Construction Supervision of Mass Transit System Project in Bangkok (Red Line) Bang Sue-Rangsit Section
Main Menu About the Project Project Development Public Relations Contact
Public Relations
Progress
Activity Photos

 

  Progress
 

 

Project Progress as of August 2018

 

Contract 1

        Accumulative progress of complete task is 76.07% from the planned target of 78.16%, or 2.09% behind the schedule.

         Details of the tasks are provided hereunder:

 
No. Activity Status
1 Elevated and At-grade Railway Work
  Installed 2,732 from 2,753 beams for the structure of the elevated rail track In operation
  Installed 670 from 932 main precast concrete spans of the elevated rail track In operation
  Demolition of premises In operation
  Relocation of infrastructural systems, i.e. electricity posts, telegraph posts, etc. In operation
2 Stations
  Concrete pouring (Type F1A) of 712 from 753 footings at the Bang Sue Grand Station construction site In operation
  Installed 297 from 303 main precast concrete spans of the elevated rail track at the Bang Sue Grand Station construction site In operation
  Ground and wall concrete pouring for the basement of the Bang Sue Grand Station construction site In operation
  Concrete pouring on ticket hall and platform floors at the Bang Sue Grand Station construction site In operation
  Installation of roof structure at Bang Sue Grand Station construction site In operation
  Construction of aerated concrete wall for ticket hall floor at Bang Sue Grand Station construction site In operation
3 LD Train Maintenance Depot Work
  Interior finishing at the Daily Maintenance Building construction site In operation
  Concrete pouring at the Carriage Shop Building construction site In operation
  Interior finishing at the Passenger Coach Building construction site In operation
4 CT Maintenance Depot Work
  Interior finishing at the Main Workshop construction site In operation
  Interior finishing at the Infrastructure Workshop construction site In operation
  Installed platforms at the train stabling construction site In operation
5 Local Road and Road Flyover Work
  Earth filling work for local road In operation
  Installed U-ditches at the construction site In operation

 

 

Summary Report of the Execution of Contract 1 for August 2018 (Early Plan)

Contract 1: Civil Works for Bang Sue Grand Station and Depots
Bill No. Description Contract Amount (Baht) % Progress as of 25 August 2018 Status
planned actual
1 General Requirements 266,482,434 98.45% 97.89% -0.56%
2 Track Work 12,127,119,738 89.87% 99.57% 9.70%
3 Stations 16,823,702,974 66.67% 57.20% -12.47%
4 LD Train Depots and CT Depots 1,604,023,818 100.00% 100.00% -
5 Local Road and Road Flyover 2,393,497,138 69.27% 50.45% -18.82%
6 Provisional sums and Provisional Items 672,130,000 52.19% 18.59% -33.60%
7 Day-Work Schedule 17,823,300 34.78% 0.00% -34.78%
Total 33,904,779,402 78.16% 76.07% -2.09%

 

 

 Summary Table of Construction Plan and Progress of Contract 1 for August 2018

 

Contract 2

          Accumulative progress of complete task is 99.46% from the planned target of 100.00%, or 0.54% behind the schedule.

Details of the tasks are provided hereunder:

No. Activity Status
1 Elevated and at Grade Railway Work
  Installation of boundary fences In operation
2 Station Work
  Interior finishing at Wat Samian Nari Station In operation
  Construction of skywalk to Wat Samian Nari Station In operation
  Interior finishing at Bang Khen Station In operation
  Construction of skywalk to Bang Khen Station In operation
  Interior finishing at Thung Song Hong Station In operation
  Construction of skywalk to Thung Song Hong Station In operation
  Interior finishing at Lak Si Station In operation
  Construction of skywalk to Lak Si Station In operation
  Interior finishing at Kan Kheha Station In operation
  Construction of skywalk to Kan Kheha Station In operation
  Construction of sidewalk and improvement of landscape at Don Mueang Station In operation
  Installation of electricity and mechanical systems at Don Mueang Station In operation
  Construction of skywalk to Don Mueang Station In operation
  Interior finishing at Lak Hok Station In operation
  Interior finishing at Rangsit Station In operation
3 Local Road and Road Flyover Work
  Earth re-filling work forlocal road In operation
  Drainage system for local road In operation

 

 

Summary Report of the Execution of Contract 2 for August 2018

Contract 2: Civil Works for Bang Sue-Rangsit Railway
Bill No. Description Contract
Amount  (Baht)
% Progress as of 25 August 2018 Status
planned actual
1 General Requirements 272,629,119 100.00% 100.00% 0.00%
2 Track Work 12,431,497,987 100.00% 99.99% -0.01%
3 Stations 9,957,755,499 100.00% 98.81% -1.19%
4 Local Road and Road Flyover 1,263,337,028 100.00% 99.37% -0.63%
5 Provisional Sums and Provisional Items - - - -
Total 23,925,219,633 100.00% 99.46% -0.54%

 

 

  Summary Table of Construction Plan and Progress of Contract 2 for August 2018

Contract 3

Accumulative progress of complete task is 34.77% from the planned target of 59.07% (early plan) and of 53.01% (late plan), or 24.30% and 18.24% behind the early plan and the late plan, respectively.

Details of the tasks are provided hereunder:

No. Activity Status
1 General Management In progress 
1.1 Management Plan In progress 
1.2 Facilities and Temporary Access Control In progress  
1.3 Public Utilities System In progress 
2 Engineering Work In progress
2.1 Track Work In progress 
2.2 Electrical System In progress
2.2.1 Design of overhead catenary system (OCS) In progress 
2.2.2 Design of Power Supply and Distribution System (PDS) In progress  
2.3 Railway Signaling and Control Systems In progress
2.3.1 All Signalling (ETCS)  In progress
2.4 Telecommunication System In progress
2.4.1 Design of Data Transmission System (DTS) In progress
2.4.2 Design of Radio System In progress 
2.4.3 Design o Master Clock (MC) System In progress 
2.4.4 Design of CCTV System In progress  
2.4.5 Design of Passenger Information Display System (PIDS) In progress 
2.4.6 Design of Public Address (PA) System In progress
2.4.7 Design of Station Management System (SMS) In progress 
2.4.8 Design of Train-Borne Communication System (TCS) In progress 
2.4.9 Design of Telephone System In progress 
2.5 Design of Automatic Fare Collection (AFC) System In progress  
2.6 Depot Machinery and Equipment In progress 
2.6.1 Design of LD Train Depot Machinery and Equipment In progress
2.6.2 Design of CT Depot Machinery and Equipment In progress 
2.7 Other Systems In progress 
2.7.1 Design of Control Access Security System (CASS) In progress 
2.7.2 Design of Operation Automation and Information Technology (OA&IT) System In progress  
2.8 Design of Train Car Body In progress 
2.9 Construction Planning and Design In progress
3 Procurement and Recruit of Manufacturers In progress 
3.1 Railway Track In progress 
3.2 Electrical System In progress  
3.2.1 Overhead Catenary System (OCS) In progress 
3.2.2 Design of Power Supply and Distribution System (PDS) In progress
3.2.3 Supervisory Control and Data Acquisition (SCADA) In progress 
3.3 Railway Signaling and Control Systems In progress 
 3.3.1  Switch Machine In progress 
3.4 Telecommunication System In progress  
3.4.1 Data Transmission System (DTS) In progress 
3.4.2 Radio System In progress 
3.4.3 Master Clock (MC) System In progress  
3.4.4 CCTV System In progress 
3.4.5 Passenger Information Display System (PIDS) In progress
3.4.6 Public Address (PA) System In progress 
3.4.7 Station Management System (SMS) In progress
3.4.8 Train-Borne Communication System (TCS) In progress 
3.4.9 Design of Telephone System In progress  
3.5 Automatic Fare Collection (AFC) System In progress
3.6 Depot Machinery and Equipment In progress 
3.6.1 LD train depot machinery and equipment In progress 
3.6.2 CT Depot Machinery and Equipment In progress  
3.7 Other Associated Systems, including Control Access
Security System (CASS), Operation Automation and
Information Technology System (OA&IT)
In progress 
3.8 Train In progress
3.8.1 Materials and equipment In progress 
4 Construction and Installation In progress 
4.1.1 Railway Track In progress  
4.1.2 Power Distribution Substation In progress 

 

Summary Report of the Execution of Contract 3 for August 2018

 


 
 