Construction Supervision of Mass Transit System Project in Bangkok (Red Line) Bang Sue-Rangsit Section
Main Menu About the Project Project Development Public Relations Contact
Public Relations
Progress
Activity Photos
  Progress
 

 

October 2013

 

Contract 1

Tasks that have been implemented included clearing, grubbing and land levelling of area in zone 1 and zones 3-5 near the Bang Sue Grand Station; land excavation for foundation works of the Grand Station, installation of bored piles for the construction of station building; demolition of structures at stabling yard, and removal of railway tracks, traffic management for rail track removal in zone 3; construction of site access road in zone 3; and construction of local roads in zone 5. Plus many others tasks as detailed hereunder:

No. Activity Status
1 Control surveys Completed
2 Land Levelling In operation
3 Preparation of mobilization work (Site office, vehicles and equipment) Completed
4 Land excavation for foundation works of the Grand Station In operation
5 Demolition of Hopewell’s 113 structural columns(Type 1A Case 1=14 columns/Type 2B Case 1=1 column/ Type 3A Case 1=45columns/ Type 3B Case 1=10 columns/Type 4 Case 1 =2 columns/ Type 12 Case 2=18columns/ Type 13 Case 2 =16columns/ Type 14 Case 3 =5 columns/ Type 15 Case 3 =2 columns) In operation
6 Testing work of 3 Pilot piles (diameter = 1,500 mm)
(at Terd Damri Road at MRTA parking lot and at local road near Samian Nari Temple).
Completed
7 Testing work of Pilot pile (diameter = 1,200 mm)
at the construction site of the Bang Sue Grand Station.
Completed
8 Testing work of Pilot pile (diameter = 500 mm)
at the construction site of the LD Depots.
In operation
9 Pile testing of the existing Hopewell structures at local road near Samian Nari Temple. Completed
10 Batching Plant investigation. In operation
11 Concrete Mixed Designinvestigation. In operation
12 Aggregate sourceinvestigation. In operation
13 Bored pile plantinvestigation. In operation
14 Demolition of premises. In operation
15 Relocation of infrastructural systems, i.e. electricity posts, telegraph posts, etc. In operation
16 Removal of concrete surface. In operation
17 Construction of 410 bored piles (diameter = 1,500 mm) at the Bang Sue Grand Station site. In operation
18 Construction of 44 bored piles (diameter = 500 mm) atLD Passenger Coach construction site. In operation
19 Removal of railway tracksat the Bang Sue Grand Station site. In operation

 

Contract 2

The tasks include: land levelling, site preparation (site office, vehicles and equipment), pile testing, installation of bored piles for the construction of elevated railway, driven piling work for at-grade railway, demolition of structures.Details of the tasks are provided hereunder:

No. Activity Status
1 Control surveys Completed
2 Land Levelling In operation
3 Preparation of mobilization work (Site office, vehicles and equipment) In operation
4 Demolition of Hopewell’s 377 structural columns
(Type 1 Case 1 = 1column/ Type 1A Case 1 = 28columns/ Type 2A Case 1 = 3columns/ Type 2B Case 1 = 1column/ Type 3A Case 1 = 83 columns/ Type 4 Case 1 = 18 columns/ Type 6 Case 1 = 1 column/ Type 5A Case 2 = 3 columns/ Type 5B Case 2 = 1 column/ Type 7 Case 2 = 7columns/ Type 8 Case 2 = 70  columns/ Type 9 Case 2 = 1 column/ Type 10 Case 2 = 4 columns/  Type 11 Case 2 = 84columns/  Type 16 Case 2 = 42 columns/Type 16A Case 2 = 18 columns/ Type 16B Case 2 = 9 columns/ Type 19 Case 2 = 3 columns)
In operation
5
  • Testing work of Pilot pile (diameter = 1,500 mm) at 4 areas: 1) Lak Si area (Sta. 17+500), 2) Near Don Muang District Office (Sta. 20+600), 3) Near the entrance of Grand Canal Village (Sta. 24+600), and 4) at Rangsit Railway Station (Sta. 29+800).
  • Testing work of Pilot pile (diameter = 1,200 mm) near the entrance of Grand Canal Village (Sta. 24+600).
Completed
6 Pile testing of the existing Hopewell structures at local road near Chulabhorn Research Institute (CRI). Completed
7 Installation of 182 bored piles (diameter = 1,500 mm) In operation
8 Construction of 5 footing works for the elevated railway. In operation
9 Batching plantinvestigation. In operation
10 Concrete Mixed Designinvestigation. In operation
11 Aggregate sourceinvestigation. In operation
12 Asphalt plantinvestigation. In operation
13 Bored pile plant investigation. In operation
14 Demolition of existing railway stations (Bang Khen and Lak Si). In operation
15 Work on 704 driven piles (0.35 x 0.35 meters). In operation
16 Work on 259 driven piles (0.22 x 0.22 meters) for
at-grade railway
track.
In operation
17 Earth filling work for at-grade railway track. In operation
18 Removal of railway track at the Rangsit Station site. In operation
19 Earth filling work forlocal roads. In operation

 
 