Construction Supervision of Mass Transit System Project in Bangkok (Red Line) Bang Sue-Rangsit Section
Main Menu About the Project Project Development Public Relations Contact
Public Relations
Progress
Activity Photos

 

  Progress
 

 

Project Progress as of April 2018

 

Contract 1

         Accumulative progress of complete task is 69.18% from the planned target of 70.54%, or 1.36% behind the schedule.

         Details of the tasks are provided hereunder:

 
No. Activity Status
1 Elevated and at Grade Railway Work
  Installed 2,723 from 2,749 beams for the structure of the elevated rail track In operation
  Installed 504 from 932 main precast concrete spans of the elevated rail track In operation
  Demolition of premises In operation
  Relocation of infrastructural systems, i.e. electricity posts, telegraph posts, etc. In operation
2 Stations
  Concrete pouring (Type F1A) of 690 from 753 footings at the Bang Sue Grand Station construction site In operation
  Installed 269 from 305 main precast concrete spans of the elevated rail track at the Bang Sue Grand Station construction site In operation
  Ground and wall concrete pouring for the basement of the Bang Sue Grand Station construction site In operation
  Concrete pouring on ticket hall and platform floors at the Bang Sue Grand Station construction site In operation
  Installed steel roof structure at the Bang Sue Grand Station construction site In operation
  Installed aerated concrete walls on ticket hall floor the Bang Sue Grand Station construction site In operation
3 LD Train Maintenance Depot Work
  Interior finishing at the Daily Maintenance Building construction site In operation
  Concrete pouring at the Carriage Shop Building construction site In operation
  Interior finishing at the Passenger Coach Building construction site In operation
4 CT Maintenance Depot Work
  Interior finishing at the Main Workshop construction site In operation
  Interior finishing at the Infrastructure Workshop construction site In operation
  Installed platforms at the Train Stabling construction site In operation
5 Local Road and Road Flyover Work
  Earth filling work for local road In operation
  Installed U-ditches at the construction site In operation

 

 

Summary Report of the Execution of Contract 1 for April 2018 (Early Plan)

Contract 1: Civil Works for Bang Sue Grand Station and Depots
Bill No. Description Contract Amount (Baht) % Progress as of 25 April 2018 Status
planned actual
1 General Requirements 266,482,434 100.00% 97.89% -2.11%
2 Track Work 11,422,571,521 100.00% 99.89% -0.11%
3 Stations 14,247,067,853 100.00% 59.17% -40.83%
4 LD Train Depots and CT Depots 1,604,023,818 100.00% 87.23% -12.77%
5 Local Road and Road Flyover 1,410,141,074 100.00% 70.54% -29.46%
6 Provisional sums and Provisional Items 672,130,000 100.00% 18.59% -81.41%
7 Day-Work Schedule 17,823,300 100.00% 0.00% -100.00%
Total 29,640,240,000 100.00% 79.28% -20.72%

 

Summary Report of the Execution of Contract 1 for April 2018 (Late Plan)

Contract 1: Civil Works for Bang Sue Grand Station and Depots
Bill No. Description Contract Amount (Baht) % Progress as of 25 April 2018 Status
planned actual
1 General Requirements 266,482,434 98.03% 97.89% -0.14%
2 Track Work 12,127,119,738 86.51% 94.09% 7.58%
3 Stations 16,823,702,974 59.45% 50.11% -9.34%
4 LD Train Depots and CT Depots 1,604,023,818 100.00% 87.23% -12.77%
5 Local Road and Road Flyover 2,393,497,138 53.88% 41.56% -12.32%
6 Provisional sums and Provisional Items 672,130,000 39.44% 18.59% -20.85%
7 Day-Work Schedule 17,823,300 17.39% 0.00% -17.39%
Total 33,904,779,402 70.54% 69.31% -1.23%

 

 

 Summary Table of Construction Plan and Progress of Contract 1 for April 2018

 

 

Contract 2

       Accumulative progress of complete task is 97.94% from the planned target of 99.77%, or 1.83% behind the schedule

Details of the tasks are provided hereunder:

No. Activity Status
1 Elevated and at Grade Railway Work
  Installed 14,303 from 14,303 segments for elevated railway Completed
  Installation of boundary fences In operation
2 Station Work
  Interior finishing at Wat Samian Nari Station In operation
  Installed elevators and escalators at Wat Samian Nari Station In operation
  Installed electricity and mechanical systems at Wat Samian Nari Station In operation
  Interior finishing at Bang Khen Station In operation
  Installed elevators and escalators at Bang Khen Station In operation
  Installed electricity and mechanical systems at Bang Khen Station In operation
  Interior finishing at Thung Song Hong Station In operation
  Installed electricity and mechanical systems at Thung Song Hong Station In operation
  Installed elevators and escalators at Thung Song Hong Station In operation
  Interior finishing at Lak Si Station In operation
  Installed electricity and mechanical systems at Lak Si Station In operation
  Installed elevators and escalators at Lak Si Station In operation
  Interior finishing at Kan Kheha Station In operation
  Installed electricity and mechanical systems at Kan Kheha Station In operation
  Installed elevators and escalators at Kan Kheha Station In operation
  Concrete pouring for construction of ticket hall floor at Don Mueang Station In operation
  Installed steel roof structure at Don Mueang Station In operation
  Installed steel structure for entrance staircases at Don Mueang Station In operation
  Installed electricity and mechanical systems at Don Mueang Station In operation
  Installed elevators and escalators at at Don Mueang Station In operation
  Installed electricity and mechanical systems at Lak Hok Station In operation
  Installed elevators and escalators at Lak Hok Station In operation
  Installed steel structure for entrance staircases at Rangsit Station In operation
  Installed electricity and mechanical systems at Rangsit Station In operation
  Installed elevators and escalators at Rangsit Station In operation
3 Local Road and Road Flyover Work
  Local road construction In operation
  Construction of drainage system for local road In operation

 

 

Summary Report of the Execution of Contract 2 for April 2018

Contract 2: Civil Works for Bang Sue-Rangsit Railway
Bill No. Description Contract
Amount (Baht)
% Progress as of 25 April 2018 Status
planned actual
1 General Requirements 272,629,119 99.76% 97.86% -1.90%
2 Track Work 12,431,497,987 100.00% 99.82% -0.18%
3 Stations 9,957,755,499 99.46% 96.12% -3.34%
4 Local Road and Road Flyover 1,263,337,028 99.92% 93.69% -6.24%
5 Provisional Sums and Provisional Items - - - -
Total 23,925,219,633 99.77% 97.94% -1.83%

 

 

 Summary Table of Construction Plan and Progress of Contract 2 for April 2018

Contract 3

Accumulative progress of complete task is 26.71% from the planned target of 51.90% (early plan) and of 43.41% (late plan), or 25.19% and 16.70% behind the early plan and the late plan, respectively.

 

Details of the tasks are provided hereunder:

No. Activity Status
A 3A Bang Sue-Rangsit and 3B Bang Sue-Taling Chan
1 Engineering Work
1.1 Railway Track  
  Production, preparation, and submission of design details In progress
  Production and submission of revised information for approval In progress
  Production, preparation, and submission of testing steps In progress
  Production, preparation, and submission of field testing steps In progress
1.2 Electrical System
1.2.1 Design of Overhead Catenary System (OCS)  
  Preparation of information, preliminary design, and submission of revised information for approval Completed
  Production and submission of revised information for approval In progress
  Production, preparation, and submission of testing steps In progress
1.2.2 Design of Power Supply and Distribution System (PDS)  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production and submission of revised information for approval In progress
  Production, preparation, and submission of testing steps In progress
1.3 Railway Signaling and Control Systems
1.3.1 Operation Control Center (OCC) and Centralized Traffic Control (CTC) system  
  Production and submission of revised information for approval In progress
1.3.2 Computer Based Interlocking (CBI)  
  Production and submission of revised information for approval In progress
1.3.3 Automatic Train Protection (ATP) and Automatic Train Operation (ATO)  
  Preparation and submission of information and preliminary design In progress
  Production and submission of revised information for approval In progress
1.3.4 Wayside Equipment (Signal)  
  Preparation and submission of information and preliminary design In progress
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
  Production and submission of revised information for approval In progress
1.4 Telecommunication System
1.4.1 Design of Data Transmission System (DTS)  
  Production and submission of revised information for approval In progress
  Production, preparation, and submission of testing steps In progress
1.4.2 Design of Radio System  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of testing steps In progress
1.4.3 Design of  Master Clock (MC) System  
  Production and submission of revised information for approval In progress
  Production, preparation, and submission of testing steps In progress
1.4.4 Design of CCTV System  
  Production and submission of revised information for approval In progress
  Production, preparation, and submission of testing steps In progress
1.4.5 งานออกแบบระบบ Passenger Information Display System (PIDS)   
  Design of Passenger Information Display System (PIDS) In progress
  Production and submission of revised information for approval In progress
1.4.6 Design of Public Address (PA) System  
  Production and submission of revised information for approval In progress
  Production, preparation, and submission of testing steps In progress
1.4.7 Design of Station Management System (SMS)  
  Production and submission of revised information for approval In progress
  Production, preparation, and submission of testing steps In progress
1.4.8 Design of Train-Borne Communication System (TCS)  
  Production and submission of revised information for approval In progress
  Production, preparation, and submission of testing steps In progress
1.4.9 Design of Telephone System  
  Production and submission of revised information for approval In progress
  Production, preparation, and submission of testing steps In progress
1.5 Automatic Fare Collection (AFC) System
  Production and submission of revised information for approval In progress
  Production, preparation, and submission of testing steps In progress
1.6 Depot Machinery and Equipment
1.6.1 Design of LD Train Depot Machinery and Equipment  
  Production, preparation, and submission of design details In progress
1.6.2 Design of CT Depot Machinery and Equipment  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details Completed
  Production and submission of revised information for approval In progress
1.7 Other Systems
1.7.1 Design of Control Access Security System (CASS)  
  Production and submission of revised information for approval In progress
1.7.2 Design of Operation Automation and Information Technology System (OA&IT)  
  Production and submission of revised information for approval In progress
1.8 Design of Train Car Body
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production and preparation of design details In progress
  Production and submission of revised information for approval In progress
1.9 Construction Planning and Design
  Production of preliminary design of electric power substation and submission of revised design for approval In progress
2 Procurement of Manufacturers
2.1 Railway Track
  Manufacturer examination and railway testing In progress
  Railway track transport In progress
  Railway transport to the LD Train Depot construction site Completed
  Railway transport to the CT Depot construction site Completed
  Manufacturer examination and track fastener testing In progress
  Track fastener transport In progress
  Track fastener transport to the North Line N1 construction site In progress
  Track fastener transport to the LD Train Depot construction site Completed
  Track fastener transport to the CT Depot construction site Completed
  Manufacturer examination and ballast stone testing In progress
  Ballast stone transport In progress
  Manufacturer examination and testing of railway turnouts, expansion joints, and compromise rails In progress
  Manufacturer examination and rubber pad testing In progress
  Rubber pad transport In progress
  Preparation of information, manufacturer examination and testing, negotiation, and contract signing In progress
  Manufacturer examination and testing for provision of concrete sleepers for ballastless track system In progress
  Transport of concrete sleepers for ballastless track system In progress
  Transport of concrete sleepers for ballastless track system to the North Line N2 construction site Completed
  Manufacturer examination and testing for provision of concrete sleepers for ballasted track system In progress
  Transport of concrete sleepers for ballasted track system In progress
2.2 Electrical System
2.2.1 Overhead Catenary System (OCS)  
  Manufacturer examination and testing of Overhead Catenary System (OCS) columns and beams In progress
  Manufacturer examination and testing of signal cables In progress
  Manufacturer examination and testing for associated works In progress
  Preparation of information, manufacturer examination and testing, negotiation, and contract signing for provision of associated OCS works Completed
  Order processing for associated OCS works Completed
  Manufacturer examination and testing for associated OCS works In progress
2.2.2 Power Supply and Distribution System (PDS)   
  Manufacturer examination and 115-kV GISS system testing In progress
  Manufacturer examination and 115/25-kV traction transformer testing In progress
  Manufacturer examination and 115/24-kV power transformer testing In progress
  Manufacturer examination and 25-kV Gas-insulated Switchgear (GIS) testing In progress
  Manufacturer examination and 24-kV Switchgear testing In progress
  Manufacturer examination and 25-kV Auto Transformer testing In progress
  Manufacturer examination and 25-kV AT Switching Station testing In progress
  Manufacturer examination and 24/0.4-kV Dry-type Transformer testing In progress
  Preparation of information, manufacturer examination and testing, negotiation, and contract signing for provision of 400V emergency diesel generator Completed
  Order processing for 400V emergency diesel generator Completed
  Manufacturer examination and 400V emergency diesel generator testing In progress
  Preparation of information, manufacturer examination and testing, negotiation, and contract signing for provision of power cables Completed
  Power cable order processing Completed
  Manufacturer examination and power cable testing In progress
2.2.3 Supervisory Control and Data Acquisition (SCADA)  
  Manufacturer examination and SCADA testing In progress
  Preparation of information, manufacturer examination and testing, negotiation, and contract signing for provision of cables Completed
  SCADA order processing Completed
  Manufacturer examination and SCADA equipment testing In progress
2.3 Railway Signaling and Control Systems  
2.3.1 Centralized Traffic Control (CTC) system  
  Manufacturer examination and CTC system testing In progress
2.3.2 Computer Based Interlocking (CBI)  
  Manufacturer examination and CBI testing In progress
2.4 Telecommunication System
2.4.1 Design of Data Transmission System (DTS)  
  Manufacturer examination and DTS testing In progress
2.4.2 Design of Radio System  
  Manufacturer examination and radio system testing In progress
2.4.3 Design of Master Clock (MC) System  
  Manufacturer examination and MC system testing In progress
2.4.4 Design of CCTV System  
  Manufacturer examination and CCTV system testing In progress
2.4.5 Design of Passenger Information Display System (PIDS)  
  Manufacturer examination and PIDS testing In progress
2.4.6 Design of Public Address (PA) System  
  Manufacturer examination and PA system testing In progress
2.4.7 Design of Station Management System (SMS)  
  Manufacturer examination and SMS testing In progress
2.4.8 Design of Train-Borne Communication System (TCS)  
  Manufacturer examination and TCS testing In progress
2.4.9 Design of Telephone System  
  Manufacturer examination and telephone testing In progress
2.5 Automatic Fare Collection (AFC) System
  Preparation for system procurement, manufacturer examination and testing In progress
2.6 Depot Machinery and Equipment
2.6.1 Design of LD Train Depot Machinery and Equipment  
  Preparation of information, manufacturer examination and testing, negotiation, and contract signing In progress
2.6.2 CT Depot Machinery and Equipment  
  Preparation for procurement, manufacturer examination, and testing In progress
2.7 Other Associated Systems, including Control Access Security System (CASS), Operation Automation and Information Technology System (OA&IT)
  Preparation for procurement, manufacturer examination, and testing In progress
2.8 Train 
2.8.1 Materials and Equipment   
  Agent procurement, negotiation, and contract signing for train car body Completed
  Preparation of information, manufacturer examination and testing, and negotiation for train car body In progress
  Agent procurement, negotiation, and contract signing for heating, ventilation, and air conditioning (HVAC) Completed
  Preparation of information, manufacturer examination and testing, and negotiation for heating, ventilation, and air conditioning (HVAC) In progress
  Preparation of information, manufacturer examination and testing, negotiation, and contract signing for train In progress
  Preparation of coupler and drive construction standard In progress
  Preparation of entrance system construction standard In progress
  Agent procurement, negotiation, and contract signing for traction transformer Completed
  Preparation of information, manufacturer examination and testing, and negotiation for traction transformer In progress
  Agent procurement, negotiation, and contract signing for traction converter Completed
  Preparation of information, manufacturer examination and testing, and negotiation for traction converter In progress
  Agent procurement, negotiation, and contract signing for traction motor Completed
  Preparation of information, manufacturer examination and testing, and negotiation for traction motor Completed
  Preparation of pantograph construction standard In progress
  Agent procurement, negotiation, and contract signing for APS output transformer box Completed
  Preparation of information, manufacturer examination and testing, and negotiation for APS output transformer box In progress
  Agent procurement, negotiation, and contract signing for train integrated management system (TIMS) Completed
  Preparation of information, manufacturer examination and testing, and negotiation for train integrated management system (TIMS) In progress
  Preparation of information, manufacturer examination and testing, and negotiation for brake and air distribution system In progress
2.9 Construction Machinery and Tools
  Manufacturer examination and testing construction machinery and tools In progress
  Transport of construction machinery and tools In progress
3 Construction and Installation Work
3.1 Railway Track
3.1.1 General Requirements for the North Lines  
  N2 (12+201 to 24+826)  
  N2-A (12+201-18+000): Preparation for construction work and equipment (12+201-18+000) In operation
  N3 (24+826-32+500)  
  N2-A (24+826 to 29+230) : Flash butt welding (24+826 - 29+230 (32+500)) In operation
3.1.2 North Line-Distribution Substation  
  Distribution Substation Construction  
  Pile installation at the construction site of distribution substation In operation

 

Summary Table of Construction Plan and Progress of Contract 3 for April 2018

 


 
 