Construction Supervision of Mass Transit System Project in Bangkok (Red Line) Bang Sue-Rangsit Section
Main Menu About the Project Project Development Public Relations Contact
Public Relations
Progress
Activity Photos

 

  Progress
 

 

Project Progress as of November 2016

 

Contract 1

          Accumulative progress of complete task is 53.30% from the planned target of 95.99%, or 42.69% behind the schedule.

Details of the tasks are provided hereunder:

No. Activity Status
1 Elevated and at Grade Railways Work
  Installed 2,040 from 3,282 columns for the structure of the elevated rail track In operation
  Installed 690 from 2,749 beams for the structure of the elevated rail track In operation
  Installed 71 from 932 main pre-cast concrete spans of the elevated rail track In operation
  Demolition of premises In operation
  Relocation of infrastructural systems, i.e. electricity posts, telegraph posts, etc. In operation
2 Station Work
  Land excavation of 254,496 cu.m from the target of 293,314 cu.m for foundation works of the Grand Station In operation
  Installed the total 623 bored piles (diameter = 800 mm) at the Bang Sue Grand Station construction site Completed
  Installed 1,109 from 1,232 bored piles (diameter = 1,000 mm) (including piles for approach) at the Bang Sue Grand Station construction site In operation
  Installed the total 257 bored piles (diameter = 1,200 mm) at the Bang Sue Grand Station construction site Completed
  Installed the total 123 bored piles (diameter = 2,000 mm) at the Bang Sue Grand Station construction site. Completed
  Lean concrete pouring of 155 from 160 footings at the Bang Sue Grand Station construction site In operation
  Concrete pouring (Type F1A) of 622 from 632 footings at the Bang Sue Grand Station construction site In operation
  Installed 758 structural columns (from the total 800) and 1,625 beams (from the total 1,907) at the Bang Sue Grand Station construction site In operation
  Installed concrete components of elevated structures (84 spans from the total 305 spans) In operation
  Ground and wall concrete pouring for the basement of the Bang Sue Grand Station construction site In operation
3 LD Train Maintenance Depot Work
  Wall masonry and plastering at the Daily Maintenance construction site In operation
  Installed steel structure at the hallway of the Daily Maintenance building In operation
  Installed 1,547 from 1,596 driven piles (0.40x0.40 m) at the Passenger Coach construction site In operation
  Installed column and roof steel structures at the Passenger Coach construction site In operation
  Concrete pouring at the Passenger Coach construction site In operation
  Wall masonry and plastering at the Passenger Coach construction site In operation
4 CT Train Maintenance Depot Work
  Installed the total 266 structural columns at the Main Workshop construction site Completed
  Installed pre-cast beams and concrete pouring at the Main Workshop construction site In operation
  Installed column steel structures at the Main Workshop construction site. In operation
  Installed culverts at the Infrastructure Workshop construction site In operation
  Installed pre-cast slabs and wall masonry at the Infrastructure Workshop construction site In operation
  Installed 1,796 from 2,384 driven piles (0.18x0.18 m) at the Train Stabling construction site In operation
  Finished 741 from 1,168 footings at the Train Stabling construction site In operation
  Installed 1,234 from 2,384 structural columns at the Train Stabling construction site. In operation
  Installed platforms at the Train Stabling construction site In operation
5 Local Road and Road Flyover Work
  Earth filling work for local road In operation
  Installed U-ditches at the construction site In operation

 

 

Summary Report of The Execution of Contract 1 for November 2016

Contract 1: Civil Works for Bang Sue Grand Station and Depots
Bill No. Description Contract Amount(Baht)

% Progress as of 25 November 2016

Status
planned actual
1 General Requirements 266,482,434 95.00% 93.75% -1.25%
2 Track Work 11,422,571,521 96.90% 63.71% -33.19%
3 Stations 14,247,067,853 94.25% 41.43% -52.82%
4 LD Train Depots and CT Train Depots 1,604,023,818 100.00% 94.46% -5.54%
5 Local Road and Road Flyover 1,410,141,074 99.94% 47.78% -52.16%
6 Provisional sums and Provisional Items 672,130,000 100.00% 26.69% -73.31%
7 Day-Work Schedule 17,823,300 88.57% 0.00% -88.57%
Total 29,640,240,000 95.99% 53.30% -42.69%

 

 

Summary Table of Construction Plan and Progress of Contract 1 for November 2016

 

 

Contract 2

         Accumulative progress of complete task is 75.82 % from the planned target of83.20 %, or4.63 % behind the schedule

Details of the tasks are provided hereunder:

No. Activity Status
1 Elevated and at Grade Railway Work
  Installed 9,187 from 14,303 segments for elevated railway In operation
  Earth filling, sand embankment and subballast for at-grade railway track In operation
  Installation of boundary fences In operation
2 Station Work
  Installed aerated concrete walls on ticket hall floor at SamianNari Temple Station In operation
  Flooring tiling work at SamianNari Temple Station In operation
  Installed steel structure for entrance staircases at SamianNari Temple Station In operation
  Installed elevators and escalators at SamianNari Temple Station In operation
  Installed electricity and mechanical systems at SamianNari Temple Station In operation
  Installed aerated concrete walls on ticket hall floor at Bang Khen Station In operation
  Flooring tiling work at Bang Khen Station In operation
  Installed elevators and escalators at Bang Khen Station In operation
  Installed electricity and mechanical systems at Bang Khen Station In operation
  Installed aerated concrete walls on ticket hall floor at Thung Song Hong Station In operation
  Flooring tiling work at Thung Song Hong Station In operation
  Installed electricity and mechanical systems at Thung Song Hong Station In operation
  Installed aerated concrete walls on ticket hall floor at Lak Si Station In operation
  Installed steel structure for entrance staircases at Lak Si Station In operation
  Installed electricity and mechanical systems at Lak Si Station In operation
  Installed aerated concrete walls on ticket hall floor at KanKheha Station In operation
  Installed steel structure for entrance staircases at KanKheha Station In operation
  Installed elevators and escalators at KanKheha Station In operation
  Concrete pouring for construction of ticket hall floor at Don Mueang Station In operation
  Installed steel roof structure at Don Mueang Station In operation
  Installed steel structure for entrance staircases at Don Mueang Temple Station In operation
  Installed elevators and escalators at Don Mueang Station In operation
  Installed steel structure for entrance staircases at LakHok Station In operation
  Installed aerated concrete walls on ticket hall floor at LakHok Station In operation
  Installed elevators and escalators at lakHok Station In operation
  Concrete pouring for construction of ticket hall at Rangsit Station Completed
  Installed roof structures at Rangsit Station Completed
  Installed steel structure for entrance staircases at Rangsit Station In operation
  Installed aerated concrete walls on ticket hall floor at Rangsit Station In operation
3 Local Road and Road Flyover Work
  Earth filling work for local road In operation
  Construction of drainage system for local road In operation

 

 

Summary Report of The Execution of Contract 2 for November 2016

Contract 1: Civil Works for Bang Sue Grand Station and Depots
Bill No. Description Contract Amount(Baht)

% Progress as of 25 November 2016

Status
planned actual
1 General Requirements 272,629,119 92.44% 93.31% 0.87%
2 Track Work 12,431,497,987 89.00% 85.28% -3.72%
3 Stations 9,957,755,499 74.34% 69.23% -5.11%
4 Local Road and Road Flyover 1,263,337,028 94.05% 82.99% -11.06%
5 Provisional Sums and Provisional Items - - - -
Total 23,925,219,633 83.20% 78.57% -4.63%

 

 

Summary Table of Construction Plan and Progress of Contract 2 for November 2016

Contract 3

Accumulative progress of complete task is 3.19 % from the planned target of5.27 % (previous plan) and of 3.41 % (current plan), or 2.08 % and 1.86 % behind the previous plan and the current plan, respectively

Details of the tasks are provided hereunder:

No.

Activity

Status

A

3A Bang Sue-Rangsit

1

Project Management

 

 

Preparation and submission of project management plan

Completed

 

Preparation and submission of contractor’s construction work plan

Completed

 

Preparation and submission of quality assurance system work plan

Completed

 

Preparation and submission of security system work plan

Completed

 

Preparation and submission of EMCmanagement plan

Completed

 

Production and delivery of quality assurance software

Completed

 

Preparation and submission of procurement and production plan

Completed

 

Preparation and submission of engineering work plan

Completed

 

Preparation and submission of audit plan for pre-operation, operation stage and post-operation

Completed

2

Financial Plan

 

 

Preparation and submission of financial plan

In progress

3

Standard Design and Operation Procedure

 

 

Preparation and submission

In progress

4

Electro-Magnetic Compatibility (EMC) System

 

 

Preparation and delivery

Completed

5

Engineering Work

 

5.1

Railway Track

 

 

Survey and confirmation of the necessity oftrack work in accordance with construction activities under Contract 1 and Contract 2

Completed

 

Preparation and submission of information and preliminary design

In progress

5.2

Design of Overhead Contact System(OCS)

 

 

 Survey and confirmation of the necessity of OCS system in accordance with construction activities under Contract 1 and Contract 2

Completed

 

Preparation and submission of information and preliminary design

In progress

5.3

Design of Electrical Power system

 

 

Survey and confirmation of the necessity of electrical power system in accordance with construction activities under Contract 1 and Contract 2

Completed

 

Preparation and submission of information and preliminary design

In progress

5.4

Design of Operation Control Center (OCC)and Centralized Traffic Control (CTC) system

 

 

Survey and confirmation of the necessity in accordance with construction activities under Contract 1 and Contract 2

Completed

 

Preparation and submission of information and preliminary design

In progress

5.5

Design of Computer Based Interlocking (CBI) system

 

 

Survey and confirmation of the necessity in accordance with construction activities under Contract 1 and Contract 2

Completed

 

Preparation and submission of information and preliminary design

 In progress

5.6

Design of Automatic Train Protection (ATP)/Automatic Train Operation (ATO) system

 

 

Survey and confirmation of the necessity in accordance with construction activities under Contract 1 and Contract 2

Completed

 

Preparation and submission of information and preliminary design

In progress

5.7

Design of Wayside Equipment (Signal) System

 

 

Survey and confirmation of the necessity in accordance with construction activities under Contract 1 and Contract 2

Completed

 

Preparation and submission of information and preliminary design

In progress

5.8

Design of Data Transmission System (DTS)

 

 

Survey and confirmation of the necessity in accordance with construction activities under Contract 1 and Contract 2

Completed

 

Preparation and submission of information and preliminary design

In progress

5.9

Design of Radio System

 

 

Survey and confirmation of the necessity in accordance with construction activities under Contract 1 and Contract 2

Completed

 

Preparation and submission of information and preliminary design

In progress

5.10

Design of  Master Clock (MC) System

 

 

Survey and confirmation of the necessity in accordance with construction activities under Contract 1 and Contract 2

Completed

 

Preparation and submission of information and preliminary design

In progress

5.11

Design of CCTV System

 

 

Survey and confirmation of the necessity in accordance with construction activities under Contract 1 and Contract 2

Completed

 

Preparation and submission of information and preliminary design

In progress

5.12

Design of Passenger Information Display System (PIDS)

 

 

Survey and confirmation of the necessity in accordance with construction activities under Contract 1 and Contract 2

Completed

 

Preparation and submission of information and preliminary design

In progress

5.13

Design of Public Address (PA) System

 

 

Survey and confirmation of the necessity in accordance with construction activities under Contract 1 and Contract 2

Completed

 

Preparation and submission of information and preliminary design

In progress

5.14

Design of Station Management System (SMS)

 

 

Survey and confirmation of the necessity in accordance with construction activities under Contract 1 and Contract 2

Completed

 

Preparation and submission of information and preliminary design

In progress

5.15

Design of Train-Borne Communication System (TCS)

 

 

Survey and confirmation of the necessity in accordance with construction activities under Contract 1 and Contract 2

Completed

 

Preparation and submission of information and preliminary design

In progress

5.16

Design of telephone system

 

 

Survey and confirmation of the necessity in accordance with construction activities under Contract 1 and Contract 2

Completed

 

Preparation and submission of information and preliminary design

In progress

5.17

Design of Automatic Fare Collection (AFC) System

 

 

Survey and confirmation of the necessity of  Automatic Fare Collection System (AFC) in accordance with construction activities under Contract 1 and Contract 2

Completed

 

Preparation and submission of information and preliminary design

In progress

5.18

Design of Depot Machinery and Equipment

 

 

Survey and confirmation of the necessity of depot machinery and equipment in accordance with construction activities under Contract 1 and Contract 2

Completed

 

Preparation and submission of information and preliminary design

In progress

5.19

Design of OtherAssociated Systems,including Collision Avoidance System (CAS), Quality Assurance (QA) and Train Information (TI) system

 

 

Survey and confirmation of the necessity of other associated systemsin accordance with construction activities under Contract 1 and Contract 2

Completed

 

Preparation and submission of information and preliminary design

In progress

5.20

Design of Train Car Body

 

 

Survey and confirmation of the necessity in accordance with construction activities under Contract 1 and Contract 2

Completed

 

Preparation and submission of information and preliminary design

In progress

6

Procurement of materials and manufacturers

 

 

Survey, data collection, negotiation and contract signing

In progress

 

Track fasteners, track ballast, turnouts, bumpers and concrete sleepers

In progress

B

3B Bang Sue-Taling Chan

 

1

Survey of construction site for Bang Sue-Taling Chan railway track

In operation


 
 