Construction Supervision of Mass Transit System Project in Bangkok (Red Line) Bang Sue-Rangsit Section
Main Menu About the Project Project Development Public Relations Contact
Public Relations
Progress
Activity Photos

 

  Progress
 

 

Project Progress as of June 2016

 

Contract 1

    Accumulative progress of complete task is 45.54% from the planned target of 77.61%, or 32.07% behind the schedule.

Details of the tasks are provided hereunder:

No. Activity Status
1 Elevated and at Grade Railways Work
  Installed 2,008 from 2,009 bored piles (diameter = 1,500 mm) for the structure of the elevated rail track. In operation
  Installed 364 from 366  bored piles (diameter = 2,000 mm) for the structure of the elevated rail track. In operation
  Concrete pouring of 691 footings from the target of 698 footings for elevated railway In operation
  Installed columns for the structure of the elevated rail track In operation
  Installed beams for the structure of the elevated rail track In operation
  Installed main pre-cast concrete compotents of the elevated rail track In operation
  Demolition of premises. In operation
  Relocation of infrastructural systems, i.e. electricity posts, telegraph posts, etc. In operation
2 Station Work
  Land excavation of 254,496 cu.m from the target of 293,314 cu.m for foundation works of the Grand Station. In operation
  Installed 578  from 623 bored piles (diameter = 800 mm) at the Bang Sue Grand Station construction site. In operation
  Installed 1,088 from 1,232 bored piles (diameter = 1,000 mm) (including piles for approach) at the Bang Sue Grand Station construction site. In operation
  Installed 256 from 257 bored piles (diameter = 1,200 mm) at the Bang Sue Grand Station construction site. In operation
  Installed 116 from 123 bored piles (diameter = 2,000 mm) at the Bang Sue Grand Station construction site. In operation
  Lean concrete pouring of 150 from 160 footings at the Bang Sue Grand Station construction site. In operation
  Concrete pouring (Type F1A) of 526 from 632 footings at the Bang Sue Grand Station construction site. In operation
  Installed structural columns and beams at the Bang Sue Grand Station construction site. In operation
  Installed concrete components of elevated structures. In operation
  Foundation and wall concrete pouring for the basement of the Bang Sue Grand Station construction site In operation
  Installed structural columns at the Chatuchak Station construction site. In operation
3 LD Train Maintenance Depot Work
  Installed pre cast beams at the Daily Maintenance construction site. In operation
  Concrete pouring at the Daily Maintenance construction site. In operation
  Installed steel columns and roof structures at the Daily Maintenance construction site. In operation
  Wall concrete pouring and plastering at the Daily Maintenance construction site. In operation
  Installed 1,547 from 1,596 driven piles (0.40x0.40 m) at the Passenger Coach construction site. In operation
  Installed steel columns and roof structures at the Passenger Coach construction site. In operation
  Concrete pouring at the Passenger Coach construction site. In operation
4 CT Train Maintenance Depot Work
  Finished 323 from 328 footings at the Main Workshop construction site. In operation
  Installed 266 structural columns at the Main Workshop construction site. In operation
  Installed pre cast beams and concrete pouring at the Main Workshop construction site. In operation
  Installed steel columns at the Main Workshop construction site. In operation
  Installed columns and roof structures at the Infrastructure Workshop construction site. In operation
  Installed culverts at the Infrastructure Workshop construction site. In operation
  Installed pre cast slabs and wall concrete pouring at the Infrastructure Workshop construction site. In operation
  Installed 1,796 from 2,384 driven piles (0.18x0.18 m) at the Train Stabling construction site. In operation
  Finished 741 from 1,168 footings at the Train Stabling construction site. In operation
  Installed 1,234 from 2,384 structural columns at the Train Stabling construction site. In operation
  Installed platforms at the Train Stabling construction site. In operation
5 Local Road and Road Flyover Work
  Earth filling work forlocal road. In operation
  Installed U-ditches at the construction site In operation

 

 

Summary Report of The Execution of Contract 1 for June 2016

Contract 1 : Civil Works for Bang Sue Grand Station and Depots
Bill No. Description Contract Amount (BahT) % Progress as of
25-June-16
Status
planned actual
1 General Requirements 266,482,434 84.38% 86.93% 2.55%
2 Track work 11,422,571,521 82.42% 50.93% -31.49%
3 Stations 14,247,067,853 67.93% 36.51% -31.42%
4 LD-Train Depots and CT-Train Depots 1,604,023,818 99.37% 88.22% -11.68%
5 Local Road and Road Flyover 1,410,141,074 99.80% 46.33% -53.47%
6 Provisional Sums and Provisional Items 672,130,000 99.82% 26.69% -73.13%
7 Day-Work Schedule 17,823,300 69.23% 0.00% -69.23%
Total 29,640,240,000 77.61% 45.54% -32.07%

 

 

Summary Table of Construction Plan and Progress of Contract 1 for June 2016

 

 

Contract 2

         Accumulative progress of complete task is 64.27% from the planned target of 67.30%, or 3.03% behind the schedule.

Details of the tasks are provided hereunder:

No. Activity Status
1 Elevated and at Grade Railways Work
  Installed 872 from 875 structural columns for elevated railway. In operation
  Installed 415 from 438 cross beams for the structure of elevated railway. In operation
  Installed 7,255 from 14,303 segments for elevated railway. In operation
  Earth filling, sand embankment and subballast for at-grade railway track. In operation
  Reinforced concrete work for at-grade railway track. In operation
2 Station Work
  Installed aerated concrete walls on ticket hall floor at Samian Nari Temple Station. In operation
  Installed roof structures at Samian Nari Temple Station. Completed
  Installed roof structures at Samian Nari Temple Station. In operation
  Installed aerated concrete walls on ticket hall floor at Bang Khen Station. In operation
  Installed elevators and escalators at Bang Khen Station. In operation
  Installed aerated concrete walls on ticket hall floor at Thung Song Hong Station. In operation
  Installed elevators and escalators at Thung Song Hong Station. In operation
  Concrete pouring for construction of ticket hall at Lak Si Station. In operation
  Installed roof structures at Lak Si Station. In operation
  Installed elevators and escalators at Kan Kheha Station. In operation
  Installed I-Girders for elevated railway at Don Muang Station. In operation
  Concrete pouring for construction of ticket hall floor at Lak Hok Station. In operation
  Installed roof structures at LakHok Station. In operation
  Installed I-Girders for elevated railway at Rangsit Station. In operation
  Concrete pouring for construction of ticket hall at Rangsit Station. In operation
3 Local Road and Road Flyover Work
  Earth filling work for local road In operation
  Construction of drainage system for local road In operation

 

 

Summary Report of The Execution of Contract 2 for June 2016

Contract 2 : Civil Works for Bang Sue - Rangsit Railway
Bill No. Description Contract Amount (BahT) % Progress as of
25-JUNE-16
Status
planned actual
1 General Requirements 272,629,120 85.17% 85.25% 0.08%
2 Track work 12,431,497,987 76.92% 71.93% -4.99%
3 Stations 9,957,755,499 55.44% 53.39% -2.05%
4 Local Road and Road Flyover 1,263,337,028 62.19% 70.16% -7.97%
5 Provisional Sums and Provisional Items - - - -
Total 23,925,219,633 67.30% 64.27% -3.03%

 

 