Construction Supervision of Mass Transit System Project in Bangkok (Red Line) Bang Sue-Rangsit Section
Main Menu About the Project Project Development Public Relations Contact
Public Relations
Progress
Activity Photos

 

  Progress
 

 

Project Progress as of May 2018

 

Contract 1

         Accumulative progress of complete task is 71.15 % from the planned target of 72.31%, or 1.16% behind the schedule.

         Details of the tasks are provided hereunder:

 
No. Activity Status
1 Elevated and at Grade Railway Work
  Installed 2,723 from 2,749 beams for the structure of the elevated rail track In operation
  Installed 533 from 932 main precast concrete spans of the elevated rail track In operation
  Demolition of premises In operation
  Relocation of infrastructural systems, i.e. electricity posts, telegraph posts, etc. In operation
2 Stations
  Concrete pouring (Type F1A) of 704 from 753 footings at the Bang Sue Grand Station construction site In operation
  Installed 271 from 305 main precast concrete spans of the elevated rail track at the Bang Sue Grand Station construction site In operation
  Ground and wall concrete pouring for the basement of the Bang Sue Grand Station construction site In operation
  Concrete pouring on ticket hall and platform floors at the Bang Sue Grand Station construction site In operation
  Installed steel roof structure at the Bang Sue Grand Station construction site In operation
  Installed aerated concrete walls on ticket hall floor the Bang Sue Grand Station construction site In operation
3 LD Train Maintenance Depot Work
  Interior finishing at the Daily Maintenance Building construction site In operation
  Concrete pouring at the Carriage Shop Building construction site In operation
  Interior finishing at the Passenger Coach Building construction site In operation
4 CT Maintenance Depot Work
  Interior finishing at the Main Workshop construction site In operation
  Interior finishing at the Infrastructure Workshop construction site In operation
  Installed platforms at the Train Stabling construction site In operation
5 Local Road and Road Flyover Work
  Earth filling work for local road In operation
  Installed U-ditches at the construction site In operation

 

 

Summary Report of the Execution of Contract 1 for May 2018 (Early Plan)

Contract 1: Civil Works for Bang Sue Grand Station and Depots
Bill No. Description Contract Amount (Baht) % Progress as of 25 May 2018 Status
planned actual
1 General Requirements 266,482,434 98.14% 97.89% -0.25%
2 Track Work 12,127,119,738 87.34% 95.43% 8.09%
3 Stations 16,823,702,974 61.93% 52.28% -9.65%
4 LD Train Depots and CT Depots 1,604,023,818 100.00% 90.17% -9.83%
5 Local Road and Road Flyover 2,393,497,138 56.45% 43.55% -12.90%
6 Provisional sums and Provisional Items 672,130,000 42.63% 18.59% -24.04%
7 Day-Work Schedule 17,823,300 21.74% 0.00% -21.74%
Total 33,904,779,402 72.31% 71.15% -1.16%

 

 

 Summary Table of Construction Plan and Progress of Contract 1 for May 2018

 

Contract 2

          Accumulative progress of complete task is 97.94% from the planned target of 99.77%, or 1.83% behind the schedule

Details of the tasks are provided hereunder:

No. Activity Status
1 Elevated and At-grade Railway Work
  Installation of boundary fences In operation
2 Station Work
  Interior finishing at Wat Samian Nari Station In operation
  Installed elevators and escalators at Wat Samian Nari Station Completed
  Installed electricity and mechanical systems at Wat Samian Nari Station Completed
  Interior finishing at Bang Khen Station In operation
  Installed elevators and escalators at Bang Khen Station Completed
  Installed electricity and mechanical systems at Bang Khen Station Completed
  Interior finishing at Thung Song Hong Station In operation
  Installed electricity and mechanical systems at Thung Song Hong Station Completed
  Installed elevators and escalators at Thung Song Hong Station Completed
  Interior finishing at Lak Si Station In operation
  Installed electricity and mechanical systems at Lak Si Station Completed
  Installed elevators and escalators at Lak Si Station Completed
  Interior finishing at Kan Kheha Station In operation
  Installed electricity and mechanical systems at Kan Kheha Station Completed
  Installed elevators and escalators at Kan Kheha Station Completed
  Concrete pouring for construction of ticket hall floor at Don Mueang Station Completed
  Installed steel roof structure at Don Mueang Station Completed
  Installed aerated concrete walls on ticket hall floor at Don Mueang Station Completed
  Constructed footpath and improved landscape at Don Mueang Station In operation
  Installed electricity and mechanical systems at Don Mueang Station In operation
  Installed elevators and escalators at Don Mueang Station Completed
  Interior finishing at Lak Hok Station In operation
  Installed electricity and mechanical systems at Lak Hok Station Completed
  Installed elevators and escalators at Lak Hok Station Completed
  Interior finishing at Rangsit Station In operation
  Installed steel structure for entrance staircases at Rangsit Station Completed
  Installed electricity and mechanical systems at Rangsit Station Completed
  Installed elevators and escalators at Rangsit Station Completed
3 Local Road and Road Flyover Work
  Local road construction In operation
  Construction of drainage system for local road In operation

 

 

Summary Report of the Execution of Contract 2 for May 2018

Contract 2: Civil Works for Bang Sue-Rangsit Railway
Bill No. Description Contract
Amount  (Baht)
% Progress as of 25 May 2018 Status
planned actual
1 General Requirements 272,629,119 100.00% 100.00% 0.00%
2 Track Work 12,431,497,987 100.00% 99.99% -0.01%
3 Stations 9,957,755,499 100.00% 98.55% -1.45%
4 Local Road and Road Flyover 1,263,337,028 100.00% 93.69% -6.31%
5 Provisional Sums and Provisional Items - - - -
Total 23,925,219,633 100.00% 99.06% -0.94%

 

 

 Summary Table of Construction Plan and Progress of Contract 2 for May 2018

Contract 3

Accumulative progress of complete task is 28.25% from the planned target of 53.73% (early plan) and of 46.17% (late plan), or 25.48% and 17.92% behind the early plan and the late plan, respectively.

Details of the tasks are provided hereunder:

No. Activity Status
A 3A Bang Sue-Rangsit and 3B Bang Sue-Taling Chan
1 General Requirements  
1.1 General Management  
1.1.1 Management Plan  
  Company representative details In progress
  Submission of traffic management plan  In progress
1.1.2 Facilities and Temporary Access Control  
  Proposal on blocking public utilities management In progress
  Proposal on management of utilities-related agencies In progress
  Proposal on safety system  In progress
1.1.3 Traffic Management Plan  
  Proposal on temporary traffic management and road traffic control In progress
  Road and sidewalk reinstatement In progress
2 Engineering Work
2.1 Railway Track  
  Production, preparation, and submission of design details In progress
  Production and submission of revised information for approval In progress
  Production, preparation, and submission of testing steps In progress
  Production, preparation, and submission of field testing steps In progress
2.2 Electrical System
2.2.1 Design of Overhead Catenary System (OCS)  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production and submission of revised information for approval In progress
2.2.2 Design of Power Supply and Distribution System (PDS)  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production and submission of revised information for approval In progress
  Production, preparation, and submission of testing steps In progress
2.3 Railway Signaling and Control Systems
2.3.1 Operation Control Center (OCC) and Centralized Traffic Control (CTC) system  
  Production and submission of revised information for approval In progress
2.3.2 Computer Based Interlocking (CBI)  
  Production and submission of revised information for approval In progress
2.3.3 ระบบ ATP/A–   
 
Automatic Train Protection (ATP) and Automatic Train Operation (ATO)
  Preparation and submission of information and preliminary design In progress
  Production and submission of revised information for approval In progress
2.3.4 Wayside Equipment (Signal)  
  Preparation and submission of information and preliminary design In progress
  Preparation of information, preliminary design, and submission of revised information for approval In progress
Production, preparation, and submission of design details In progress
  Production and submission of revised information for approval In progress
2.4 Telecommunication System
2.4.1 Design of Data Transmission System (DTS)  
  Production and submission of revised information for approval In progress
  Production, preparation, and submission of testing steps Completed
2.4.2 Design of Radio System  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of testing steps Completed
2.4.3 Design of  Master Clock (MC) System  
  Production and submission of revised information for approval Completed
  Production, preparation, and submission of testing steps Completed
2.4.4 Design of CCTV System  
  Production and submission of revised information for approval In progress
  Production, preparation, and submission of testing step Completed
2.4.5 Design of Passenger Information Display System (PIDS)  
  Production and submission of revised information for approval In progress
  Production, preparation, and submission of testing steps Completed
2.4.6 Design of Public Address (PA) System  
  Production and submission of revised information for approval In progress
  Production, preparation, and submission of testing steps Completed
2.4.7 Design of Station Management System (SMS)  
  Production and submission of revised information for approval In progress
  Production, preparation, and submission of testing steps Completed
2.4.8 Design of Train-Borne Communication System (TCS)  
  Production and submission of revised information for approval In progress
  Production, preparation, and submission of testing steps Completed
2.4.9 Design of Telephone System  
  Production and submission of revised information for approval In progress
  Production, preparation, and submission of testing steps Completed
2.5 Automatic Fare Collection (AFC) System
  Production and submission of revised information for approval In progress
  Production, preparation, and submission of testing steps In progress
2.6 Depot Machinery and Equipment
2.6.1 Design of LD Train Depot Machinery and Equipment  
  Production, preparation, and submission of design details In progress
2.6.2 Design of CT Depot Machinery and Equipment  
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production, preparation, and submission of design details In progress
  Production and submission of revised information for approval In progress
2.7 Other Systems
2.7.1 Design of Control Access Security System (CASS)  
  Production and submission of revised information for approval In progress
2.7.2 Design of Operation Automation and Information Technology System (OA&IT)  
  Production and submission of revised information for approval In progress
2.8 Design of Train Car Body
  Preparation of information, preliminary design, and submission of revised information for approval In progress
  Production and preparation of design details In progress
  Production and submission of revised information for approval In progress
2.9 Construction Planning and Design
  Production of preliminary design of electric power substation and submission of revised design for approval In progress
3 Procurement of Manufacturers
3.1 Railway Track
  Manufacturer examination and railway testing In progress
  Railway track transport In progress
  Manufacturer examination and track fastener testing In progress
  Track fastener transport In progress
  Track fastener transport to the North Line N1 construction site Completed
  Manufacturer examination and ballast stone testing In progress
  Ballast stone transport In progress
  Manufacturer examination and testing of railway turnouts, expansion joints, compromise rails In progress
  Transport of railway turnouts, expansion joints, and compromise rails In progress
  Manufacturer examination and rubber pad testing In progress
  Rubber pad transport In progress
  Preparation of information, manufacturer examination and testing, negotiation, and contract signing In progress
  Manufacturer examination and testing for provision of concrete sleepers for ballastless track system In progress
  Transport of concrete sleepers for ballastless track system In progress
  Manufacturer examination and testing for provision of concrete sleepers for ballasted track system In progress
  Transport of concrete sleepers for ballasted track system In progress
3.2 Electrical System
3.2.1 Overhead Catenary System (OCS)  
  Manufacturer examination and testing of Overhead Catenary System (OCS) columns and beams In progress
  Transport of Overhead Catenary System (OCS) columns and beams In progress
  Transport of Overhead Catenary System (OCS) columns and beams to the North Line N1 construction site  
In progress
  Manufacturer examination and testing of signal cables In progress
  Manufacturer examination and testing for associated works In progress
  Manufacturer examination and testing for associated OCS works In progress
3.2.2 Design of Power Supply and Distribution System (PDS)  
  Manufacturer examination and 115-kV GISS system testing In progress
  Manufacturer examination and 115/25-kV traction transformer testing In progress
  Manufacturer examination and 115/24-kV power transformer testing In progress
  Manufacturer examination and 25-kV Gas-insulated Switchgear (GIS) testing In progress
  Manufacturer examination and 24-kV Switchgear testing In progress
  Manufacturer examination and 25-kV Auto Transformer testing In progress
  Manufacturer examination and 25-kV AT Switching Station testing In progress
  Manufacturer examination and 24/0.4-kV Dry-type Transformer testing In progress
  Manufacturer examination and 400V emergency diesel generator testing In progress
  Manufacturer examination and power cable testing In progress
3.2.3 Supervisory Control and Data Acquisition (SCADA)  
  Manufacturer examination and testing for Supervisory Control and Data Acquisition (SCADA) equipment In progress
3.3 Railway Signaling and Control Systems  
3.3.1 Centralized Traffic Control (CTC) system  
  Manufacturer examination and CTC system testing In progress
3.3.2 Computer Based Interlocking (CBI)  
  Manufacturer examination and CTC system testing In progress
3.3.3 ระบบ ATP/ A– ATP/A System  
  ตรวจสอบโรงงานและทดสอบ ระบบ ATP/A– In progress
Manufacturer examination and ATP/A- system testing
  ตรวจสอบโรงงานและทดสอบ On-Board ATP/ A– In progress
Manufacturer examination and On-Board ATP/A- testing
3.4 Telecommunication System
3.4.1 Design of Data Transmission System (DTS)  
  Manufacturer examination and DTS testing In progress
3.4.2 Design of Radio System  
  Manufacturer examination and radio system testing In progress
3.4.3 Design of Master Clock (MC) System  
  Manufacturer examination and MC system testing In progress
3.4.4 Design of CCTV System  
  Manufacturer examination and CCTV system testing In progress
3.4.5 Design of Passenger Information Display System (PIDS)  
  Manufacturer examination and PIDS testing In progress
3.4.6 Design of Public Address (PA) System  
  Manufacturer examination and PA system testing In progress
3.4.7 Design of Station Management System (SMS)  
  Manufacturer examination and SMS testing In progress
3.4.8 Design of Train-Borne Communication System (TCS)  
  Manufacturer examination and TCS testing In progress
3.4.9 Design of Telephone System  
  Manufacturer examination and telephone testing In progress
3.5 Automatic Fare Collection (AFC) System
  Preparation for system procurement, manufacturer examination and testing In progress
3.6 Depot Machinery and Equipment
3.6.1 Design of LD Train Depot Machinery and Equipment  
  Preparation of information, manufacturer examination and testing, negotiation, and contract signing In progress
3.6.2 CT Depot Machinery and Equipment  
  Preparation for procurement, manufacturer examination, and testing In progress
3.7 Other Associated Systems, including Control Access Security System (CASS), Operation Automation and Information Technology System (OA&IT)
  Preparation for procurement, manufacturer examination, and testing In progress
     
3.8 Train 
3.8.1 Materials and equipment  
  Preparation of information, manufacturer examination and testing, and negotiation for train car body In progress
  Preparation of information, manufacturer examination and testing, and negotiation for heating, ventilation, and air conditioning (HVAC) In progress
  Preparation of information, manufacturer examination and testing, and negotiation for train In progress
  Preparation of coupler and drive construction standard In progress
  Preparation of entrance system construction standard In progress
  Agent procurement, negotiation, and contract signing for traction transformer In progress
  Agent procurement, negotiation, and contract signing for traction converter In progress
  Preparation of information, manufacturer examination and testing, and negotiation for traction motor In progress
  Preparation of pantograph construction standard In progress
  Agent procurement, negotiation, and contract signing for APS output transformer box In progress
  Preparation of construction standard for battery In progress
  Agent procurement, negotiation, and contract signing for train integrated management system (TIMS) In progress
  Preparation of information, manufacturer examination and testing, and negotiation for brake and air distribution system In progress
3.9 Construction Machinery and Tools
  Manufacturer examination and testing construction machinery and tools Completed
  Transport of construction machinery and tools  In progress
4 Construction and Installation Work
4.1 North Lines Bang Sue-Rangsit
4.1.1 N2 (12+201 – 24+826)  
  General Requirements for the North Lines  
  N2-A (12+201 – 18+000) Preparation for construction work and equipment (12+201–18+000) In operation
  Railway Track  
  N2-A (24+826 – 29+230) : Flash butt welding In operation
(12+201–18+000 (24+826))
4.1.2 N3 (24+826 – 32+500)  
  Railway Track  
  N2-A (24+826 – 29+230) : Flash butt welding In operation
(24+826 – 29+230 (32+500))
  Overhead Catenary System (OCS)  
  N2-A (24+826 – 29+230) : Installation of  Overheard Catenary System (OCS) and equipment  In operation
(24+826 – 29+230)
  Railway Track  
  N3-B (29+230 – 32+500) :  Flash butt welding In operation
(29+350 – 32+350)
4.1.3 North Line-Distribution Substation  
  Distribution Substation Construction  
  Pile installation at the construction site of distribution substation In operation
  Foundation construction at the construction site of distribution substation In operation
4.2 West Line  (Bang Sue-Taling Chan)
4.2.1 W1 (9+004 – 17+979)  
  General Requirements -Main West Railway  
  W1-B (13+500 – 17+979) : Installation of OOS post at the base  (15+300 – 17+979) In operation
4.2.2 W1 (9+004 – 17+979)  
  General Requirements –Main West Railway  
  W2-A (17+979 – 22+085) : Installation of OOS post at the base  (17+979 – 22+085) In operation

 

Summary Table of Construction Plan and Progress of Contract 3 for May 2018

 


 
 