Construction Supervision of Mass Transit System Project in Bangkok (Red Line) Bang Sue-Rangsit Section
Main Menu About the Project Project Development Public Relations Contact
Public Relations
Progress
Activity Photos

 

  Progress
 

 

Project Progress as of April 2016

 

Contract 1

    Accumulative progress of complete task is 42.27% from the planned target of 72.66%, or 30.39% behind the schedule.

Details of the tasks are provided hereunder:

No. Activity Status
1 Elevated and at Grade Railways Work
  Testing of 3 pilot piles (diameter = 1,500 mm) (at Terd Damri Road at MRTA parking and at local road near Samian Nari Temple). Completed
  Testing of pilot piles (diameter = 1,200 mm) at the Bang Sue Grand Station construction site. Completed
  Testing of pilot piles (diameter = 800 mm) at the road flyover construction site. Completed
  Pile testing of the existing Hopewell structures at the local road construction site near Samian Nari Temple. Completed
  Demolition of 237 Hopewell’s structural columns (Type 1A Case 1 = 65 columns/ Type 2A, 2B Case 1 = 11 columns/ Type 3A, 3B Case 1 = 60 columns/ Type 4 Case 1 = 5 columns/ Type 12 Case 2 = 29 columns/ Type 13 Case 2 = 32 columns/ Type 14 Case 3 = 32 columns/ Type 15 Case 3 = 3 columns) Completed
  Installed 200 (diameter = 1,000 mm) bored piles for the elevated structures. Completed
  Installed 252 (diameter = 1,200 mm) bored piles for the elevated structures. Completed
  Installed 2,008 from 2,009 bored piles (diameter = 1,500 mm) for the elevated structures. In operation
  Installed 364 from 366  bored piles (diameter = 2,000 mm) for the elevated structures. In operation
  Installed 9 barrette piles (diameter = 1,000x3,000 mm) for the elevated structures. Completed
  Concrete pouring of 684 footings from the target of 698 footings for elevated railway In operation
  Installed columns for the elevated structures In operation
  Installed beams for the elevated structures In operation
  Installed main pre-cast concrete compotents of the elevated rail track In operation
  Demolition of premises. In operation
  Relocation of infrastructural systems, i.e. electricity posts, telegraph posts, etc. In operation
  Removal of concrete surface. Completed
2 Station Work
  Land excavation of 254,496 cu.m from the target of 293,314 cu.m for foundation works of the Grand Station. In operation
  Installed 573 from 623 bored piles (diameter = 800 mm) at the Bang Sue Grand Station construction site. In operation
  Installed 1,013  from 1,232 bored piles (diameter = 1,000 mm) (including piles for approach) at the Bang Sue Grand Station construction site. In operation
  Installed 253 from 257 bored piles (diameter = 1,200 mm) at the Bang Sue Grand Station construction site. In operation
  Installed 1,706 bored piles (diameter = 1,500 mm) at the Bang Sue Grand Station construction site. Completed
  Installed 116 from 123 bored piles (diameter = 2,000 mm) at the Bang Sue Grand Station construction site. In operation
  Lean concrete pouring of 138 from 160 footings at the Bang Sue Grand Station construction site. In operation
  Concrete pouring (Type F1A) of  523 from 632 footings at the Bang Sue Grand Station construction site. In operation
  Installed structural columns and beams at the Bang Sue Grand Station construction site. In operation
  Installed concrete components of elevated structures. In operation
  Foundation and wall concrete pouring for the basement of the Bang Sue Grand Station construction site In operation
  Removal of railway tracks at the Bang Sue Grand Station construction site. Completed
  Installed 88 bored piles (diameter = 2,000 mm) at the Chatuchak Station construction site. Completed
  Installed 26 bored piles (diameter = 1,000 mm) at the Chatuchak Station construction site. Completed
  Foundation concrete pouring of 22 footings at the Chatuchak Station construction site. Completed
3 LD Train Maintenance Depot Work
  Installed 1,426 driven piles (0.40x0.40 m) and construction of 234 bored piles (diameter 0.50 m) at the Daily Maintenance construction site. Completed
  Finished 709 footings at the Daily Maintenance construction site. Completed
  Installed 4,991 structural columns at the Daily Maintenance construction site. Completed
  Installed pre cast beams at the Daily Maintenance construction site. In operation
  Concrete pouring at the Daily Maintenance construction site. In operation
  Installed steel columns and roof structures at the Daily Maintenance construction site. In operation
  Wall concrete pouring and plastering at the Daily Maintenance construction site. In operation
  Installed 1,535 from 1,596 driven piles (0.40x0.40 m) at the Passenger Coach construction site. In operation
  Finished 250 footings at the Passenger Coach construction site. Completed
  Installed steel columns and roof structures at the Passenger Coach construction site. In operation
4 CT Train Maintenance Depot Work
  Installed 1,559 driven piles (0.40x0.40 m) at the Main Workshop construction site. Completed
  Finished 315 from 328 footings at the Main Workshop construction site. In operation
  Installed 266 structural columns at the Main Workshop construction site. In operation
  Installed pre cast beams and concrete pouring at the Main Workshop construction site. In operation
  Installed steel columns at the Main Workshop construction site. In operation
  Installed 582 driven piles (0.40x0.40 m) at the Infrastructure Workshop construction site. Completed
  Finished 244 footings at the Infrastructure Workshop construction site. Completed
  Installed 244 structural columns at the Infrastructure Workshop construction site. Completed
  Installed pre cast beams at the Infrastructure Workshop construction site. Completed
  Installed columns and roof structures at the Infrastructure Workshop construction site. In operation
  Installed culverts at the Infrastructure Workshop construction site. In operation
  Installed pre cast slabs and wall concrete pouring at the Infrastructure Workshop construction site. In operation
  Installed 8 driven piles (0.30x0.30 m) at the Hazardous Material Store construction site. Completed
  Installed 17 driven piles (0.30x0.30 m) at the Signaling and Communications building construction site. Completed
  Installed 36 driven piles (0.30x0.30 m) at the Train Operators and Cleaners construction site. Completed
  Installed 48 driven piles (0.35x0.35 m) at the Wheel Reprofiling Plant construction site. Completed
  Installed 1,796 from 2,384 driven piles (0.18x0.18 m) at the Train Stabling construction site. In operation
  Finished 741 from 1,168 footings at the Train Stabling construction site. In operation
  Installed 1,234 from 2,384 structural columns at the Train Stabling construction site. In operation
  Installed platforms at the Train Stabling construction site. In operation
5 Local Road and Road Flyover Work
  Earth filling work forlocal road. In operation
  Installed 816 driven piles (0.22x0.22 m) for road flyover. Completed
  Installed 306 driven piles (0.26x0.26 m) for road flyover. Completed
  Installed 282 bored piles (diameter = 0.80 m). Completed
  Finished 33 footings for road flyover. Completed
  Installed 33 structural columns for road flyover. Completed
  Installed 33 beams for road flyover. Completed
  Installed I-Girders for road flyover. Completed
  Installed U-ditches at the construction site In operation

 

 

Summary Report of The Execution of Contract 1 for April 2016

Contract 1 : Civil Works for Bang Sue Grand Station and Depots
Bill No. Description Contract Amount (BahT) % Progress as of
25-APRIL-16
Status
planned actual
1 General Requirements 266,482,434 80.14% 78.34% -1.80%
2 Track work 11,422,571,521 76.17% 46.53% -29.64%
3 Stations 14,247,067,853 63.06% 33.94% -29.12%
4 LD-Train Depots and CT-Train Depots 1,604,023,818 98.91% 84.55% -14.36%
5 Local Road and Road Flyover 1,410,141,074 99.75% 44.89% -54.85%
6 Provisional Sums and Provisional Items 672,130,000 94.34% 26.69% -67.65%
7 Day-Work Schedule 17,823,300 61.54% 0.00% -61.54%
Total 29,640,240,000 72.66% 42.27% -30.39%

 

 

Summary Table of Construction Plan and Progress of Contract 1 for April 2016

 

 

Contract 2

         Accumulative progress of complete task is 61.49% from the planned target of 99.83%, or 38.34% behind the schedule.

Details of the tasks are provided hereunder:

No. Activity Status
1 Elevated and at Grade Railways Work
  Demolition of Hopewell’s 553 structural columns
(Type 1 Case 1 = 1 column, Type 1A Case 1 = 31 columns, Type 2A Case 1 = 5 columns, Type 2B  Case 1 = 1 column, Type 3A Case 1 = 83 columns, Type 4 Case 1 = 18 columns, Type 6 Case 1 = 1 column, Type 5A Case 2 = 3 columns, Type 5B Case 2 = 1 column, Type 7 Case 2 = 7 columns, Type 8 Case 2 = 75 columns, Type 9 Case 2 = 10 columns, Type 10 Case 2 = 6 columns, Type 11 Case 2 = 84 columns, Type 14 Case 3 = 138 columns, Type 15 = 6 columns, Type 16 Case 2 = 42 columns, Type 16A Case 2 = 18 columns, Type 16B Case 2 = 9 columns, Type 18 Case 2 = 11 columns, Type 19 Case 2 = 3 columns).
Completed
  Testing work of pilot pile (diameter = 1,500 mm) in 4 areas: 1) Lak Si area (Sta. 17+500), 2) Near Don Muang District Office (Sta. 20+600), 3) Near the entrance of Grand Canal Village (Sta. 24+600), and 4) at Rangsit Railway Station (Sta. 29+800). Completed
  Testing work of pilot pile (diameter = 1,200 mm) near the entrance of Grand Canal Village (Sta. 24+600). Completed
  Pile testing of the existing Hopewell structures at local road near Chulabhorn Research Institute (CRI). Completed
  Installed 2,040 bored piles (diameter = 1.2, 1.5, and 1.8 m) for elevated railway. Completed
  Installed 86 barrette piles (diameter = 1,000x3,000 mm.) for elevated railway. Completed
  Finished 677 footings for elevated railway Completed
  Installed 838 from 875 structural columns for elevated railway. In operation
  Installed 405 from 428 cross beams for the elevated structures. In operation
  Installed 6,175 from 14,303 segments for elevated railway. In operation
  Installed 2,443 driven piles (0.35x0.35 m) at Sta. 24+830 to Sta. 25+152. Completed
  Installed 24,721 driven piles (0.22x0.22 m) at Sta. 25+210 to Sta. 28+900. Completed
  Earth filling, sand embankment and subballast for at-grade railway track. In operation
  Reinforced concrete work for at-grade railway track. In operation
2 Station Work
  Demolition of existing railway stations (Bang Khen and Lak Si). Completed
  Installed 66 bored piles (diameter = 1,500 mm) and 44 barrette piles at Samian Nari Temple Station. Completed
  Finished 22 footings for elevated railway at Samian Nari Temple Station. Completed
  Installed 44 structural columns for elevated railway at Samian Nari Temple Station. Completed
  Installed 21 cross beams for elevated railway at Samian Nari Temple Station. Completed
  Installed I-Girders for elevated railway at Samian Nari Temple Station. Completed
  Concrete pouring for construction of ticket hall floor  at Samian Nari Temple Station. Completed
  Installed aerated concrete walls on ticket hall floor  at Samian Nari Temple Station. In operation
  Installed roof structures at Samian Nari Temple Station. In operation
  Installed 66 bored piles (diameter = 1,500 mm) and 44 barrette piles at Bang Khen Station. Completed
  Finished 22 footings for elevated railway at Bang Khen Station. Completed
  Installed 44 structural columns for elevated railway at Bang Khen Station. Completed
  Installed 21 cross beams for elevated railway at Bang Khen Station. Completed
  Installed I-Girders for elevated railway at Bang Khen Station. Completed
  Concrete pouring for construction of ticket hall floor  at Bang Khen Station. Completed
  Installed aerated concrete walls on ticket hall floor  at Bang Khen Station. In operation
  Installed roof structures at Bang Khen Station. Completed
  Installed elevators and escalators at Bang Khen Station. In operation
  Installed 66 bored piles (diameter = 1,500 mm) and 44 barrette piles at Thung Song Hong Station. Completed
  Finished 22 footings for elevated railway at Thung Song Hong Station. Completed
  Installed 44 structural columns for elevated railway at Thung Song Hong  Station. Completed
  Installed 21 cross beams for elevated railway at Thung Song Hong Station. Completed
  Installed I-Girders for elevated railway at Thung Song Hong Station. Completed
  Concrete pouring for construction of ticket hall floor  at Thung Song Hong Station. Completed
  Installed aerated concrete walls on ticket hall floor  at Thung Song Hong Station. In operation
  Installed roof structures at Thung Song Hong Station. Completed
  Installed elevators and escalators at Thung Song Hong Station. In operation
  Installed 132 bored piles (diameter = 1,500 mm) at Lak Si Station. Completed
  Finished 22 footings for elevated railway at Lak Si Station. Completed
  Installed 44 structural columns for elevated railway at Lak Si Station. Completed
  Installed of 21 cross beams for elevated railway at Lak Si Station. Completed
  Installed I-Girders for elevated railway at Lak Si Station. Completed
  Concrete pouring for construction of ticket hall at Lak Si Station. In operation
  Installed 128 bored piles (diameter = 1,500 mm) (including 4 existing Hopewell structures (total 132 structures) at Kan Kheha Station. Completed
  Finished 22 footings for elevated railway at Kan Kheha Station. Completed
  Installed 44 structural columns for elevated railway at Kan Kheha Station. Completed
  Installed  21 cross beams for elevated railway at Kan Kheha Station. Completed
  Installed I-Girders for elevated railway at Kan Kheha Station. Completed
  Concrete pouring for construction of ticket hall floor  at Kan Kheha Station. Completed
  Installed roof structures at Kan Kheha Station. Completed
  Installed elevators and escalators at Kan Kheha Station. In operation
  Installed 171 barrette piles at Don Muang Station. Completed
  Finished 34 footings for elevated railway at Don Muang Station. Completed
  Installed 102 structural columns for elevated railway at Don Muang Station. Completed
  Installed 51 cross beams for elevated railway at Don Muang  Station. Completed
  Installed I-Girders for elevated railway at Don Muang  Station. In operation
  Installed 108 bored piles (diameter = 1,000 mm) at Lak Hok Station. Completed
  Finished 18 footings for elevated railway at Lak Hok Station. Completed
  Installed 18 structural columns for elevated railway at Lak Hok Station. Completed
  Installed 9 cross beams for elevated railway at Lak Hok Station. Completed
  Installed I-Girders for elevated railway at Lak Hok Station. Completed
  Concrete pouring for construction of ticket hall floor  at Lak Hok Station. In operation
  Installed 470 bored piles (diameter = 1,500 mm) at Rangsit Station. Completed
  Finished 50 footings for elevated railway at Rangsit Station. Completed
  Installed 144 structural columns for elevated railway at Rangsit Station. Completed
  Installed 28 cross beams for elevated railway at Rangsit Station. Completed
  Installed I-Girders for elevated railway at Rangsit Station. In operation
  Concrete pouring for construction of ticket hall at Rangsit Station. In operation
3 Local Road and Road Flyover Work
  Construction of 528 driven piles (0.22 x 0.22 m and 0.26 x 0.26 m) for road flyover from Sta. 25+201 to Sta. 25+253. Completed
  Installed 122 bored piles for road flyover (diameter = 800 mm). Completed
  Foundation work of 14 footings for road flyover at Sta. 24+910. Completed
  Installed 14 structural columns for road flyover at Sta. 24+910. Completed
  Installed substructure for road flyover at Sta. 24+910. Completed
  Installed superstructure for road flyover at Sta. 24+910. Completed
  Installed 594 driven piles (0.22 x 0.22 m and 0.26 x 0.26 m) for road flyover at Sta. 27+650. Completed
  Installed 66 bored piles (diameter = 800 mm) for road flyover at Sta. 27+650. Completed
  Finished 7 footings for road flyover at Sta. 27+650. Completed
  Installed 7 structural columns for road flyover at Sta. 27+650. Completed
  Installed substructure for road flyover at Sta. 27+650. Completed
  Installed superstructure for road flyover at Sta. 27+650. Completed
  Earth filling work for local road In operation
  Construction of drainage system for local road In operation

 

 

Summary Report of The Execution of Contract 2 for April 2016

Contract 2 : Civil Works for Bang Sue - Rangsit Railway
Bill No. Description Contract Amount (BahT) % Progress as of
25-APRIL-16
Status
planned actual
1 General Requirements 272,629,120 86.77% 82.21% -4.56%
2 Track work 10,514,931,561 100.00% 69.12% -30.88%
3 Stations 8,558,445,112 100.00% 53.13% -46.87%
4 Local Road and Road Flyover 1,264,542,043 100.00% 46.20% -53.80%
5 Provisional Sums and Provisional Items - - - -
Total 20,610,547,836 99.83% 61.49% -38.34%

 

 

Summary Table of Construction Plan and Progress of Contract 2 for April 2016

 
 
โครงการระบบรถไฟชานเมือง (สายสีแดง) ช่วงบางซื้อ-รังสิต