examination and track fastener testing In progress
Track fastener transport In progress
Track fastener transport to the LD Train Depot construction site In progress
Track fastener transport to the CT Depot construction site In progress
Manufacturer examination and ballast stone testing In progress
Ballast stone transport In progress
Manufacturer examination and testing of railway turnouts, expansion joints, compromise rails In progress
Manufacturer examination and rubber pad testing In progress
Rubber pad transport In progress
Preparation of information, manufacturer examination and testing, negotiation, and contract signing In progress
Manufacturer examination and testing for provision of concrete sleepers for ballastless track system In progress
Transport of concrete sleepers for ballastless track system In progress
Transport of concrete sleepers for ballastless track system to the North Line N2 construction site In progress
  Manufacturer examination and testing for provision of concrete sleepers for ballasted track system In progress
  Transport of concrete sleepers for ballasted track system In progress
2.2 Electrical System
2.2.1 Overheard Catenary System (OCS)  
Manufacturer examination and testing of Overheard Catenary System (OCS) columns and beams In progress
Manufacturer examination and testing of signal cables In progress
Manufacturer examination and testing for associated works In progress
Preparation of information, manufacturer examination and testing, negotiation, and contract signing for provision of associated OCS works In progress
  Order processing for associated OCS works In progress
  Manufacturer examination and testing for associated OCS works In progress
2.2.2 Manufacturer examination and 115-kV GISS system testing In progress
Manufacturer examination and 115/25-kV traction transformer testing In progress
Manufacturer examination and 115/24-kV power transformer testing In progress
Manufacturer examination and 25-kV Gas-insulated Switchgear (GIS) testing In progress
Manufacturer examination and 24-kV Switchgear testing In progress
Manufacturer examination and 25-kV Auto Transformer testing In progress
Manufacturer examination and 25-kV AT Switching Station testing In progress
Manufacturer examination and 24/0.4-kV Dry-type Transformer testing In progress
Preparation of information, manufacturer examination and testing, negotiation, and contract signing for provision of 400V emergency diesel generator In progress
Order processing for 400V emergency diesel generator In progress
Manufacturer examination and 400V emergency diesel generator testing In progress
Preparation of information, manufacturer examination and testing, negotiation, and contract signing for provision of power cables In progress
Power cable order processing In progress
  Manufacturer examination and power cable testing In progress
2.2.3 Supervisory Control and Data Acquisition (SCADA)  
Manufacturer examination and SCADA testing In progress
Preparation of information, manufacturer examination and testing, negotiation, and contract signing for provision of cables In progress
  SCADA order processing In progress
  Manufacturer examination and SCADA equipment testing In progress
2.3 Railway Signaling and Control Systems  
2.3.1 Centralized Traffic Control (CTC) system
Manufacturer examination and CTC system testing In progress
2.3.2 Computer Based Interlocking (CBI)
Manufacturer examination and CBI testing In progress
2.4 Telecommunication System
2.4.1 Design of Data Transmission System (DTS)
Manufacturer examination and DTS testing In progress
2.4.2 Design of Radio System  
Manufacturer examination and radio system testing In progress
2.4.3 Design of Master Clock (MC) System  
Manufacturer examination and MC system testing In progress
2.4.4 Design of CCTV System  
Manufacturer examination and CCTV system testing In progress
2.4.5 Design of Passenger Information Display System (PIDS)
Manufacturer examination and PIDS testing In progress
2.4.6 Design of Public Address (PA) System  
Manufacturer examination and PA system testing In progress
2.4.7 Design of Station Management System (SMS)  
Manufacturer examination and SMS testing In progress
2.4.8 Design of Train-Borne Communication System (TCS)  
Manufacturer examination and TCS testing In progress
2.4.9 Design of Telephone System  
Manufacturer examination and telephone testing In progress
2.5 Automatic Fare Collection (AFC) System
Preparation for system procurement, manufacturer examination and testing In progress
2.6 Depot Machinery and Equipment
2.6.1 Design of LD Train Depot Machinery and Equipment
Preparation of information, manufacturer examination and testing, negotiation, and contract signing In progress
2.6.2 CT Depot Machinery and Equipment  
Preparation for procurement, manufacturer examination, and testing In progress
2.7 Other Associated Systems, including Control Access Security System (CASS), Operation Automation and Information Technology System (OA&IT)
Preparation for procurement, manufacturer examination, and testing In progress
2.8 Train Car Body
2.8.1 Agent procurement, negotiation, and contract signing for train car body In progress
Preparation of information, manufacturer examination and testing, and negotiation for train car body In progress
Agent procurement, negotiation, and contract signing for heating, ventilation, and air conditioning (HVAC) In progress
Preparation of information, manufacturer examination and testing, and negotiation for heating, ventilation, and air conditioning (HVAC) In progress
Preparation of information, manufacturer examination and testing, negotiation, and contract signing for train In progress
Preparation of coupler and drive construction standard In progress
Preparation of entrance system construction standard In progress
Agent procurement, negotiation, and contract signing for traction transformer In progress
Preparation of information, manufacturer examination and testing, and negotiation for traction transformer In progress
Agent procurement, negotiation, and contract signing for traction converter In progress
Preparation of information, manufacturer examination and testing, and negotiation for traction converter In progress
Agent procurement, negotiation, and contract signing for traction motor In progress
Preparation of information, manufacturer examination and testing, and negotiation for traction motor In progress
Preparation of pantograph construction standard In progress
Agent procurement, negotiation, and contract signing for APS output transformer box In progress
Preparation of information, manufacturer examination and testing, and negotiation for APS output transformer box In progress
Agent procurement, negotiation, and contract signing for train integrated management system (TIMS) In progress
Preparation of information, manufacturer examination and testing, and negotiation for train integrated management system (TIMS) In progress
Preparation of information, manufacturer examination and testing, and negotiation for brake and air distribution system In progress
2.9 Construction Machinery and Tools
Manufacturer examination and testing In progress
3 Construction and Installation Work
3.1 Railway Track
3.1.1 General Requirements for the North Lines  
N2 (12+201 to 24+826)  
N2-A (12+201-18+000): Preparation for construction work and equipment (12+201-18+000) In progress
3.1.2 N3 (24+826-32+500)  
  N2-A (24+826 to 29+230): Flash butt welding (24+826 - 29+230 (32+500) In progress

 

Summary Table of Construction Plan and Progress of Contract 3 for March 2018

 


 
 