Construction Supervision of Mass Transit System Project in Bangkok (Red Line) Bang Sue-Rangsit Section
Main Menu About the Project Project Development Public Relations Contact
Public Relations
Progress
Activity Photos
  Progress
 

 

November 2013

 

Contract 1

Tasks that have been implemented included clearing, grubbing and land levelling of area in zone 1 and zones 3-5 near the Bang Sue Grand Station; land excavation for foundation works of the Grand Station, installation of bored piles for the construction of station building, and long-distant maintenance depot; demolition of structures at stabling yard, and removal of railway tracks at the Bang Sue Station, demolition of Hopewell structure (at zone 4 phase 1 at the western portion and zone 5 at the northern portion); traffic management for rail track removal in zone 3; construction of site access road in zone 3 of the Bang Sue Grand Station; and construction of local roads in zones 4A, 4B and 5. Plus many others tasks as detailed hereunder:

No. Activity Status
1 Control surveys Completed
2 Land Levelling In operation
3 Preparation of mobilization work (Site office, vehicles and equipment) Completed
4 Land excavation for foundation works of the Grand Station In operation
5 Demolition of Hopewell’s 144 structural columns(Type 1A Case 1 = 25 columns/Type 2B Case 1 = 2 columns/ Type 3A Case 1 = 45 columns/ Type 3B Case 1 = 10 columns/Type 4 Case 1 = 2 columns/ Type 12 Case 2 = 18 columns/ Type 13 Case 2 = 16 columns/ Type 14 Case 3 = 23 columns/ Type 15 Case 3 = 3 columns) In operation
6 Testing work of 3 Pilot piles (diameter = 1,500 mm) (at Terd Damri RoadatMRTA parking lot and at local road near Samian Nari Temple). Completed
7 Testing work of Pilot pile (diameter = 1,200 mm) at the construction site of the Bang Sue Grand Station. Completed
8 Testing work of Pilot pile (diameter = 500 mm) at the construction site of the LD Depots. In operation
9 Pile testing of the existing Hopewell structures at local road near Samian Nari Temple. Completed
10 Batching Plant investigation. In operation
11 Concrete Mixed Designinvestigation. In operation
12 Aggregate source investigation. In operation
13 Bored pile plant investigation. In operation
14 Demolition of premises. In operation
15 Relocation of infrastructural systems, i.e. electricity posts, telegraph posts, etc. In operation
16 Removal of concrete surface. In operation
17 Construction of 571 bored piles (diameter = 1,500 mm) at the Bang Sue Grand Station site. In operation
18 Construction of 66 bored piles (diameter = 500 mm) atLD Passenger Coach construction site. In operation
19 Removal of railway tracksat the Bang Sue Grand Station site. In operation
20 Construction of 154driven piles (diameter = 0.18x0.18 m) atTrain Stablingconstruction site. In operation
21 Construction of drainage pipes at BS7 road. In operation

 

Contract 2

The tasks include: land levelling for the construction of flyover at Sta. 24+910; relocation of infrastructural amenities belonged to the MWA, MEA, and TOT; installation of bored piles for the construction of elevated railway (for 044-086, 101-130, 237-266 sections), driven piling work for elevated rail structure from sections 111 to 131; demolition of structures at D1 (1) to D9 (1). Cast in situ bored pile installation for rail construction at Sta.25+232.5 to Sta.29+145, before reaching Lak Hok Station and flyover at Sta.24+910; removal of oil pipeline and demolition of existing station buildings at Lak Si and Bang Khen. Details of the tasks are provided hereunder:

No. Activity Status
1 Control surveys Completed
2 Land Levelling In operation
3 Preparation of mobilization work (Site office, vehicles and equipment) In operation
4 Demolition of Hopewell’s 398 structural columns
(Type 1 Case 1 = 1 column/ Type 1A Case 1 = 28 columns/ Type 2A Case 1 = 3 columns/ Type 2B Case 1 = 1column/ Type 3A Case 1 = 83 columns/ Type 4 Case 1 = 18 columns/ Type 6 Case 1 = 1 column/ Type 5A Case 2 = 3 columns/ Type 5B Case 2 = 1 column/ Type 7 Case 2 = 7columns/ Type 8 Case 2 = 70  columns/ Type 9 Case 2 = 5columns/ Type 10 Case 2 = 6columns/  Type 11 Case 2 = 84columns/  Type 16 Case 2 = 42 columns/Type 16A Case 2 = 18 columns/ Type 16B Case 2 = 9 columns/ Type 19 Case 2 = 3 columns)
In operation
5
  • Testing work of Pilot pile (diameter = 1,500 mm) at 4 areas: 1) Lak Si area (Sta. 17+500), 2) Near Don Muang District Office (Sta. 20+600), 3) Near the entrance of Grand Canal Village (Sta. 24+600), and 4) at Rangsit Railway Station (Sta. 29+800).
  • Testing work of Pilot pile (diameter = 1,200 mm) near the entrance of Grand Canal Village (Sta. 24+600).
Completed
6 Pile testing of the existing Hopewell structures at local road near Chulabhorn Research Institute (CRI). Completed
7 Installation of 286 bored piles (diameter = 1,500 mm) In operation
8 Construction of 8footing works for the elevated railway(P115, P120, P116, P123,P125, P056, P059, P060). In operation
9 Construction of 7 columns for elevated railway (P115L/R, P116L/R, P120L, P56L/R). In operation
10 Batching plant investigation. In operation
11 Concrete Mixed Design investigation. In operation
12 Aggregate source investigation. In operation
13 Asphalt plant investigation. In operation
14 Bored pile plant investigation. In operation
15 Demolition of existing railway stations (Bang Khen and Lak Si). In operation
16 Work on 955 driven piles (0.35 x 0.35 meters) from Sta.24+830 to Sta.25+152. In operation
17 Work on 1,622 driven piles (0.22 x 0.22 meters) for at-grade railway trackfrom Sta.25+210 to Sta.25+711. In operation
18 Earth filling work for at-grade railway track. In operation
19 Removal of railway trackat the Rangsit Station site. In operation
20 Earth filling work for local roads. In operation
21 Work on 248 driven piles (0.22 x 0.22 meters and 0.26 x 0.26 meters) for the foundation of flyoverfrom Sta.25+201 to Sta.25+253. In operation
22 Reinforced concrete work for at-grade road. In operation

 
 