Construction Supervision of Mass Transit System Project in Bangkok (Red Line) Bang Sue-Rangsit Section
Main Menu About the Project Project Development Public Relations Contact
Public Relations
Progress
Activity Photos

 

  Progress
 

 

Project Progress as of June 2018

 

Contract 1

        Accumulative progress of complete task is 73.27% from the planned target of 74.06%, or 0.78% behind the schedule.

         Details of the tasks are provided hereunder:

 
No. Activity Status
1 Elevated and at Grade Railway Work
  Installed 2,723 from 2,749 beams for the structure of the elevated rail track In operation
  Installed 580 from 932 main precast concrete spans of the elevated rail track In operation
  Demolition of premises In operation
  Relocation of infrastructural systems, i.e. electricity posts, telegraph posts, etc. In operation
2 Stations
  Concrete pouring (Type F1A) of 707 from 753 footings at the Bang Sue Grand Station construction site In operation
  Installed 276 from 305 main precast concrete spans of the elevated rail track at the Bang Sue Grand Station construction site In operation
  Ground and wall concrete pouring for the basement of Bang Sue Grand Station In operation
  Concrete pouring on ticket hall and platform floors at the Bang Sue Grand Station construction site In operation
  Installation of roof structure at Bang Sue Grand Station construction site In operation
  Construction of aerated concrete wall for ticket hall floor at Bang Sue Grand Station construction site In operation
3 LD Train Maintenance Depot
  Interior finishing at the Daily Maintenance Building construction site In operation
  Concrete pouring at the Carriage Shop Building construction site In operation
  Interior finishing at the Passenger Coach Building construction site In operation
4 CT Maintenance Depot
  Interior finishing at the Main Workshop construction site In operation
  Interior finishing at the Infrastructure Workshop construction site In operation
  Installed platforms at the Train Stabling construction site In operation
5 Local Road and Road Flyovers
  Earth filling work for local road In operation
  Installed U-ditches at the construction site In operation

 

 

Summary Report of the Execution of Contract 1 for June 2018 (Early Plan)

Contract 1: Civil Works for Bang Sue Grand Station and Depots
Bill No. Description Contract Amount (Baht) % Progress as of 25 June 2018 Status
planned actual
1 General Requirements 266,482,434 98.24% 97.89% -0.35%
2 Track Work 12,127,119,738 88.17% 96.89% 8.72%
3 Stations 16,823,702,974 64.32% 54.21% -10.11%
4 LD Train Depot and CT Depot 1,604,023,818 100.00% 100.00% -
5 Local Road and Road Flyover 2,393,497,138 59.19% 45.95% -13.24%
6 Provisional sums and Provisional Items 672,130,000 45.81% 18.59% -27.22%
7 Day-Work Schedule 17,823,300 26.09% 0.00% -26.09%
Total 33,904,779,402 74.06% 73.27% -0.78%

 

 

 Summary Table of Construction Plan and Progress of Contract 1 for June 2018

 

Contract 2

          Accumulative progress of complete task is 99.63% from the planned target of 100.00%, or 0.64% behind the schedule

Details of the tasks are provided hereunder:

No. Activity Status
1 Elevated and At-grade Railway
  Installation of boundary fences In operation
2 Stations
  Interior finishing at Wat Samian Nari Station In operation
  Construction of skywalk to Wat Samian Nari Station In operation
  Interior finishing at Bang Khen Station In operation
  Construction of skywalk to Bang Khen Station In operation
  Interior finishing at Thung Song Hong Station In operation
  Construction of skywalk to Thung Song Hong Station In operation
  Interior finishing at Lak Si Station In operation
  Construction of skywalk to Lak Si Station In operation
  Interior finishing at Kan Kheha Station In operation
  Construction of skywalk to Kan Kheha Station In operation
  Construction of sidewalk and improvement of landscape at Don Mueang Station In operation
  Installation of electrical and mechanical systems at Don Mueang Station In operation
  Construction of skywalk to Don Mueang Station In operation
  Interior finishing at Lak Hok Station In operation
  Interior finishing at Rangsit Station In operation
3 Local Road and Road Flyovers
  Earth filling work forlocal road In operation
  Installed the drainage system for the local road In operation

 

 

Summary Report of the Execution of Contract 2 for June 2018

Contract 2: Civil Works for Bang Sue-Rangsit Railway
Bill No. Description Contract
Amount  (Baht)

% Progress as of
25 June 2018

Status
planned actual
1 General Requirements 272,629,119 100.00% 100.00% 0.00%
2 Track Work 12,431,497,987 100.00% 99.99% -0.01%
3 Stations 9,957,755,499 100.00% 98.55% -1.45%
4 Local Road and Road Flyovers 1,263,337,028 100.00% 99.37% -0.63%
5 Provisional Sums and Provisional Items - - - -
Total 23,925,219,633 100.00% 99.36% -0.64%

 

 

 Summary Table of Construction Plan and Progress of Contract 2 for June 2018

Contract 3

Accumulative progress of complete task is 30.29% from the planned target of 55.43% (early plan) and of 48.49% (late plan), or 25.14% and 18.20% behind the early plan and the late plan, respectively.

Details of the tasks are provided hereunder:

No. Activity Status
A 3A Bang Sue-Rangsit and 3B Bang Sue-Taling Chan
1 General Requirements  
1.1 General Management  
1.1.1 Management Plan  
  Company representative details In progress
  Submission of traffic management plan In progress
1.1.2 Facilities and Temporary Access Control  
  Proposal on blocking public utilities management In progress
  Proposal on management of utilities-related agencies In progress
  Proposal on safety system In progress
1.1.3 Traffic Management Plan  
  Proposal on temporary traffic management and road traffic control In progress
  Road and sidewalk reinstatement In progress
1.1.4 Infrastructure   
  Preparation and submission of infrastructure management and plan In progress
  Preparation and submission of detailed proposal on   infrastructure improvement  and management   In progress
2 Engineering Work
2.1 Track Work  
  Production, preparation, and submission of design details In progress
  Production and submission of revised information on design details for approval In progress
  Production, preparation, and submission of factory acceptance test procedure In progress
  Production, preparation, and submission of field testing procedure In progress
2.2 Electrical System
2.2.1 Design of Overhead Catenary System (OCS)  
  Production and submission of revised information on design details for approval In progress
  Production, preparation, and submission of factory acceptance test procedure In progress
  Production, preparation, and submission of field testing procedure In progress
2.2.2 Design of Power Supply and Distribution System (PDS)  
  Preparation and submission of revised information on  preliminary design for approval In progress
  Production and submission of revised information on design details for approval In progress
  Production, preparation, and submission of factory acceptance test procedure In progress
  Production, preparation, and submission of field testing procedure In progress
2.3 Railway Signaling and Control Systems
2.3.1 Operation Control Center (OCC) and Centralized Traffic Control (CTC) System  
  Production and submission of revised information on preliminary design for approval In progress
  Production, preparation, and submission of  design details In progress
2.3.2 Computer Based Interlocking (CBI) System  
  Production and submission of revised information on preliminary design for approval In progress
  Production, preparation, and submission of design details In progress
2.3.3 Automatic Train Protection (ATP) and Automatic Train Operation (ATO)  
  Preparation and submission of information and preliminary design In progress
  Production and submission of revised information on preliminary design for approval In progress
2.3.4 Wayside Equipment (Signal)  
  Preparation and submission of information and preliminary design Completed
  Production and submission of revised information on preliminary design for approval In progress
  Production, preparation, and submission of design details In progress
  Production and submission of revised information on design details for approval In progress
2.4 Telecommunication System
2.4.1 Design of Data Transmission System (DTS)  
  Production and submission of revised information on design details for approval In progress
2.4.2 Design of Radio System  
  Production and submission of revised information on design details for approval In progress
2.4.3 Design of CCTV System  
  Production and submission of revised information on design details for approval In progress
2.4.4 Design of Passenger Information Display System (PIDS)  
  Production and submission of revised information on design details for approval In progress
2.4.5 Design of Public Address (PA) System  
  Production and submission of revised information on design details for approval In progress
2.4.5 Design of Station Management System (SMS)  
  Production and submission of revised information on design details for approval In progress
2.4.6 Design of Train-Borne Communication System (TCS)  
  Production and submission of revised information on design details for approval In progress
2.4.7 Design of Telephone System  
  Production and submission of revised information on design details for approval In progress
2.5 Automatic Fare Collection (AFC) System
  Production and submission of revised information on design details  for approval In progress
  Production, preparation, and submission of factory acceptance test procedure In progress
  Production, preparation, and submission of field testing procedure In progress
2.6 Depot Machinery and Equipment
2.6.1 Design of  LD Train Depot Machinery and Equipment  
  Production, preparation, and submission of design details In progress
2.6.2 Design of CT Depot Machinery and Equipment  
  Preparation and submission of revised information on preliminary design for approval In progress
  Production and submission of revised information on design details for approval In progress
  Production and preparation of revised information of factory acceptance test procedure for approval In progress
2.7 Other Systems
2.7.1 Design of Control Access Security System (CASS)  
  Production and submission of revised information on design details for approval In progress
2.7.2 Design of Operation Automation and Information Technology (OA&IT) System   
  Production and submission of revised information on design details for approval In progress
2.8 Design of Train Car Body
  Preparation and submission of revised information on preliminary design for approval In progress
  Production and preparation of design details In progress
  Production and submission of revised information on design details for approval In progress
2.9 Construction Planning and Design
  Preparation and submission of revised information on preliminary design of the electric power substation for approval In progress
3 Procurement and Recruit of Manufacturers
3.1 Railway Track
  Factory inspection and railway testing In progress
  Transportation of railway tracks In progress
  Factory inspection and track fastener testing In progress
  Transportation of track fasteners In progress
  Factory inspection and ballast stone testing In progress
  Transportation of ballast stones In progress
  Factory inspection and testing of railway turnouts, rail expansion joints, and compromise joints In progress
  Transportation of railway turnouts, rail expansion joints, and compromise joints In progress
  Factory inspection and rubber pad testing In progress
  Transportation of rubber pad  In progress
  Preparation of information, factory inspection and testing, negotiation, and contract signing In progress
  Factory inspection and testing of concrete sleepers for ballastless track system In progress
  Transportation of concrete sleepers for ballastless track system In progress
  Factory inspection and testing of concrete sleepers for ballasted track system In progress
  Transport of concrete sleepers for ballasted track system In progress
3.2 Electrical System
3.2.1 Overhead Catenary System (OCS)  
  Factory inspection and testing of OCS columns and beams In progress
  Transportation of OCS columns and beams In progress
  Transportation of OCS columns and beams to the North Line N1 construction site Completed
  Factory inspection and testing of signal cables In progress
  Factory inspection and testing for associated works In progress
  Factory inspection and testing for other OCS works In progress
3.2.2 Design of Power Supply and Distribution System (PDS)  
  Factory inspection and testing of 115-kV GISS  In progress
  Factory inspection and testing of 115/25-kV traction transformer In progress
  Factory inspection and testing of 115/24-kV power transformer  In progress
  Factory inspection and testing of 25-kV gas-insulated switchgear (GIS) In progress
  Factory inspection and testing of 24-kV switchgear In progress
  Factory inspection and testing of 25-kV auto transformer In progress
  Factory inspection and testing of 25-kV AT switching station  In progress
  Factory inspection and testing of 24/0.4-kV dry-type transformer  In progress
  Factory inspection and testing of 400V emergency diesel generator  In progress
  Factory inspection and testing of power cable  In progress
3.2.3 Supervisory Control and Data Acquisition (SCADA)  
  Factory inspection and testing of SCADA equipment In progress
  Factory inspection and testing off SCADA equipment (ซ้ำกับข้างบน) In progress
3.3 Railway Signaling and Control Systems  
3.3.1 Centralized Traffic Control (CTC) system  
  Factory inspection and CTC system testing In progress
3.3.2 Computer Based Interlocking (CBI)  
  Factory inspection and CBI system testing In progress
3.3.3 Automatic Train Protection (ATP) and Automatic Train Operation (ATO) systems  
  Factory inspection and ATP/ATO system testing In progress
  Factory inspection and on-board ATP/ATO testing In progress
3.4 Telecommunication System
3.4.1 Design of Data Transmission System (DTS)  
  Factory inspection and DTS testing In progress
3.4.2 Design of Radio System  
  Factory inspection and radio system testing In progress
3.4.3 Design of Master Clock (MC) System  
  Factory inspection and MC system testing In progress
3.4.4 Design of CCTV System  
  Factory inspection and CCTV system testing In progress
3.4.5 Design of Passenger Information Display System (PIDS)  
  Factory inspection and PIDS testing In progress
3.4.6 Design of Public Address (PA) System  
  Factory inspection and PA system testing In progress
3.4.7 Design of Station Management System (SMS)  
  Factory inspection and SMS testing In progress
3.4.8 Design of Train-Borne Communication System (TCS)  
  Factory inspection and TCS testing In progress
3.4.9 Design of Telephone System  
  Factory inspection and telephone testing In progress
3.5 Automatic Fare Collection (AFC) System
  Preparation for procurement, factory inspection and testing In progress
3.6 Depot Machinery and Equipment
3.6.1 LD train depot machinery and equipment  
  Preparation of information, factory inspection and testing, negotiation, and contract signing In progress
3.6.2 CT Depot Machinery and Equipment  
  Preparation for procurement, factory inspection, and testing In progress
3.7 Other Associated Systems, including Control Access Security System (CASS), Operation Automation and Information Technology System (OA&IT)
  Preparation for procurement, factory inspection and testing In progress
3.8 Train
3.8.1 Materials and equipment  
  Preparation of information, factory inspection and testing, and negotiation for rolling stock procurement Completed
  Issuance of purchase order (PO) for the rolling stock In progress
  Factory inspection and testing of the rolling stock In progress
  Preparation of information, factory inspection and testing, and negotiation for heating, ventilation, and air conditioning (HVAC) system procurement Completed
  Issuance of purchase order (PO) for the rolling stock (ซ้ำกับข้างบน) In progress
  Preparation of information, factory inspection and testing, and negotiation for heating, ventilation, and air conditioning (HVAC) system procurement (ซ้ำกับข้างบน) In progress
  Preparation of information, factory inspection and testing,  negotiation and contract signing for train procurement In progress
  Preparation of construction standard for coupler and drive system In progress
  Seeking distributor, negotiation, and contract signing for the purchase of coupler and drive procurement In progress
  Preparation of  construction standard for passenger doors In progress
  Seeking distributor, negotiation, and contract signing for passenger door procurement In progress
  Seeking distributor, negotiation, and contract signing for traction transformer procurement Completed
  Issuance of PO for traction transformer In progress
  Factory inspection, and testing for traction transformer In progress
  Preparation of information, factory inspection and testing, and negotiation for traction converter procurement Completed
  Issuance of purchase order (PO) for traction transformer In progress
(ซ้ำกับข้างบน)
  Factory inspection, and testing of traction transformer In progress
  Preparation of information, factory inspection and testing, and negotiation for traction motor procurement Completed
  Issuance of PO for traction motor In progress
  Factory inspection, and testing of traction motor In progress
  Preparation of construction standard for pantograph In progress
  Seeking distributor, negotiation, and contract signing for pantograph procurement In progress
  Seeking distributor, negotiation, and contract signing for APS output transformer box procurement Completed
  Issuance of PO for APS output transformer box In progress
  Factory inspection, and testing for APS output transformer box In progress
  Preparation of construction standard for battery In progress
  Seeking distributor, negotiation, and contract signing for battery procurement In progress
  Seeking distributor, negotiation, and contract signing for train integrated management system (TIMS) procurement Completed
  Issuance of PO for train integrated management system (TIMS) In progress
  Factory inspection, and testing for TIMS In progress
  Preparation of information, factory inspection and testing, and negotiation for brake and air distribution system procurement In progress
3.9 Construction Machinery and Equirpment
  Transportation of construction machinery  to construction site In progress
  Transportation of construction equipment to construction site In progress
4 Construction and Installation 
4.1 North Line (Bang Sue-Rangsit)
4.1.1 N2 (12+201 – 24+826)  
  General Requirements for the North Line  
  N2-A (12+201 – 18+000) Preparation of equipment for construction work (12+201–18+000) In operation
  Railway Track  
  N2-A (24+826 – 29+230) : Flash butt welding (12+201–18+000 (24+826)) In operation
4.1.2 N3 (24+826 – 32+500)  
  Railway Track  
  N3-A (24+826 – 29+230) : : Flash butt welding (24+826 – 29+230 (32+500)) In operation
  N3-A (24+826 – 29+230) : Transportation of welded rails and concrete sleepers to be installed at CT 24+826–29+230, LD 24+826–29+350 In operation
  N3-A (24+826 – 29+230) : Pavement of the first ballast stone layer at CT 24+826–29+230, LD 24+826–29+350 In operation
  N3-A (24+826 – 29+230) : Installation of tracks and concrete sleepers (CT 24+826–29+230, LD 24+826–29+350)  In operation
  Overhead Catenary System (OCS)  
  N3-A (24+826 – 29+230) Installation of OCS posts and equipment  In operation
 (24+826 – 29+230)
  Railway Track  
  N3-B (29+230 – 32+500) : Transportation of welded rails and concrete sleepers to be installed at CT 31+700 – 32+350 In operation
  N3-B (29+230 – 32+500) :  Flash butt welding (29+350 – 32+350) In operation
  N3-B (29+230 – 32+500) : Transportation of  tracks and concrete sleepers to be installed at LD 29+350 – 32+350 In operation
4.1.3 North Line-Power Distribution Substation  
  Power Distribution Substation Construction  
  Pile installation at the construction site of the power distribution substation Completed
  Foundation construction at the construction site of the power distribution substation In operation
  Structure construction at the construction site of the power distribution substation In operation
4.2 West Line  (Bang Sue-Taling Chan)
4.2.1 W1 (9+004 – 17+979)  
  General Requirements -Main Railway  
  W1-B (13+500 – 17+979) : Installation of OOS posts at the base  (15+300 – 17+979) In operation
4.2.2 W1 (9+004 – 17+979)  
  General Requirements -Main Railway  
  W2-A (17+979 – 22+085) : Installation of OOS posts at the base  (17+979 – 22+085) In operation

 

Summary Table of Construction Plan and Progress of Contract 3 for June 2018

 


 
 