Construction Supervision of Mass Transit System Project in Bangkok (Red Line) Bang Sue-Rangsit Section
Main Menu About the Project Project Development Public Relations Contact
Public Relations
Progress
Activity Photos

 

  Progress
 

 

Project Progress as of October 2018

 

Contract 1

        Accumulative progress of complete task is 78.95% from the planned target of 82.20%, or 3.25% behind the schedule.

         Details of the tasks are provided hereunder:

 
No. Activity Status
1 Elevated and at Grade Railway Work
  Installed 2,752 from 2,753 beams for the structure of the elevated rail track In operation
  Installed 745 from 933 main precast concrete spans of the elevated rail track In operation
  Demolition of premises In operation
  Relocation of infrastructural systems, i.e. electricity posts, telegraph posts, etc. In operation
2 Stations
  Concrete pouring (Type F1A) of 720 from 753 footings at the Bang Sue Grand Station construction site In operation
  Installed 296 from 303 main precast concrete spans of the elevated rail track at the Bang Sue Grand Station construction site In operation
  Ground and wall concrete pouring for the basement of the Bang Sue Grand Station construction site In operation
  Concrete pouring on ticket hall and platform floors at the Bang Sue Grand Station construction site In operation
  Installation of structural roof at Bang Sue Grand Station construction site In operation
  Construction of aerated concrete wall for ticket hall floor at Bang Sue Grand Station construction site In operation
3 LD Train Maintenance Depot Work
  Interior finishing at the Daily Maintenance Building construction site In operation
  Concrete pouring at the Carriage Shop Building construction site In operation
  Interior finishing at the Passenger Coach Building construction site In operation
4 CT Maintenance Depot Work
  Interior finishing at the Main Workshop construction site In operation
  Interior finishing at the Infrastructure Workshop construction site In operation
  Installed platforms at the Train Stabling construction site In operation
5 Local Road and Road Flyover Work
  Earth filling work for local road In operation
  Installed U-ditches at the construction site In operation

 

 

Summary Report of the Execution of Contract 1 for October 2018 (Early Plan)

Contract 1: Civil Works for Bang Sue Grand Station and Depots
Description Contract Amount (Baht) % Progress as of 25 October 2018 Status
planned actual
1 General Requirements 266,482,434 98.65% 97.89% -0.76%
2 Track Work 12,127,119,738 91.52% 99.57% 8.05%
3 Stations 16,823,702,974 74.97% 60.82% -14.15%
4 LD Train Depots and CT Depots 1,604,023,818 100.00% 100.00% 0.00%
5 Local Road and Road Flyover 2,393,497,138 78.96% 52.52% -26.44%
6 Provisional sums and Provisional Items 672,130,000 58.56% 18.59% -39.97%
7 Day-Work Schedule 17,823,300 43.48% 0.00% -43.48%
รวม 33,904,779,402 82.20% 78.95% -3.25%

 

 

Summary Table of Construction Plan and Progress of Contract 1 for October 2018

 

Contract 2

          Accumulative progress of complete task is 99.47% from the planned target of 100.00%, or 0.53% behind the schedule

Details of the tasks are provided hereunder:

No. Activity Status
1 Elevated and at Grade Railway Work
  Installation of boundary fences In operation
2 Station Work
  Interior finishing at Wat Samian Nari Station In operation
  Construction of skywalk to Wat Samian Nari Station In operation
  Interior finishing at Bang Khen Station In operation
  Construction of skywalk to Bang Khen Station In operation
  Interior finishing at Thung Song Hong Station In operation
  Construction of skywalk to Thung Song Hong Station In operation
  Interior finishing at Lak Si Station In operation
  Construction of skywalk to Lak Si Station In operation
  Interior finishing at Kan Kheha Station In operation
  Construction of skywalk to Kan Kheha Station In operation
  Construction of sidewalk and improvement of landscape at Don Mueang Station Completed
  Installation of electricity and mechanical systems at Don Mueang Station In operation
  Construction of skywalk to Don Mueang Station In operation
  Interior finishing at Lak Hok Station In operation
  Interior finishing at Rangsit Station In operation
3 Local Road and Road Flyover Work
  Earth filling work for local road Completed
  Drainage system for local road Completed

 

 

Summary Report of the Execution of Contract 2 for October 2018

Contract 2: Civil Works for Bang Sue-Rangsit Railway
Description Contract
Amount  (Baht)
% Progress as of 25 October 2018 Status
planned actual
1 General Requirements 272,629,119 100.00% 100.00% 0.00%
2 Track Work 12,431,497,987 100.00% 99.99% -0.01%
3 Stations 9,957,755,499 100.00% 98.81% -1.19%
4 Local Road and Road Flyover 1,263,337,028 100.00% 99.37% -0.63%
5 Provisional Sums and Provisional Items - - - -
Total 23,925,219,633 100.00% 99.47% -0.53%

 

 

Summary Table of Construction Plan and Progress of Contract 2 for October 2018

Contract 3

Accumulative progress of complete task is 36.28% from the planned target of 61.55% (early plan) and of 55.24% (late plan), or 25.27% and 18.96% behind the early plan and the late plan, respectively.

Details of the tasks are provided hereunder:

No. Activity Status
1. General Management  
1.1 Management Plan In progress
1.2 Facilities and Temporary Access Control In progress
1.3 Utility System In progress
2. Engineering Work  
2.1 Track Work In progress
2.2 Electrical System  
2.2.1 Design of Overhead Catenary System (OCS) In progress
2.2.2 Design of Power Supply and Distribution System (PDS) In progress
2.3 Railway Signaling and Control Systems  
2.3.1 The European Train Control System (ETCS) In progress
2.4 Telecommunication System  
2.4.1 Design of Data Transmission System (DTS) In progress
2.4.2 Design of Radio System In progress
2.4.3 Design of Master Clock (MC) System In progress
2.4.4 Design of CCTV System In progress
2.4.5 Design of Passenger Information Display System (PIDS) In progress
2.4.6 Design of Public Address (PA) System In progress
2.4.7 Design of Station Management System (SMS) In progress
2.4.8 Design of Train-Borne Communication System (TCS) In progress
2.4.9 Design of Telephone System In progress
2.5 Design of Automatic Fare Collection (AFC) System In progress
2.6 Depot Machinery and Equipment  
2.6.1 Design of LD Train Depot Machinery and Equipment In progress
2.6.2 Design of CT Depot Machinery and Equipment In progress
2.7 Other Systems  
2.7.1 Design of Control Access Security System (CASS) In progress
2.7.2 Design of Operation Automation and Information Technology System (OA&IT)) In progress
2.8 Design of Train Car Body In progress
2.9 Construction Planning and Design In progress
3. Procurement of Manufacturers  
3.1 Railway Track In progress
3.2 Electrical System  
3.2.1 Overhead Catenary System (OCS) In progress
3.2.2 Power Supply and Distribution System (PDS) In progress
3.2.3 Information Control System In progress
3.3 Railway Signaling and Control Systems  
3.3.1 Switch Machine In progress
3.4 Telecommunication System  
3.4.1 Data Transmission System (DTS) In progress
3.4.2 Radio System In progress
3.4.3 Master Clock (MC) System In progress
3.4.4 CCTV System In progress
3.4.5 Passenger Information Display System (PIDS) In progress
3.4.6 Public Address (PA) System In progress
3.4.7 Station Management System (SMS) In progress
3.4.8 Train-Borne Communication System (TCS) In progress
3.4.9 Design of Telephone System In progress
3.5 Automatic Fare Collection (AFC) System In progress
3.6 Depot Machinery and Equipment  
3.6.1 LD Train Depot Machinery and Equipment In progress
3.6.2 CT Depot Machinery and Equipment In progress
3.7 Control Access Security System (CASS) and Operation Automation and Information Technology System (OA&IT) In progress
3.8 Train Car  
3.8.1 Materials and Equipment In progress
4. Construction and Installation  
4.1 Track Work In progress
4.2 Distribution substation In progress

 

Summary Report of the Execution of Contract 3 for October 2018

 


 
 