June 2014

 

Contract 1

Tasks that have been implemented by contractor are provided hereunder:

  • Land levelling, demolition of obstructions, and preparation for the construction of Bang Sue Grand Station (zone 1, zone 3, zone 4A, and zone 4B including zone 5 of Chatuchak Station and the areas of road and flyover in zone 1 and zone 2 of the Grand Station). Demolition of existing buildings in the construction sites of CT train maintenance depot and long-distant maintenance depot.
  • Variation orders including construction in the area of permanent stabling yard for freight train, demolition of existing railway tracks at Bang Sue Grand Station, removal of existing railway tracks for construction of temporary stabling yard for freight train, removal of signaling cable, construction of access road to MRT station, installation of electrical safety system, and provision of earthing and bonding for the foundation construction.
  • Preparation for construction at the northern portion of the Grand Station (zone 1, Sta. 8+127 to Sta. 9+510), at the southern portion (zone 1, Sta. 7+251 to Sta. 7+499) and basement for installation of railway tracks (zone 3, new stabling yards of commuter train at the Grand Station, Sta. 7+150 to Sta. 9+075 and zone 8).
  • Excavation and drainage work, earth filling work, and testing for installation of railway tracks in zone 3, new stabling yards of commuter train, Sta. 7+150 to Sta. 9+075 and zone 8 (at the northern and southern portions).
  • Excavation and land levelling for the construction of underground floors of the Grand Station building (gridline 12-20/H-F & 6-20/E).
  • Backfill and installation of concrete slabs for foundation works (1st floor) at gridline 6-13, 15/A – D; 6, 10/H-E.
  • Driven pile work for the construction of underground floors of the Grand Station (gridline 11, 3-5, 18-20 A-D; 6-18E; 18H-F; 1-5H-E), access road to station building (gridline 6-12), train station area at the Grand Station (gridline 12-19 at the eastern/western portion), road flyover area, CT train maintenance depot area (basic system workshops and new stabling yards of commuter train), and long-distant maintenance depot (passenger terminal/diesel engine maintenance depot and daily maintenance depot).
  • Driven pile cap work for the construction of underground floors of the Grand Station (gridline 6-17A-D; 6, 9-18H-E), road flyover in new stabling yards and basic system workshops in the CT train maintenance depot.
  • Demolition of Hopewell structure in zone 4B phase 2 and zone 5 phase 3 at the northern portion and demolition of structural columns in zone 5, Sta. 10+650 to Sta. 12+202.
  • Embankment work for site access road (zone 2, 5, and 7 phase 2 at the south portion) and roadway embankment in construction site (zone 6 phase 1 and zone 7 phase 1) including local road (zone 4B phase 2 at the western portion).
  • Construction of drainage system for local road (zone 5 and 7) and for local road (zone 4A, 4B, and 5 phase 2 at the western portion), including installation of temporary drainage equipment at the Grand Station.
  • Preparation and traffic management during the removal of existing railway tracks in zone 4A phase 1 and 2; the construction of local road in zone 4A, 4B, and 5 (phase 2 at the western portion); the construction of site access road in zone 2, 3, 5, and 7; and the construction of roadway for internal transportation in zone 6 and 7.
  • Installation of survey points for the construction of road flyover in the Grand Station construction site, maintenance depots, basic system workshops, and new stabling yards (at CT train maintenance depot).
  • Earth filling for the construction of site access road to zone 2 and 7 (phase 2 at the southern portion), new stabling yards (at CT train maintenance depot and long-distant maintenance depot), and the construction of roadway for internal transportation in zone 6 phase 1.
  • Basement for the construction of site access road to zone 8.

Other activities were indicated in the Index. Accumulative progress of complete task is 10.01% from the planned target of 20.11%, or 10.10% behind the schedule. Details of the tasks are provided hereunder:


No. Activity Status
1 Elevated and at Grade Railways Work
  Testing work of 3 pilot piles (diameter = 1,500 mm) (at Terd Damri Road at MRTA parking lot and at local road near Samian Nari Temple). Completed
  Testing work of pilot piles (diameter = 1,200 mm) at the construction site of the Grand Station. Completed
  Testing work of pilot piles (diameter = 800 mm) at the construction site of road flyover. Completed
  Pile testing of the existing Hopewell structures at local road near Samian Nari Temple. Completed
  Demolition of Hopewell’s 217 structural columns from 239 structural columns (Type 1A Case 1 = 61 columns/ Type 2A, 2B Case 1 = 11 columns/ Type 3A, 3B Case 1 = 60 columns/ Type 4 Case 1 = 5 columns/ Type 12 Case 2 = 28 columns/ Type 13 Case 2 = 20 columns/ Type 14 Case 3 = 29 columns/ Type 15 Case 3 = 3 columns) In operation
  Installation of 56 bored piles (diameter = 1,500 mm) from the total of 818 piles for the structure of the elevated rail track. In operation
  Demolition of premises. In operation
  Relocation of infrastructural systems, i.e. electricity posts, telegraph posts, etc. In operation
  Removal of concrete surface. In operation
2 Station Work
  Land excavation of 234,370 cu.m from the target of 293,314 cu.m for foundation works of the Grand Station. In operation
  Construction of 295 bored piles (diameter = 800 mm) from 623 bored piles at the Bang Sue Grand Station construction site. In operation
  Construction of 310 bored piles (diameter = 1,000 mm) from 632 bored piles at the Bang Sue Grand Station construction site. In operation
  Construction of 21 bored piles (diameter = 1,200 mm) from 231 bored piles at the Bang Sue Grand Station construction site. In operation
  Construction of 1,656 bored piles (diameter = 1,500 mm) from 1,706 bored piles at the Bang Sue Grand Station construction site. In operation
  Construction of 87 bored piles (diameter = 2,000 mm) from 123 bored piles at the Bang Sue Grand Station construction site. In operation
  Lean concrete pouring of 70 footings from 160 footings at the Bang Sue Grand Station construction site. In operation
  Removal of existing railway tracks at the Bang Sue Grand Station site. In operation
3 Short and Long-Distant Maintenance Depot Work
  Construction of 980 driven piles (diameter = 0.40x0.40 m) from 1,426 driven piles and construction of 128 bored piles (diameter 0.50 m.) from 234 bored piles at the Daily Maintenance construction site. In operation
  Construction of 151 driven piles (diameter = 0.40x0.40 m) from 1,559 driven piles at the Main Workshop construction site. In operation
  Construction of 582 driven piles (diameter = 0.40x0.40 m) at the Infrastructure Workshop construction site. Completed
  Foundation work of 65 footings from 244 footings at the Infrastructure Workshop construction site. In operation
  Construction of 1,482 driven piles (diameter = 0.18x0.18 m) from 2,384 driven piles at the Train Stabling construction site. In operation
  Foundation work of 741 footings from 1,168 footings at the Train Stabling construction site. In operation
  Installation of 708 structural columns from 2,384 columns at the Train Stabling construction site. In operation
4 Local Road and Road Flyover Work
  Earth filling work forlocal road. In operation
  Construction of 312 driven piles (diameter = 0.22x0.22 m and 0.26x0.26 m) from 816 driven piles for road flyover. In operation
  Construction of 149 driven piles (diameter = 0.26x0.26 m) from 306 driven piles for road flyover. In operation
  Construction of 154 bored piles (diameter = 0.80 m) from 282 bored piles. In operation
  Foundation work of 5 footings from 33 footings for road flyover. In operation
  Installation of 3 structural columns from 33 columns for road flyover. In operation
5 Other Works
  Batching plant investigation. In operation
  Concrete mixed design investigation. In operation
  Aggregate source investigation. In operation
  Bored pile plant investigation. In operation
  Control surveys Completed
  Land levelling In operation

 

 

Summary Report of the Execution of Contract 1 for June 2014

Contract 1 : Civil Works for Bang Sue Grand Station and Depots
Bill No. Description Contract Amount (Bath) % Progress as of
25-JUNE-14
Status
Planned Actual
1 General Requirements 266,482,434 33.61% 48.08% 14.46%
2 Track work 11,422,571,521 12.53% 3.04% -9.49%
3 Stations 14,247,067,853 18.41% 16.14% -2.27%
4 LD-Train Depots and CT-Train Depots 1,604,023,818 51.00% 3.65% -47.35%
5 Local Road and Road Flyover 1,410,141,074 55.11% 7.47% -47.64%
6 Provisional Sums and Provisional Items 672,130,000 33.06% 4.31% -28.74%
7 Day-Work Schedule 17,823,300 0.00% 0.00% 0.00%
  Total 29,640,240,000 20.11% 10.01% -10.10%

 

 

Summary Table of Construction Plan and Progress of Contract 1 for June 2014

 

 

Contract 2

Tasks that have been implemented are provided hereunder:

  • Maintenance work and traffic management for temporary detour road at foundation piles No. 317-371), measurement work and mitigation of environmental impact, including environmental public relations.
  • Land levelling at Bang Khaen Station, Lak Si Station, Lak Hok Station, Khan Keha Station, Don Muang Station, and Rangsit Station.
  • Relocation of infrastructural amenities belonged to the MWA, MEA, and TOT.
  • Lighting work for traffic during night time.
  • Demolition of Hopewell structure (between piles No. 0/S-34/S, 36/S-86, 87-133, 134-163, 164-217 and 331/S-338/S) including concrete slabs at the areas of at-grade railways and transition railway.
  • Installation of bored piles (for piles No. 009-033, 166-217, 237-266, 280-296, and 423-466) and foundation works in the areas between piles No. 054-078, 079-084(L), 97-103, 104-110(R), 104-110(L), 111-131, 237-266 and 280-296, including installation of structural columns for elevated railways (lower columns No. 054-078, 104-110(R), 104-110(L), 111-131, 237-266 and 280-296) and cast-in-situ reinforced beams (lower part of the superstructure No. 054-078, 111-131, and 132-150).
  • Land excavation and embankment for the construction of transition railway near Rangsit station and compacted sand for basement at Lak Hok station and Sta. 25+232.5 to Sta. 29+145.
  • Lean concrete pouring for the construction of transition railway near Lak Hok station and pre cast concrete bored pile work and reinforcement configuration for transition railway near Lak Hok station, Sta. 25+232.5 to Sta. 29+145.
  • Installation of bored piles at Samian Nari Temple Station BP1(2), Bang Khaen Station BP2(2), Thung Song Hong Station BP3(2), Khan Keha Station BP7(2), Lak Si Station BP6(1), Rangsit Station BP1(3), BP2(3) and BP7(4).
  • Installation of barrette piles at Don Muang Station BP4(2).
  • Foundation works at Thung Song Hong Station.
  • Excavation and backfill, including installation of sheet piles for preventing soil erosion, compacted sand, and lean concrete pouring for basement, reinforced concrete work, foundation work, and installation of structural columns, including cast-in-situ stairs, beams and other superstructures for road flyover at Sta. 24+910.
  • Demolition of existing station building and construction of temporary site office with facilities at Bang Khaen Station.
  • Dynamic load testing and seismic testing.

Other activities were indicated in the Index. Accumulative progress of complete task is 13.67% from the planned target of 51.96%, or 38.29% behind the schedule. Details of the tasks are provided hereunder:

 

No. Activity Status
1 Elevated and at Grade Railways Work  
  Demolition of Hopewell’s 566 structural columns
(Type 1 Case 1 = 1 column, Type 1A Case 1 = 31 columns, Type 2A Case 1 = 5 columns, Type 2B  Case 1 = 1 column, Type 3A Case 1 = 83 columns, Type 4 Case 1 = 18 columns, Type 6 Case 1 = 1 column, Type 5A Case 2 = 3 columns, Type 5B Case 2 = 1 column, Type 7 Case 2 = 7 columns, Type 8 Case 2 = 75 columns, Type 9 Case 2 = 10 columns, Type 10 Case 2 = 6 columns, Type 11 Case 2 = 84 columns, Type 14 Case 3 = 128 columns, Type 15 = 6 columns, Type 16 Case 2 = 42 columns, Type 16A Case 2 = 18 columns, Type 16B Case 2 = 9 columns, Type 18 Case 2 = 11 columns, Type 19 Case 2 = 3 columns).
In operation
 
  • Testing work of pilot pile (diameter = 1,500 mm) in 4 areas: 1) Lak Si area (Sta. 17+500), 2) Near Don Muang District Office (Sta. 20+600), 3) Near the entrance of Grand Canal Village (Sta. 24+600), and 4) at Rangsit Railway Station (Sta. 29+800).
  • Testing work of pilot pile (diameter = 1,200 mm) near the entrance of Grand Canal Village (Sta. 24+600).
Completed
  Pile testing of the existing Hopewell structures at local road near Chulabhorn Research Institute (CRI). Completed
  Installation of 33 bored piles (diameter = 1,200 mm) for elevated railway. In operation
  Installation of 697 bored piles (diameter = 1,500 mm) from 1,656 bored piles for elevated railway. In operation
  Installation of 309 bored piles (diameter = 1,800 mm) for elevated railway. In operation
  Foundation work of 141 footings from 428 footings for elevated railway In operation
  Construction of 187 columns from 856 columns for elevated railway. In operation
  Installation of 66 cross beams from 428 cross beams for the structure of elevated railway tracks In operation
  Installation of 1,328 driven piles (diameter 0.35x0.35 m) from 1,604 driven piles at Sta. 24+830 to Sta. 25+152. In operation
  Installation of 9,369 driven piles (diameter 0.22x0.22 m) from 28,571 driven piles at Sta. 25+210 to Sta. 28+900. In operation
  Earth filling, sand embankment and subballast for at-grade railway track. In operation
  Reinforced concrete work for at-grade railway track. In operation
2 Station Work
  Demolition of existing railway stations (Bang Khen and Lak Si). Completed
  Installation of 65 bored piles (diameter = 1,500 mm) from 65 bored piles and 26 barrette piles from 44 barrette piles at Samian Nari Temple Station. In operation
  Foundation work of 1 footings from 22 footings for elevated railway at Samian Nari Temple Station. In operation
  Installation of 66 bored piles (diameter = 1,500 mm) from 66 bored piles and 38 barrette piles from 44 barrette piles at Bang Khen Station. In operation
  Installation of 66 bored piles (diameter = 1,500 mm) and 44 barrette piles at Thung Song Hong Station. Completed
  Foundation work of 4 footings from 22 footings for elevated railway at Thung Song Hong Station. In operation
  Installation of 101 bored piles (diameter = 1,500 mm) from 145 bored piles at Lak Si Station. In operation
  Foundation work of 2 footings from 22 footings for elevated railway at Lak Si Station. In operation
  Installation of 104 bored piles (diameter = 1,500 mm) from 145 bored piles at Khan Keha Station. In operation
  Foundation work of 2 footings from 22 footings for elevated railway at Khan Keha Station. In operation
  Installation of 44 barrette piles from 150 barrette piles at Don Muang Station. In operation
  Installation of 384 bored piles (diameter = 1,500 mm) from 470 bored piles at Rangsit Station. In operation
  Foundation work of 9 footings from 56 footings for elevated railway at Rangsit Station. In operation
  Removal of existing railways at Rangsit Station and Don Muang Station. Completed
  Earth filling work forlocal roads. In operation
3 Local Road and Road Flyover Work
  Construction of 528 driven piles (diameter = 0.22 x 0.22 m and 0.26 x 0.26 m) for road flyover from Sta. 25+201 to Sta. 25+253. Completed
  Installation of 122 bored piles (diameter = 800 mm) for road flyover. Completed
  Foundation work of 13 footings from 14 footings for road flyover. In operation
  Installation of 10 structural columns from 14 columns for road flyover. In operation
4 Other Works
  Batching plant investigation. In operation
  Concrete mixed design investigation. In operation
  Aggregate source investigation. In operation
  Control surveys Completed
  Land levelling In operation
  Procurement and relocation (site office, vehicles and equipment) Completed

 

 

Summary Report of the Execution of Contract 2 for June 2014

Contract 2 : Civil Works for Bang Sue - Rangsit Railway
Bill No. Description Contract Amount (BahT) %Progress as of
25-JUNE-14
Status
Planned Actual
1 General Requirements 272,629,120 55.22% 46.13% -9.09%
2 Track work 10,514,931,561 54.58% 16.35% -38.23%
3 Stations 8,558,445,112 52.26% 11.10% -41.16%
4 Local Road and Road Flyover 1,264,542,043 27.43% 1.81% -25.62%
5 Provisional Sums and Provisional Items - 0.00% 0.00% 0.00%
Total 20,610,547,836 51.96% 13.67% -38.29%

 

 

Summary Table of Construction Plan and Progress of Contract 2 for June 2014

 
 