Project Progress as of May 2017

 

Contract 1

         Accumulative progress of complete task is 54.75 % from the planned target of 53.65 %, or 1.10 % ahead of the schedule.Details of the tasks are provided hereunder:

 
No. Activity Status
1 Elevated and at Grade Railway Work
  Installed 2,802 from 3,282 columns for the structure of the elevated rail track In operation
  Installed 1,372 from 2,749 beams for the structure of the elevated rail track In operation
  Installed 183 from 932 main precast concrete spans of the elevated rail track In operation
  Demolition of premises In operation
  Relocation of infrastructural systems, i.e. electricity posts, telegraph posts, etc. In operation
2 Stations
  Land excavation of 254,496 cu.m for foundation works of the Bang Sue Grand Station Completed
  Installed 1,109 from 1,232 bored piles (diameter = 1,000 mm) (including piles for approach) at the Bang Sue Grand Station construction site In operation
  Concrete pouring (Type F1A) of 622 from 632 footings at the Bang Sue Grand Station construction site In operation
  Installed 800 column components and 1,840 beam components (from the total 1,907) at the Bang Sue Grand Station construction site In operation
  Installed concrete components of elevated structures (166 spans from the total 305 spans) In operation
  Ground and wall concrete pouring for the basement of the Bang Sue Grand Station construction site In operation
  Installed I-Girders at the Chatuchak Station construction site In operation
3 LD Train Maintenance Depot Work
  Interior finishing at the Daily Maintenance Building construction site In operation
  Concrete pouring at the Passenger Coach Building construction site In operation
  Interior finishing at the Passenger Coach Building construction site In operation
4 CT Maintenance Depot Work
  Interior finishing at the Main Workshop construction site In operation
  Interior finishing at the Infrastructure Workshop construction site In operation
  Finished 741 from 1,168 footings at the Train Stabling construction site In operation
  Installed 1,234 from 2,384 structural columns at the Train Stabling construction site In operation
  Installed platforms at the Train Stabling construction site In operation
5 Local Road and Road Flyover Work
  Earth filling work for local road In operation
  Installed U-ditches at the construction site In operation

 

 

Summary Report of the Execution of Contract 1 for May 2017 (Early Plan)

Contract 1: Civil Works for Bang Sue Grand Station and Depots
Bill No. Description Contract Amount  (Baht) % Progress as of  25 May 2017 Status
planned actual
1 General Requirements 266,482,434 100.00% 97.89% -2.11%
2 Track Work 11,422,571,521 100.00% 78.48% -21.52%
3 Stations 14,247,067,853 100.00% 45.99% -54.01%
4 LD Train Depots and CT Depots 1,604,023,818 100.00% 66.98% -33.02%
5 Local Road and Road Flyover 1,410,141,074 100.00% 49.39% -50.61%
6 Provisional sums and Provisional Items 672,130,000 100.00% 18.59% -81.41%
7 Day-Work Schedule 17,823,300 100.00% 0.00% -100.00%
Total 29,640,240,000 100.00% 62.63% -37.377%

 

Summary Report of the Execution of Contract 1 for May 2017 (Late Plan)

Contract 1: Civil Works for Bang Sue Grand Station and Depots
Bill No. Description Contract Amount  (Baht) % Progress as of  25 May 2017 Status
planned actual
1 General Requirements 266,482,434 96.79% 97.89% 1.10%
2 Track Work 12,127,119,738 72.39% 73.92% 1.53%
3 Stations 16,823,702,974 39.64% 38.95% -0.69%
4 LD Train Depots and CT Depots 1,604,023,818 99.04% 66.98% -32.06%
5 Local Road and Road Flyover 2,393,497,138 29.96% 32.29% 2.23%
6 Provisional sums and Provisional Items 672,130,000 26.69% 18.59% -8.10%
7 Day-Work Schedule 17,823,300 0.00% 0.00% 0.00%
Total 33,904,779,402 53.65% 54.75% 1.10%

 

 

Summary Table of Construction Plan and Progress of Contract 1 for May 2017

 

 

Contract 2

       Accumulative progress of complete task is 86.16 % from the planned target of 94.87 %, or 9.71% behind the schedule.

Details of the tasks are provided hereunder:

No. Activity Status
1 Elevated and at Grade Railway Work
  Installed 10,849 from 14,303 segments for elevated railway In operation
  Installation of boundary fences In operation
2 Station Work
  Installed aerated concrete walls on ticket hall floor at Wat Samian Nari Station In operation
  Flooring tiling work at Wat Samian Nari Station In operation
  Installed steel structure for entrance staircases at Wat Samian Nari Station In operation
  Installed elevators and escalators at Wat Samian Nari Station In operation
  Installed electricity and mechanical systems at Wat Samian Nari Station In operation
  Installed aerated concrete walls on ticket hall floor at Bang Khen Station In operation
  Flooring tiling work at Bang Khen Station In operation
  Installed elevators and escalators at Bang Khen Station In operation
  Installed electricity and mechanical systems at Bang Khen Station In operation
  Installed aerated concrete walls on ticket hall floor at Thung Song Hong Station In operation
  Flooring tiling work at Thung Song Hong Station In operation
  Installed electricity and mechanical systems at Thung Song Hong Station In operation
  Installed elevators and escalators at Thung Song Hong Station In operation
  Installed aerated concrete walls on ticket hall floor at Lak Si Station In operation
  Installed steel structure for entrance staircases at Lak Si Station In operation
  Installed electricity and mechanical systems at Lak Si Station In operation
  Installed elevators and escalators at Lak Si Station In operation
  Installed aerated concrete walls on ticket hall floor at Kan Kheha Station In operation
  Installed steel structure for entrance staircases at Kan Kheha Station In operation
  Installed electricity and mechanical systems at Kan Kheha Station In operation
  Installed elevators and escalators at Kan Kheha Station In operation
  Concrete pouring for construction of ticket hall floor at Don Mueang Station In operation
  Installed steel roof structure at Don Mueang Station In operation
  Installed steel structure for entrance staircases at Don Mueang Station In operation
  Installed electricity and mechanical systems at Don Mueang Station In operation
  Installed elevators and escalators at Don Mueang Station In operation
  Installed steel structure for entrance staircases at Lak Hok Station Completed
  Installed aerated concrete walls on ticket hall floor at Lak Hok Station In operation
  Installed electricity and mechanical systems at Lak Hok Station In operation
  Installed elevators and escalators at Lak Hok Station In operation
  Installed steel structure for entrance staircases at Rangsit Station In operation
  Installed aerated concrete walls on ticket hall floor at Rangsit Station In operation
  Installed electricity and mechanical systems at Rangsit Station In operation
  Installed elevators and escalators at Rangsit Station In operation
3 Local Road and Road Flyover Work
  Local road construction In operation
  Construction of drainage system for local road In operation

 

 

Summary Report of the Execution of Contract 2 for May 2017

Contract 2: Civil Works for Bang Sue-Rangsit Railway
Bill No. Description Contract Amount  (Baht) % Progress as of 25 May 2017 Status
planned actual
1 General Requirements 272,629,119 98.37% 96.43% -1.94%
2 Track work 12,431,497,987 99.97% 91.73% -8.24%
3 Stations 9,957,755,499 87.76% 75.68% -12.08%
4 Local Road and Road Flyover 1,263,337,028 100.00% 92.79% -7.21%
5 Provisional Sums and Provisional Items - - - -
Total 23,925,219,633 94.87% 85.16% -9.71%

 

 

 Summary Table of Construction Plan and Progress of Contract 2 for May 2017

Contract 3

Accumulative progress of complete task is 12.66 % from the planned target of 24.09 % (early plan) and of 15.94 % (late plan), or 11.43 % and 3.28 % behind the early plan and the late plan, respectively.

Details of the tasks are provided hereunder:

No. Activity Status
A 3A Bang Sue-Rangsit
1 Management  
1.1 Preparation and submission of disbursement plan In progress
1.2 Planning, preparation, and submission of construction design In progress
1.3 Risk analysis and management In progress
2 Engineering Work  
2.1 Railway Track  
Preparation of information, preliminary design, and submission of revised information for approval In progress
Production, preparation, and submission of design details In progress
Production, preparation, and submission of testing steps In progress
2.2 Design of Overhead Catenary System (OCS)  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
2.3 Design of Power Supply and Distribution System (PDS)  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
2.4 Operation Control Center (OCC) and Centralized Traffic Control (CTC) system  
Preparation and submission of information in term of OCC and CTC systems and preliminary design In progress
Preparation and submission of information in term of wayside equipment and preliminary design In progress
2.5 Computer Based Interlocking (CBI)  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
2.6 Wayside Equipment (Signal)  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
2.7 Design of Data Transmission System (DTS)  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
2.8 Design of Radio System  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
2.9 Design of  Master Clock (MC) System  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
2.10 Design of CCTV System  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
2.11 Design of Passenger Information Display System (PIDS)  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
2.12 Design of Public Address (PA) System  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
2.13 Design of Station Management System (SMS)  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
2.14 Design of Train-Borne Communication System (TCS)  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
2.15 Design of Telephone system  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
2.16 Design of Automatic Fare Collection (AFC) System  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
2.17 Design of LD/CT Depot Machinery and Equipment  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
2.18 Design of Other Associated Systems, including Control Access Security System (CASS), Operation Automation and Information Technology System (OA&IT)  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
2.19 Design of Train Car Body  
  Production, preparation, and submission of information and preliminary design In progress
  Preparation of information, preliminary design, and submission of revised information for approval In progress
3 Procurement of Materials and Manufacturers  
3.1 Railway Track Survey, data collection, manufacturer examination, material testing, negotiation, and contract signing for provision of track fasteners, track ballast, turnouts, bumpers, concrete sleepers, and Overheard Catenary System (OCS) equipment. In progress
3.2 Overhead Catenary System (OCS) Preparation and submission of information in term of standard of OCS works, negotiation, and contract signing for material provision In progress
3.3 Power Supply and Distribution System (PDS) Preparation and submission of information in term of standard of PDS works, negotiation, and contract signing for material provision In progress
3.4  Supervisory Control and Data Acquisition (SCADA) Preparation and submission of information in term of standard of SCADA works, In progress
4 Telecommunication System  
4.1 Data Transmission System (DTS)  
  Preparation of information, manufacturer examination, negotiation, and contract signing In progress
4.2 Radio System  
  Preparation of information, manufacturer examination, negotiation, and contract signing In progress
4.3 Master Clock (MC) System  
  Preparation of information, manufacturer examination, negotiation, and contract signing In progress
4.4 CCTV System  
  Preparation of information, manufacturer examination, negotiation, and contract signing In progress
4.5 Passenger Information Display System (PIDS)  
  Preparation of information, manufacturer examination, negotiation, and contract signing In progress
4.6 Public Address (PA) System  
  Preparation of information, manufacturer examination, negotiation, and contract signing In progress
4.7 Station Management System (SMS)  
  Preparation of information, manufacturer examination, negotiation, and contract signing In progress
4.8 Train-Borne Communication System (TCS)  
  Preparation of information, manufacturer examination, negotiation, and contract signing In progress
4.9 Telephone System  
  Preparation of information, manufacturer examination, negotiation, and contract signing In progress
4.10 Automatic Fare Collection System (AFC)  
  Preparation of information, manufacturer examination, negotiation, and contract signing In progress
4.11 Depot Machinery and Equipment  
  Preparation of information, manufacturer examination, negotiation, and contract signing In progress
5 Other Associated Systems, including Control Access Security System (CASS), Operation Automation and Information Technology System (OA&IT)  
  Preparation of information, manufacturer examination, negotiation, and contract signing In progress
6 Machinery and Equipment  
  Procurement of agents In progress
B 3B Bang Sue-Taling Chan  
1 Submission of survey results In progress

 

Summary Table of Construction Plan and Progress of Contract 3 for May 2017


 
 