Construction Supervision of Mass Transit System Project in Bangkok (Red Line) Bang Sue-Rangsit Section
Main Menu About the Project Project Development Public Relations Contact
Public Relations
Progress
Activity Photos

 

  Progress
 

 

Project Progress as of July 2018

 

Contract 1

        Accumulative progress of complete task is 74.92% from the planned target of 76.12%, or 1.20% behind the schedule.

         Details of the tasks are provided hereunder:

 
No. Activity Status
1 Elevated and At-grade Railway Work
  Installed 2,724 from 2,749 beams for the structure of the elevated rail track In operation
  Installed 613 from 932 main precast concrete spans of the elevated rail track In operation
  Demolition of premises In operation
  Relocation of infrastructural systems, i.e. electricity posts, telegraph posts, etc. In operation
2 Stations
  Concrete pouring (Type F1A) of 710 from 753 footings at the Bang Sue Grand Station construction site In operation
  Installed 282 from 305 main precast concrete spans of the elevated rail track at the Bang Sue Grand Station construction site In operation
  Ground and wall concrete pouring for the basement of the Bang Sue Grand Station construction site In operation
  Concrete pouring on ticket hall and platform floors at the Bang Sue Grand Station construction site In operation
  Installation of roof structure at Bang Sue Grand Station construction site In operation
  Construction of aerated concrete wall for ticket hall floor at Bang Sue Grand Station construction site In operation
3 LD Train Maintenance Depot Work
  Interior finishing at the Daily Maintenance Building construction site In operation
  Concrete pouring at the Carriage Shop Building construction site In operation
  Interior finishing at the Passenger Coach Building construction site In operation
4 CT Maintenance Depot Work
  Interior finishing at the Main Workshop construction site In operation
  Interior finishing at the Infrastructure Workshop construction site In operation
  Installed platforms at the Train Stabling construction site In operation
5 Local Road and Road Flyover Work
  Earth filling work for local road In operation
  Installed U-ditches at the construction site In operation

 

 

Summary Report of the Execution of Contract 1 for July 2018 (Early Plan)

Contract 1: Civil Works for Bang Sue Grand Station and Depots
Bill No. Description Contract Amount (Baht) % Progress as of 25 July 2018 Status
planned actual
1 General Requirements 266,482,434 98.34% 97.89% -0.45%
2 Track Work 12,127,119,738 89.02% 98.24% 9.22%
3 Stations 16,823,702,974 66.99% 55.99% -11.00%
4 LD Train Depots and CT Depots 1,604,023,818 100.00% 100.00% -
5 Local Road and Road Flyover 2,393,497,138 64.34% 49.53% -14.81%
6 Provisional sums and Provisional Items 672,130,000 49.00% 18.59% -30.41%
7 Day-Work Schedule 17,823,300 30.43% 0.00% -30.43%
Total 33,904,779,402 76.12% 74.92% -1.20%

 

 

 Summary Table of Construction Plan and Progress of Contract 1 for July 2018

 

Contract 2

          Accumulative progress of complete task is 99.44% from the planned target of 100.00%, or 0.56% behind the schedule.

Details of the tasks are provided hereunder:

No. Activity Status
1 Elevated and at Grade Railway Work
  Installation of boundary fences In operation
2 Station Work
  Interior finishing at Wat Samian Nari Station In operation
  Construction of skywalk to Wat Samian Nari Station In operation
  Interior finishing at Bang Khen Station In operation
  Construction of skywalk to Bang Khen Station In operation
  Interior finishing at Thung Song Hong Station In operation
  Construction of skywalk to Thung Song Hong Station In operation
  Interior finishing at Lak Si Station In operation
  Construction of skywalk to Lak Si Station In operation
  Interior finishing at Kan Kheha Station In operation
  Construction of skywalk to Kan Kheha Station In operation
  Construction of sidewalk and improvement of landscape at Don Mueang Station In operation
  Installation of electricity and mechanical systems at Don Mueang Station In operation
  Construction of skywalk to Don Mueang Station In operation
  Interior finishing at Lak Hok Station In operation
  Interior finishing at Rangsit Station In operation
3 Local Road and Road Flyover Work
  Earth re-filling work forlocal road In operation
  Drainage system for local road In operation

 

 

Summary Report of the Execution of Contract 2 for July 2018

Contract 2: Civil Works for Bang Sue-Rangsit Railway
Bill No. Description Contract
Amount  (Baht)
% Progress as of 25 July 2018 Status
planned actual
1 General Requirements 272,629,119 100.00% 100.00% 0.00%
2 Track Work 12,431,497,987 100.00% 99.99% -0.01%
3 Stations 9,957,755,499 100.00% 98.74% -1.26%
4 Local Road and Road Flyover 1,263,337,028 100.00% 99.37% -0.63%
5 Provisional Sums and Provisional Items - - - -
Total 23,925,219,633 100.00% 99.44% -0.56%

 

 

 Summary Table of Construction Plan and Progress of Contract 2 for July 2018

Contract 3

Accumulative progress of complete task is 32.42% from the planned target of 57.29% (early plan) and of 50.71% (late plan), or 24.87% and 18.29% behind the early plan and the late plan, respectively.

Details of the tasks are provided hereunder:

No. Activity Status
A 3A Bang Sue-Rangsit and 3B Bang Sue-Taling Chan
1 General Requirements  
1.1 General Management  
1.1.1 Management Plan  
  Preparation and submission of traffic management plan In progress
  Company representative details In progress
  Submission of traffic management plan In progress
1.1.2 Facilities and Temporary Access Control  
  Proposal on blocking public utilities management In progress
  Proposal on management of utilities-related agencies In progress
  Proposal on safety system In progress
1.1.3 Traffic Management Plan  
  Proposal on temporary traffic management and road traffic control Completed
  Design of road and sidewalk reinstatement Completed
1.1.4 Public Utilities System  
  Preparation and submission of public utilities management plan In progress
  Preparation and submission of detailed proposal on improvement of public utilities management   In progress
2 Engineering Work
2.1 Track Work  
  Preparation and submission of construction design for LD  In progress
train depot 
  Preparation and submission of construction design for  skywalk connecting LD train depot  In progress
  Preparation and submission of design information Completed
  Preparation and submission of revised information on design for approval In progress
  Preparation of information, preliminary design, and submission of LD train depot for approval In progress
  Preparation of information, preliminary design, and submission of rail connecting LD train depot  for approval In progress
  Factory acceptance test, preparation and submission of factory acceptance test procedure  In progress
  Field testing, preparation and submission of field testing procedure In progress
2.2 Electrical System
2.2.1 Design of overhead catenary system (OCS)  
  Generation of  sectioning diagram/ feeding diagram design In progress
  Production and submission of revised information on design details for approval In progress
  Production, preparation, and submission of factory acceptance test procedure In progress
  Production, preparation, and submission of field testing procedure In progress
2.2.2 Design of Power Supply and Distribution System (PDS)  
  Preparation and submission of revised information on  preliminary design for approval In progress
  Production and submission of revised information on design details for approval In progress
  Production, preparation, and submission of factory acceptance test procedure In progress
  Production, preparation, and submission of field testing procedure Completed
2.3 Railway Signaling and Control Systems
2.3.1 General Requirements    
  Preparation of preliminary detail for scheme plan In progress
2.3.2 Design of the European Train Control System (ETCS)  
  Generation of preliminary design In progress
  Generation of finalized detailed design In progress
  Approval of preliminary design documents In progress
  Approval of finalized detailed design documents In progress
2.4 Telecommunication System
2.4.1 Design of Data Transmission System (DTS)  
  Preparation and submission of revised information on design for approval In progress
2.4.2 Design of Radio System  
  Preparation and submission of revised information on design for approval Completed
2.4.3 Design of CCTV System  
  Preparation and submission of revised information on design for approval In progress
2.4.4 Design of Passenger Information Display System (PIDS)  
  Preparation and submission of revised information on design for approval In progress
2.4.5 Design of Public Address (PA) System  
  Preparation and submission of revised information on design for approval In progress
2.4.5 Design of Station Management System (SMS)  
  Preparation and submission of revised information on design for approval In progress
2.4.6 Design of Train-Borne Communication System (TCS)  
  Preparation and submission of revised information on design for approval In progress
2.4.7 Design of Telephone System  
  Preparation and submission of revised information on design for approval Completed
2.5 Automatic Fare Collection (AFC) System
  Preparation and submission of revised information on design for approval In progress
  Preparation and submission of factory acceptance test procedure In progress
  Preparation and submission of field testing procedure Completed
2.6 Depot Machinery and Equipment
2.6.1 Design of LD Train Depot Machinery and Equipment  
  Preparation and submission of information on design In progress
  Preparation of information on factory acceptance test procedure In progress
2.6.2 Design of CT Depot Machinery and Equipment  
  Preparation and submission of revised information on preliminary design for approval แล้วเสร็จ
  Production and submission of revised information on design details for approval In progress
  Production and preparation of revised information of factory acceptance test procedure for approval In progress
2.7 Other Systems
2.7.1 Design of Control Access Security System (CASS)  
  Production and submission of revised information on design details for approval In progress
2.7.2 Design of Operation Automation and Information Technology (OA&IT) System   
  Production and submission of revised information on design details for approval In progress
  Preparation of information on factory acceptance test procedure In progress
2.8 Design of Train Car Body 
  Preparation and submission of revised information on preliminary design for approval In progress
  Production and preparation of design details In progress
  Production and submission of revised information on design details for approval In progress
  Preparation of information on factory acceptance test procedure In progress
2.9 Construction Planning and Design
  Preparation and submission of revised information on preliminary design of the electric power substation for approval Completed
3 Procurement and Recruit of Manufacturers
3.1 Railway Track
  Factory inspection and railway testing In progress
  Transportation of railway tracks In progress
  Factory inspection and track fastener testing In progress
  Transportation of track fasteners In progress
  Factory inspection and ballast stone testing In progress
  Transportation of ballast stones In progress
  Factory inspection and testing of railway turnouts, rail expansion joints, and compromise joints In progress
  Transportation of railway turnouts, rail expansion joints, and compromise joints In progress
  Factory inspection and rubber pad testing In progress
  Transportation of rubber pad  In progress
  Preparation of information, factory inspection and testing, negotiation, and contract signing In progress
  Factory inspection and testing of concrete sleepers for ballastless track system In progress
  Transportation of concrete sleepers for ballastless track system In progress
  Factory inspection and testing of concrete sleepers for ballasted track system In progress
  Transport of concrete sleepers for ballasted track system In progress
3.2 Electrical System
3.2.1 Overhead Catenary System (OCS)  
  Factory inspection and testing of OCS columns and beams In progress
  Transportation of OCS columns and beams In progress
  Factory inspection and testing of signal cables In progress
  Factory inspection and testing of associated works In progress
  Factory inspection and testing for other OCS works In progress
3.2.2 Design of Power Supply and Distribution System (PDS)  
  Factory inspection and testing of 115-kV GISS  In progress
  Factory inspection and testing of 115/25-kV traction transformer In progress
  Factory inspection and testing of 115/24-kV power transformer  In progress
  Factory inspection and testing of 25-kV gas-insulated switchgear (GIS) In progress
  Factory inspection and testing of 24-kV switchgear In progress
  Factory inspection and testing of 25-kV auto transformer In progress
  Factory inspection and testing of 25-kV AT switching station  In progress
  Factory inspection and testing of 24/0.4-kV dry-type transformer  In progress
  Factory inspection and testing of 400V emergency diesel generator  In progress
  Factory inspection and testing of power cables In progress
3.2.3 Supervisory Control and Data Acquisition (SCADA)  
  Factory inspection and testing off SCADA equipment In progress
  Factory inspection and testing off SCADA equipment (ซ้ำกับข้างบน) In progress
3.3 Railway Signaling and Control Systems  
 3.3.1  Switch Machine  
  Procurement and factory acceptance test of switch machine  In progress
3.4 Telecommunication System
3.4.1 Data Transmission System (DTS)  
  Factory inspection and testing of DTS In progress
3.4.2 Radio System  
  Factory inspection and testing of radio system In progress
3.4.3 Master Clock (MC) System  
  Factory inspection and testing of MC system  In progress
3.4.4 CCTV System  
  Factory inspection and testing of CCTV system  In progress
3.4.5 Passenger Information Display System (PIDS)  
  Factory inspection and testing of PIDS  In progress
3.4.6 Public Address (PA) System  
  Factory inspection and testing of PA system In progress
3.4.7 Station Management System (SMS)  
  Factory inspection and testing of SMS  In progress
3.4.8 Train-Borne Communication System (TCS)  
  Factory inspection and testing of TCS  In progress
3.4.9 Design of Telephone System  
  Factory inspection and testing of telephone system In progress
3.5 Automatic Fare Collection (AFC) System
  Preparation for system procurement, factory inspection and testing In progress
3.6 Depot Machinery and Equipment
3.6.1 LD train depot machinery and equipment  
  Preparation of information, factory inspection and testing, negotiation, and contract signing In progress
3.6.2 CT Depot Machinery and Equipment  
  Preparation for procurement, factory inspection, and testing In progress
3.7 Other Associated Systems, including Control Access Security System (CASS), Operation Automation and Information Technology System (OA&IT)
  Preparation for procurement, factory inspection and testing In progress
3.8 Train
3.8.1 Materials and equipment  
  Issuance of purchase order (PO) for the rolling stock Completed
  Factory inspection and testing of the rolling stock In progress
  Issuance of purchase order (PO) for the rolling stock (ซ้ำกับข้างบน) Completed
  Preparation of information, factory inspection and testing, and negotiation for heating, ventilation, and air conditioning (HVAC) system procurement Completed
  Preparation of information, factory inspection and testing,  negotiation and contract signing for train procurement In progress
  Preparation of construction standard for coupler and drive system Completed
  Seeking distributor, negotiation, and contract signing for the purchase of coupler and drive procurement In progress
  Seeking distributor, negotiation, and contract signing for passenger door procurement In progress
  Preparation of  construction standard for passenger doors In progress
  Agent procurement, negotiation, and contract signing for passenger doors  In progress
  Preparation of information, factory inspection and testing, and negotiation for passenger door procurement In progress
  Issuance of PO for traction transformer Completed
  Factory inspection and testing of traction transformer In progress
  Issuance of PO for traction converter Completed
  Factory inspection and testing of traction converter In progress
  Issuance of PO for traction motor Completed
  Factory inspection and testing of traction motor In progress
  Preparation of construction standard for pantograph In progress
  Seeking distributor, negotiation, and contract signing for pantograph procurement In progress
  Issuance of PO for APS output transformer box Completed
  Factory inspection and testing of APS output transformer box In progress
  Preparation of construction standard for battery Completed
  Seeking distributor, negotiation, and contract signing for battery procurement In progress
  Issuance of PO for train integrated management system (TIMS) Completed
  Factory inspection, and testing for TIMS In progress
  Preparation of information, factory inspection and testing, negotiation, and contract signing for brake and air distribution system procurement In progress
3.9 Construction Machinery and Tools
  Transportation of construction machinery  to construction site Completed
  Transportation of construction equipment to construction site Completed
4 Construction and Installation 
4.1 North Line (Bang Sue-Rangsit)
4.1.1 N2 (12+201 – 24+826)  
  General Requirements for the North Line  
  N2-A (12+201 – 18+000) Preparation of equipment for construction work (12+201–18+000) In operation
  Railway Track  
  N2-A (24+826 – 29+230) : Flash butt welding (12+201–18+000 (24+826)) In operation
4.1.2 N3 (24+826 – 32+500)  
  Railway Track  
  N3-A (24+826 – 29+230) Flash butt welding (24+826 – 29+230 (32+500)) Completed
  N3-A (24+826 – 29+230) Transportation of welded rails and concrete sleepers to be installed at CT 24+826–29+230, LD 24+826–29+350 In operation
  N3-A (24+826 – 29+230) Pavement of the first ballast stone layer at CT 24+826–29+230, LD 24+826–29+350 In operation
  N3-A (24+826 – 29+230) Installation of tracks and concrete sleepers (CT 24+826–29+230, LD 24+826–29+350)  In operation
  Overhead Catenary System (OCS)  
  N3-A (24+826 – 29+230) : ) Installation of OCS posts and equipment (24+826 – 29+230) Completed
  Railway Track  
  N3-B (29+230 – 32+500) Transportation of welded rails and concrete sleepers to be installed at CT 31+700 – 32+350 In operation
  N3-B (29+230 – 32+500) :  Flash butt welding (29+350 – 32+350) In operation
  N3-B (29+230 – 32+500) : Transportation of welded rails and concrete sleepers to be installed at LD 29+350 – 32+350 In operation
4.1.3 North Line-Power Distribution Substation  
  Power Distribution Substation Construction  
  Foundation construction at the construction site of the power distribution substation Completed
  Structure construction at the construction site of the power distribution substation In operation
  Installation of system work equipment and decoration In operation
4.2 West Line  (Bang Sue-Taling Chan)
4.2.1 W1 (9+004 – 17+979)  
  General Requirements -Main Railway  
  W1-B (13+500 – 17+979) : Installation of OOS posts at the base   (15+300 – 17+979) Completed
  W1-B (13+500 – 17+979) : Installation of OOS posts at the base   (13+500 – 17+979) In operation
4.2.2 W1 (9+004 – 17+979)  
  General Requirements -Main Railway  
  W2-A (17+979 – 22+085) : Installation of OOS posts at the base (17+979 – 22+085) In operation

 

Summary Table of Construction Plan and Progress of Contract 3 for July 2018

 


 
 