Construction Supervision of Mass Transit System Project in Bangkok (Red Line) Bang Sue-Rangsit Section
Main Menu About the Project Project Development Public Relations Contact
Public Relations
Progress
Activity Photos

 

  Progress
 

 

Project Progress as of September 2016

 

Contract 1

    Accumulative progress of complete task is 50.49% from the planned target of 88.75%, or 38.26% behind the schedule.

Details of the tasks are provided hereunder:

No. Activity Status
1 Elevated and at Grade Railways Work
  Concrete pouring of 698 footings from the target of 698 footings for elevated railway Completed
  Installed columns for the structure of the elevated rail track In operation
  Installed beams for the structure of the elevated rail track In operation
  Installed main pre-cast concrete compotents of the elevated rail track In operation
  Demolition of premises. In operation
  Relocation of infrastructural systems, i.e. electricity posts, telegraph posts, etc. In operation
2 Station Work
  Land excavation of 254,496 cu.m from the target of 293,314 cu.m for foundation works of the Grand Station. In operation
  Installed 607 from 623 bored piles (diameter = 800 mm) at the Bang Sue Grand Station construction site. In operation
  Installed 1,109 from 1,232 bored piles (diameter = 1,000 mm) (including piles for approach) at the Bang Sue Grand Station construction site. In operation
  Installed 256 from 257 bored piles (diameter = 1,200 mm) at the Bang Sue Grand Station construction site. In operation
  Installed 122 from 123 bored piles (diameter = 2,000 mm) at the Bang Sue Grand Station construction site. In operation
  Lean concrete pouring of 152 from 160 footings at the Bang Sue Grand Station construction site. In operation
  Concrete pouring (Type F1A) of 619 from 632 footings at the Bang Sue Grand Station construction site. In operation
  Installed structural columns and beams at the Bang Sue Grand Station construction site. In operation
  Installed concrete components of elevated structures at the Bang Sue Grand Station construction site. In operation
  Ground and wall concrete pouring for the basement of the Bang Sue Grand Station construction site In operation
  Installed structural columns at the Chatuchak Station construction site. In operation
3 LD Train Maintenance Depot Work
  Wall masonry and plastering at the Daily Maintenance construction site. In operation
  Installed steel structure for hallway at the Daily Maintenance construction site. In operation
  Installed 1,547 from 1,596 driven piles (0.40x0.40 m) at the Passenger Coach construction site. In operation
  Installed steel columns and roof structures at the Passenger Coach construction site. In operation
  Concrete pouring at the Passenger Coach construction site. In operation
  Wall masonry and plastering at the Passenger Coach construction site. In operation
4 CT Train Maintenance Depot Work
  Installed 266 structural columns at the Main Workshop construction site. In operation
  Installed pre cast beams and concrete pouring at the Main Workshop construction site. In operation
  Installed steel columns at the Main Workshop construction site. In operation
  Installed culverts at the Infrastructure Workshop construction site. In operation
  Installed pre cast slabs and wall masonry at the Infrastructure Workshop construction site. In operation
  Installed 1,796 from 2,384 driven piles (0.18x0.18 m) at the Train Stabling construction site. In operation
  Finished 741 from 1,168 footings at the Train Stabling construction site. In operation
  Installed 1,234 from 2,384 structural columns at the Train Stabling construction site. In operation
  Installed platforms at the Train Stabling construction site. In operation
5 Local Road and Road Flyover Work
  Earth filling work forlocal road. In operation
  Installed U-ditches at the construction site In operation

 

 

Summary Report of The Execution of Contract 1 for September 2016

Contract 1 : Civil Works for Bang Sue Grand Station and Depots
Bill No. Description Contract Amount (BahT) % Progress as of
25-september-16
Status
planned actual
1 General Requirements 266,482,434 90.76% 91.03% 0.26%
2 Track work 11,422,571,521 91.91% 58.86% -33.05%
3 Stations 14,247,067,853 83.30% 39.94% -43.35%
4 LD-Train Depots and CT-Train Depots 1,604,023,818 100.00% 91.24% -8.76%
5 Local Road and Road Flyover 1,410,141,074 99.88% 47.28% -52.60%
6 Provisional Sums and Provisional Items 672,130,000 100.00% 26.69% -73.31%
7 Day-Work Schedule 17,823,300 80.77% 0.00% -80.77%
Total 29,640,240,000 88.75% 50.49% -38.26%

 

 

Summary Table of Construction Plan and Progress of Contract 1 for September 2016

 

 

Contract 2

         Accumulative progress of complete task is 74.17% from the planned target of 77.22%, or 3.05% behind the schedule.

Details of the tasks are provided hereunder:

No. Activity Status
1 Elevated and at Grade Railways Work
  Installed 474 from 474 cross beams for the structure of elevated railway. Completed
  Installed 8,100 from 14,303 segments for elevated railway. In operation
  Earth filling, sand embankment and subballast for at-grade railway track. In operation
  Installation of boundary fences In operation
2 Station Work
  Demolition of 3 Hopewell’s structural columns for construction of skywalk at Samian Nari Temple Station  (Type 3 = 2 columns/ Type 14B = 1 column) In operation
  Installed aerated concrete walls on ticket hall floor at Samian Nari Temple Station. In operation
  Flooring tiling work at Samian Nari Temple Station. In operation
  Installed steel structure for entrance staircases at Samian Nari Temple Station. In operation
  Installed elevators and escalators at Samian Nari Temple Station. In operation
  Installed electricity and mechanical systems at Samian Nari Temple Station. In operation
  Demolition of 5 Hopewell’s structural columns for construction of skywalk at Bang Khen Station  (Type 1A = 1 column/ Type 5A = 1 column/ Type 14A = 1 column/ Type 14B = 1 column/ Type 15B = 1 column) In operation
  Installed aerated concrete walls on ticket hall floor at Bang Khen Station. In operation
  Flooring tiling work at Bang Khen Station. In operation
  Installed elevators and escalators at Bang Khen Station. In operation
  Installed electricity and mechanical systems at Bang Khen Station. In operation
  Demolition of 4 Hopewell’s structural columns for construction of skywalk at Thung Song Hong Station  (Type 3 = 2 columns/ Type 16A = 2 columns) In operation
  Installed aerated concrete walls on ticket hall floor at Thung Song Hong Station. In operation
  Flooring tiling work at Thung Song Hong Station. In operation
  Installed electricity and mechanical systems at Thung Song Hong Station. In operation
  Installed aerated concrete walls on ticket hall floor at Lak Si Station. In operation
  Installed steel structure for entrance staircases at Lak Si Station. In operation
  Installed electricity and mechanical systems at Lak Si Station. In operation
  Installed aerated concrete walls on ticket hall floor at Kan Kheha Station. In operation
  Installed steel structure for entrance staircases at Kan Kheha Station. In operation
  Installed elevators and escalators at Kan Kheha Station. In operation
  Installed I-Girders for elevated railway at Don Muang Station. In operation
  Concrete pouring for construction of ticket hall floor at Don Muang Station. In operation
  Installed steel roof structure at Don Muang Station. In operation
  Installed steel structure for entrance staircases at Don Muang Temple Station. In operation
  Concrete pouring for construction of ticket hall floor at Lak Hok Station. Completed
  Installed roof structures at Lak Hok Station. In operation
  Installed aerated concrete walls on ticket hall floor at Lak Hok Station. In operation
  Installed elevators and escalators at Lak Hok Station. In operation
  Concrete pouring for construction of ticket hall at Rangsit Station. In operation
  Installed roof structures at Rangsit Station. In operation
  Installed aerated concrete walls on ticket hall floor at Rangsit Station. In operation
3 Local Road and Road Flyover Work
  Earth filling work for local road In operation
  Construction of drainage system for local road In operation

 

 

Summary Report of The Execution of Contract 2 for September 2016

Contract 2 : Civil Works for Bang Sue - Rangsit Railway
Bill No. Description Contract Amount (BahT) % Progress as of
25-september-16
Status
planned actual
1 General Requirements 272,629,120 89.58% 91.44% 1.86%
2 Track work 12,431,497,987 84.26% 81.53% -2.73%
3 Stations 9,957,755,499 67.15% 63.74% -3.41%
4 Local Road and Road Flyover 1,263,337,028 84.66% 80.26% -4.40%
5 Provisional Sums and Provisional Items - - - -
Total 23,925,219,633 77.22% 74.17% -3.05%

 

 

Summary Table of Construction Plan and Progress of Contract 2 for September 2016

Contract 3

Contractor in Contract 3 was designated to commence its assignment on 28 June 2016 and started its operation from 28 July – 25 August 2016.

              Accumulative progress of complete task is 2.06% from the planned target of 2.61%, or 0.55% behind the schedule.

              Details of the tasks are provided hereunder:

No. Activity Status
A. 3A Bang Sue-Rangsit
1 Project Management  
  Project Management Plan – Implement and submit Implementationand Submitting
  Contractors’ plans – Implement and submit
  Quality assurance plan – Implement and submit
  Safety system plan  – Implement and submit
  EMC Managemnt Plan – Implement and submit
  Quality assurance software – Implement and submit
  Procurement and production plan – Implement and submit
  Engineering plan – Implement and submit
  Investigation plan before, during and after working – Implement and submit
  Procurement, production and deilvery plan – Implement and submit
  Details of representative  – Implement and submit
  Health and safety plan of contactors – Implement and submit
  Enviromnetal management plan – Implement and submit
  Environemntal mitigation schedule – Implement and submit
  Traffic management – Implement and submit
2 Constrol of temporary construction facility  
  Proposal for preventive and avoidance issues – Implement and submit In operation
3 Project and report  
  Project Description In operation
  Full proposal
  Procurement and production  
4 Standard plan and procedure  
  Implement and submit In operation
5 Engineering  
5.1 Trackwork  
  Survey and reaffirm the requirements of trackwork in pursuant to the construction in contract 1 and 2 In operation
  Data preparation, and preliminary design
5.2 Design of OCS  
  Survey and reaffirm the requirements of OCS in pursuant to the construction in contract 1 and 2 In operation
  Data preparation, and preliminary design
5.3 Design of electricial power  
  Survey and reaffirm the requirements of electrical power in pursuant to the construction in contract 1 and 2 In operation
  Data preparation, and preliminary design
5.4 Design of OCC CTC systems  
  Survey and reaffirm the requirements of construction work in pursuant to the construction in contract 1 and 2 In operation
  Data preparation, and preliminary design
5.5 Design of Computer Based Interlocking (CBI) system  
  Survey and reaffirm the requirements in pursuant to the construction in contract 1 and 2 In operation
  Data preparation and preliminary design
5.6 Design of ATP/ATO system  
  Survey and reaffirm the requirements in pursuant to the construction in contract 1 and 2 In operation
  Data preparation, and preliminary design
5.7 Design of Wayside Equipment (Signal)  
  Survey and reaffirm the requirements in pursuant to the construction in contract 1 and 2 In operation
  Data preparation, and preliminary design
5.8 Design of Data Transmission System (DTS)  
  Survey and reaffirm the requirements in pursuant to the construction in contract 1 and 2 In operation
  Data preparation, and preliminary design
5.9 Design of Radio System  
  Survey and reaffirm the requirements in pursuant to the construction in contract 1 and 2 In operation
  Data preparation, and preliminary design
5.10 Design of Master Clock System (MC)  
  Survey and reaffirm the requirements in pursuant to the construction in contract 1 and 2 In operation
  Data preparation, and preliminary design
5.11 Design of CCTV System  
  Survey and reaffirm the requirements in pursuant to the construction in contract 1 and 2 In operation
  Data preparation, and preliminary design
5.12 Design of Passenger Information Display System (PIDS)  
  Survey and reaffirm the requirements in pursuant to the construction in contract 1 and 2 In operation
  Data preparation, and preliminary design
5.13 Design of Public Address System (PA)  
  Survey and reaffirm the requirements in pursuant to the construction in contract 1 and 2 In operation
  Data preparation, and preliminary design
5.14 Design of Station Management System (SMS)  
  Survey and reaffirm the requirements in pursuant to the construction in contract 1 and 2 In operation
  Data preparation, and preliminary design
5.15 Design of Train-Bome Communication System (TCS)  
  Survey and reaffirm the requirements in pursuant to the construction in contract 1 and 2 In operation
  Data preparation, and preliminary design
5.16 Design of telephone communication system  
  Survey and reaffirm the requirements in pursuant to the construction in contract 1 and 2 In operation
  Data preparation, and preliminary design
5.17 Design of Automatic Fare Collection System (AFC)
  Survey and reaffirm the requirements of Autometic Fare Collection System (AFC) in pursuant to the construction in contract 1 and 2 In operation
  Data preparation, and preliminary design
5.18 Design of equipment and machinery for maintenance depot
  Survey and reaffirm the requirements of equipment and machinery for maintenance depot in pursuant to the construction in contract 1 and 2 In operation
  Data preparation, and preliminary design
5.19 Design of CASS and QA&TI  
  Survey and reaffirm the requirements of CASS and QA&TI in pursuant to the construction in contract 1 and 2 In operation
  Data preparation, and preliminary design
5.20 Design of electric railway cars
  Survey and reaffirm the requirements of electric railway cars in pursuant to the construction in contract 1 and 2 In operation
  Data preparation, and preliminary design
5.21 Design for existing track relocation and replacement  
  Survey, data preparation, and preliminary design In operation
5.22 Submitting of equipment, machinery, appliances descriptions in accordance with the standard procedures of construction contract In operation
B. 3B Bang Sue-Taling Chan  
1 Survey of construction site of the project In operation

Summary Table of Construction Plan and Progress of Contract 3 for September 2016



 
 