Construction Supervision of Mass Transit System Project in Bangkok (Red Line) Bang Sue-Rangsit Section
Main Menu About the Project Project Development Public Relations Contact
Public Relations
Progress
Activity Photos

 

  Progress
 

 

December 2014

 

Contract 1

Tasks undertaken by contractor are detailed hereunder:

  • Land levelling, demolition of obstructions, and construction preparation at Bang Sue Grand Station (zone 1, zone 4A, zone 4B, and zone 5), including removal of gas and oil pipelines.
  • Variation of the structure of elevated railway (zone 1, zone 4A phase 2 and 3, and zone 4B phase 1 and 2 including zone 5 at the northern and southern portions).
  • Works according to variation orders include construction in the area of permanent stabling yard for freight train, demolition of existing railway tracks at Bang Sue Grand Station, removal of existing railway tracks for construction of temporary stabling yard for freight train, removal of signaling cable, provision of lighting for roads at the area of stabling yard, replacement of cast-in-situ bored piles with precast driven piles, construction of access road to MRT station at the Grand Station, installation of electrical safety system, provision of earthing and bonding for the foundation construction, provision of lighting at BS7 road and removal of the BMA’s traffic equipment at the area of the Northern Bus Terminal on Terd Damri Road.
  • Construction preparation at the northern and southern portions of the Grand Station (zone 1), basement for railway tracks installation (zone 3, 4A, and 5), construction of access road (zone 2, 5, and 7), local road (zone 4A, 4B, and 5), and road for material transport (zone 6 and 7).
  • Excavation and drainage work, earth filling work, and testing for installation of railway tracks in zone 3 and excavation at the area of daily maintenance depot.
  • Excavation, land levelling, and construction of temporary platform for underground floors of the Grand Station building (gridline 18-20/H-F & 6-20/E, 4-5A-H).
  • Backfill and installation of concrete slabs for foundation works (1st floor) at gridline 6-18/A–D; 6, 15/H-E.
  • Driven pile work for the construction of underground floors of the Grand Station (gridline 4-5A-D; 18H-F; 19-20E; 1-5H-E), access road to station building (gridline 6-12), train station area at the Grand Station (gridline 12-19 at the eastern/western portion), road flyover area at CT train maintenance depot area (basic system workshops and new stabling yards of commuter train), and long-distant maintenance depot (passenger terminal/diesel engine maintenance depot and daily maintenance depot), including elevated railway in zone 4A phase 3 (at the central portion) and zone 1 (at the southern portion).
  • Foundation works of the Grand Station (gridline 9-20H-E; 4-5, 18, 20A-D).
  • Pile driving work for underground floors of the Grand Station (gridline 6-20H-E; 18,20A-D), train station area (gridline 12-19E), and road flyover in new stabling yards and basic system workshops in the CT train maintenance depot, including long-distant maintenance depot.
  • Installation of columns, piles, and beams for the construction of flyover at the Grand Station.
  • Backfill at the Grand Station (gridline 6-16A-D; 6-15H-E).
  • Foundation works of the Grand Station (gridline 9-16A-D; 9-15H-E).
  • Installation of columns and beams No. GB1-GB3 including electrical grounding systems for basic system workshops at CT train maintenance depot area.
  • Installation of electrical grounding systems for CT train maintenance depot.
  • Installation of structural columns at grade beams and ground beams at the area of daily maintenance depot.
  • Installation of stairs at CT train maintenance depot area.
  • Demolition of Hopewell’s 5 structural columns and concrete flyover in zone 4A, demolition of portal frames in phase 2 (zone 4B), demolition of Hopewell structures in zone 5 phase 3 at the northern portion.
  • Embankment work for site access road (zone 2, 5, and 7 phase 2 at the south portion) and roadway embankment in construction site (zone 6 phase 1 and zone 7 phase 1) including local road (zone 4A phase 2 at the western portion).
  • Construction of drainage system for access road (zone 2, 5 and installation of U-drain in zone 7) and for local road (zone 4A).
  • Preparation and traffic management during the removal of existing railway tracks in zone 4A phase 1 and 2 and zone 5 phase 3 at the northern portion, preparation for the construction of local road (zone 4A, 4B, and 5) and site access road (zone 2, 3, 5, and 7) including roadway for internal transportation (zone 6 and 7).
  • Installation of survey points for the construction of road flyover in the Grand Station construction site, maintenance depots, basic system workshops, and new stabling yards (at CT train maintenance depot).
  • Basement for the installation of railway tracks (zone 4A phase 1 and 2), for the construction of site access road (zone 2 and 7 phase 2 at the southern portion), for the construction of stabling yards at CT train maintenance depot and long-distant maintenance depot for material transport (zone 6 phase 1) and for the construction of local road (zone 4A).
  • Basement for the construction of site access road (zone 2 and 7) and local road (zone 4A).
  • Subbase and basement for the construction of local road (zone 4A) and site access road (zone 7).
  • Construction of precast concrete columns and segments for the construction of the Grand Station.
  • Installation of oil pipeline of FPT.
  • Connection of oil pipeline of FPT.

           Other activities were indicated in the Index. Accumulative progress of complete task is 16.94% from the planned target of 30.67%, or 13.73% behind the schedule.

Details of the tasks are provided hereunder:

No. Activity Status
1 Elevated and at Grade Railways Work
  Testing of 3 pilot piles (diameter = 1,500 mm) (at Terd Damri Road at MRTA parking lot and at local road near Samian Nari Temple). Completed
  Testing of pilot piles (diameter = 1,200 mm) at the construction site of the Grand Station. Completed
  Testing of pilot piles (diameter = 800 mm) at the construction site of road flyover. Completed
  Pile testing of the existing Hopewell structures at local road near Samian Nari Temple. Completed
  Demolition of 237 from 239 Hopewell’s structural columns (Type 1A Case 1 = 65 columns/ Type 2A, 2B Case 1 = 11 columns/ Type 3A, 3B Case 1 = 60 columns/ Type 4 Case 1 = 5 columns/ Type 12 Case 2 = 29 columns/ Type 13 Case 2 = 32 columns/ Type 14 Case 3 = 32 columns/ Type 15 Case 3 = 3 columns) In operation
  Installed 64 from 214 (diameter = 1,200 mm) bored piles for the structure of the elevated rail track. In operation
  Installed 699 from 2,596 bored piles (diameter = 1,500 mm) for the structure of the elevated rail track. In operation
  Installed 23 from 114 bored piles (diameter = 2,000 mm) for the structure of the elevated rail track. In operation
  Installed 3 from 16 barrette piles In operation
  Concrete pouring of 40 footings for elevated railway In operation
  Demolition of premises. In operation
  Relocation of infrastructural systems, i.e. electricity posts, telegraph posts, etc. In operation
  Removal of concrete surface. In operation
2 Station Work
  Land excavation of 254,496 cu.m from the target of 293,314 cu.m for foundation works of the Grand Station. In operation
  Installed 467 from 623 bored piles (diameter = 800 mm) at the Bang Sue Grand Station construction site. In operation
  Installed 666 from 1,005 bored piles (diameter = 1,000 mm) (including piles for ascents) at the Bang Sue Grand Station construction site. In operation
  Installed 162 from 231 bored piles (diameter = 1,200 mm) at the Bang Sue Grand Station construction site. In operation
  Installed 1,689 from 1,706 bored piles (diameter = 1,500 mm) at the Bang Sue Grand Station construction site. In operation
  Installed 91 from 123 bored piles (diameter = 2,000 mm) at the Bang Sue Grand Station construction site. In operation
  Lean concrete pouring of 111 from 160 footings at the Bang Sue Grand Station construction site. In operation
  Concrete pouring (Type F1A) of 95 from 632 footings at the Bang Sue Grand Station construction site. In operation
  Removal of railway tracks at the Bang Sue Grand Station construction site. In operation
  Installation of fuel oil pipeline of FPT In operation
3 Long-Distant Maintenance Depot Work
  Installed 1,426 driven piles (0.40x0.40 m) and construction of 234 bored piles (diameter 0.50 m.) at the Daily Maintenance construction site. Completed
  Finished 469 from 709 footings at the Daily Maintenance construction site. In operation
  Installed 398 from 4,991 structural columns at the Daily Maintenance construction site. In operation
  Installed pre cast beams at the Daily Maintenance construction site. In operation
  Installed 1,153 from 1,596 driven piles (0.40x0.40 m) at the Passenger Coach construction site. In operation
4 CT Train Maintenance Depot Work
  Installed 985 from 1,559 driven piles (0.40x0.40 m) at the Main Workshop construction site. In operation
  Finished 177 from 328 footings at the Main Workshop construction site. In operation
  Installed 97 structural columns at the Main Workshop construction site. In operation
  Installed 582 driven piles (0.40x0.40 m) at the Infrastructure Workshop construction site. Completed
  Finished 232 from 244 footings at the Infrastructure Workshop construction site. In operation
  Installed 232 from 244 structural columns at the Infrastructure Workshop construction site. In operation
  Installed pre cast beams at the Infrastructure Workshop construction site. In operation
  Installed 1,764 from 2,384 driven piles (0.18x0.18 m) at the Train Stabling construction site. In operation
  Finished 741 from 1,168 footings at the Train Stabling construction site. In operation
  Installed 1,234 from 2,384 structural columns at the Train Stabling construction site. In operation
5 Local Road and Road Flyover Work
  Earth filling work forlocal road. In operation
  Installed 504 from 816 driven piles (0.22x0.22 m) for road flyover. In operation
  Installed 172 from 306 driven piles (0.26x0.26 m) for road flyover. In operation
  Installed 209 from 282 bored piles (diameter = 0.80 m). In operation
  Finished 21 from 33 footings for road flyover. In operation
  Installed 19 from 33 structural columns for road flyover. In operation
  Installed U-ditches at the construction site In operation
6 Other Works
  Batching plant investigation. In operation
  Concrete mixed design investigation. In operation
  Aggregate source investigation. In operation
  Bored pile plant investigation. In operation
  Control surveys Completed
  Land levelling In operation

 

Summary Report of The Execution of Contract 1 for December 2014

Contract 1 : Civil Works for Bang Sue Grand Station and Depots
Bill No. Description Contract Amount (BahT) % Progress as of
25-DECEMBER-14
Status
Planned Actual
1 General Requirements 266,482,434 46.39% 56.50% 10.11%
2 Track work 11,422,571,521 24.43% 7.90% -16.53%
3 Stations 14,247,067,853 24.57% 18.10% -6.46%
4 LD-Train Depots and CT-Train Depots 1,604,023,818 74.81% 56.36% -18.45%
5 Local Road and Road Flyover 1,410,141,074 80.92% 21.69% -59.23%
6 Provisional Sums and Provisional Items 672,130,000 49.86% 26.69% -23.17%
7 Day-Work Schedule 17,823,300 0.00% 0.00% 0.00%
Total 29,640,240,000 30.67% 16.94% -13.73%

 

Summary Table of Construction Plan and Progress of Contract 1 for December 2014

 

 

Contract 2

Tasks undertaken by contractor are detailed hereunder:
  • Maintenance work and traffic management for temporary diversions at foundation piles No. 317-371 and for temporary access road (Sta. 25+232.5 to Sta. 29+124), measurement work and mitigation of environmental impact, and environmental public relations, including procurement and maintenance of traffic equipment.
  • Relocation of infrastructural amenities belonged to the MWA, MEA, and TOT.
  • Demolition of structures and buildings such as the upper part of at-grade concrete slabs and transition point of at-grade railway bridge at Sta. 29+145.
  • Installation of bored piles (for piles No. 297-328(L&R), 343-376 (R/L), 377-430, 470-446, 504-489, and 529A-505) for elevated railways.
  • Installation of structures for elevated railways including foundation works (columns No. 025-033 R/L, 166-199, 200-211L, 229-235L, 236-265, 275-279, 280-296, 377-430, 470-447 R/L), installation of structural columns (lower columns No. 044-053 (L&R), 054-078, 97-131, 237-266 and 280-296), and cast-in-situ reinforced beams (lower part of the superstructure No. 054-078, 97-131, 237-266, and 280-296).
  • Installation of viaduct box girder (for piles No. 165-099).
  • Excavation and embankment for the construction of at-grade railway track near Rangsit Station, compacted sand at the area of transition railway at Lak Hok Station from Sta. 25+232.5 to Sta. 29+145 and from Sta. 31+485 to Sta. 32+350, excavation, backfill, and installation of steel sheet piles for erosion prevention, compacted sand for the basement at Samian Nari Temple Station, Thung Song Hong Station, Lak Si Station, Khan Keha Station, Lak Hok Station, and Rangsit Station, and for road flyover at Sta. 24+910.
  • Pile driving work and reinforcement configuration (for the construction of transition railway near Lak Hok Station from Sta. 25+232.5 to. Sta. 29+145 and from Sta. 31+485 to Sta. 32+350 and for the construction of road flyover at Sta. 24+910).
  • Lean concrete pouring for the construction of transition railway near Lak Hok Station.
  • Foundation works at transition railway (at the transition point near Lak Hok Station) including at-grade railway and transition railway from Sta.25+232.5 to 29+145 and from Sta. 31+485 to Sta. 32+350.
  • Construction of retaining wall at transition railway near Lak Hok Station.
  • Installation of barrette piles at Don Muang Station (R/L).
  • Footing works at Samian Nari Temple Station (R/L), Bang Khen Station (R), Lak Si Station (R/L), Thung Song Hong Station (R/L), Kan Kheha Station (R/L), Lak Hok Station  (R) and Rangsit Station (R/L).
  • Installation of lower part of superstructure at Samian Nari Temple Station (R), Thung Song Hong Station (R/L), Lak Si Station (R/L), and Khan Keha Station (R), and Rangsit Station (R/L).
  • Cast-in-situ beams for road flyover at Sta. 24+910.
  • Cast-in-situ stairs, beams and other superstructure for road flyover at Sta. 24+910.
  • Demolition of existing station building and construction of temporary site office with facilities at Don Muang Station.
  • Removal of SIG & COM systems at Don Muang Station and Rangsit Station, including local road.
  • Dynamic load test and seismic test

           Other activities were indicated in the Index. Accumulative progress of complete task is 29.77% from the planned target of 71.49%, or 41.72% behind the schedule.

Details of the tasks are provided hereunder:

No. Activity Status
1 Elevated and at Grade Railways Work  
  Demolition of Hopewell’s 553 structural columns
(Type 1 Case 1 = 1 column, Type 1A Case 1 = 31 columns, Type 2A Case 1 = 5 columns, Type 2B  Case 1 = 1 column, Type 3A Case 1 = 83 columns, Type 4 Case 1 = 18 columns, Type 6 Case 1 = 1 column, Type 5A Case 2 = 3 columns, Type 5B Case 2 = 1 column, Type 7 Case 2 = 7 columns, Type 8 Case 2 = 75 columns, Type 9 Case 2 = 10 columns, Type 10 Case 2 = 6 columns, Type 11 Case 2 = 84 columns, Type 14 Case 3 = 138 columns, Type 15 = 6 columns, Type 16 Case 2 = 42 columns, Type 16A Case 2 = 18 columns, Type 16B Case 2 = 9 columns, Type 18 Case 2 = 11 columns, Type 19 Case 2 = 3 columns).
Completed
  Testing work of pilot pile (diameter = 1,500 mm) in 4 areas: 1) Lak Si area (Sta. 17+500), 2) Near Don Muang District Office (Sta. 20+600), 3) Near the entrance of Grand Canal Village (Sta. 24+600), and 4) at Rangsit Railway Station (Sta. 29+800). Completed
  Testing work of pilot pile (diameter = 1,200 mm) near the entrance of Grand Canal Village (Sta. 24+600). Completed
  Pile testing of the existing Hopewell structures at local road near Chulabhorn Research Institute (CRI). Completed
  Installation of 299 bored piles (diameter = 1,200 mm) for elevated railway. In operation
  Installation of 855 bored piles (diameter = 1,500 mm) for elevated railway. In operation
  Installation of 886 bored piles (diameter = 1,800 mm) for elevated railway. In operation
  Installed 86 from 111 barrette piles for elevated railway. In operation
  Finished 362 footings for elevated railway In operation
  Installed 355 structural columns for elevated railway. In operation
  Installed 138 from 428 cross beams for the structure of elevated railway. In operation
  Installed 736 from 14,303 segments for elevated railway. In operation
  Installed 1,507 from 1,604 driven piles (0.35x0.35 m) at Sta. 24+830 to Sta. 25+152. In operation
  Installation of 16,121 driven piles (0.22x0.22 m) from 28,571 driven piles at Sta. 25+210 to Sta. 28+900. In operation
  Earth filling, sand embankment and subballast for at-grade railway track. In operation
  Reinforced concrete work for at-grade railway track. In operation
2 Station Work
  Demolition of existing railway stations (Bang Khen and Lak Si). Completed
  Installation of 66 bored piles (diameter = 1,500 mm) and 44 barrette piles at Samian Nari Temple Station. Completed
  Finished 22 footings for elevated railway at Samian Nari Temple Station. Completed
  Installed 23 from 44 structural columns for elevated railway at Samian Nari Temple Station. In operation
  Installation of cross beams for elevated railway at Samian Nari Temple Station. In operation
  Installation of 66 bored piles (diameter = 1,500 mm) and 44 barrette piles at Bang Khen Station. Completed
  Finished 14 from 22 footings for elevated railway at Bang Khen Station. In operation
  Installed 5 from 44 structural columns for elevated railway at Bang Khen Station. In operation
  Installation of 66 bored piles (diameter = 1,500 mm) and 44 barrette piles at Thung Song Hong Station. Completed
  Finished 22 footings for elevated railway at Thung Song Hong Station. Completed
  Installed 27 from 44 structural columns for elevated railway at Thung Song Hong Station. In operation
  Installation of cross beams for elevated railway at Thung Song Hong Station. In operation
  Installation of 132 bored piles (diameter = 1,500 mm) at Lak Si Station. Completed
  Finished 21 from 22 footings for elevated railway at Lak Si Station. In operation
  Installed 20 from 44 structural columns for elevated railway at Lak Si Station. In operation
  Installation of cross beams for elevated railway at Lak Si Station. In operation
  Installation of 128 bored piles (diameter = 1,500 mm) at Kan Kheha Station. Completed
  Finished 22 footings for elevated railway at Khan Keha Station. Completed
  Installed 18 from 44 structural columns for elevated railway at Kan Kheha Station. In operation
  Installed 161 from 171 barrette piles at Don Muang Station. In operation
  Finished 8 from 34 footings for elevated railway at Don Muang Station. In operation
  Installation of 108 bored piles (diameter = 1,000 mm) at Lak Hok Station. Completed
  Finished 18 footings for elevated railway at Lak Hok Station. Completed
  Installation of 470 bored piles (diameter = 1,500 mm) at Rangsit Station. Completed
  Finished 50 footings for elevated railway at Rangsit Station. Completed
  Installed 23 structural columns for elevated railway at Rangsit Station. In operation
3 Local Road and Road Flyover Work
  Construction of 528 driven piles (0.22 x 0.22 m and 0.26 x 0.26 m) for road flyover from Sta. 25+201 to Sta. 25+253. Completed
  Installation of 122 bored piles for road flyover (diameter = 800 mm). Completed
  Foundation work of 14 footings for road flyover at Sta. 24+910. Completed
  Installation of 14 structural columns for road flyover at Sta. 24+910. Completed
  Installation of pre cast I-girders for road flyover at Sta. 24+910. Completed
  Concrete bridge deck for road flyover at Sta. 24+910. In operation
  Installed 581 from 591 driven piles (0.22 x 0.22 m and 0.26 x 0.26 m) for road flyover at Sta. 27+650. In operation
  Installation of 66 bored piles (diameter = 800 mm) for road flyover at Sta. 27+650. Completed
  Finished 6 footings for road flyover at Sta. 27+650. In operation
  Installation of 6 structural columns for road flyover at Sta. 27+650. In operation
  Earth filling work for local road In operation
4 Other Works
  Batching plant investigation. In operation
  Concrete mixed design investigation. In operation
  Aggregate source investigation. In operation
  Control surveys Completed
  Land levelling In operation
  Procurement and relocation (site office, vehicles and equipment) Completed

 

Summary Report of The Execution of Contract 2 for December 2014

Contract 2 : Civil Works for Bang Sue - Rangsit Railway
Bill No. Description Contract Amount (BahT) %Progress as of
25-DECemBER-14
Status
Planned Actual
1 General Requirements 272,629,120 63.92% 58.40% -5.52%
2 Track work 10,514,931,561 74.43% 34.63% -39.80%
3 Stations 8,558,445,112 70.64% 29.65% -40.99%
4 Local Road and Road Flyover 1,264,542,043 54.38% 7.23% -47.15%
5 Provisional Sums and Provisional Items - 0.00% 0.00% 0.00%
Total 20,610,547,836 71.49% 29.77% -41.72%

 

Summary Table of Construction Plan and Progress of Contract 2 for December 2014

 
 
โครงการระบบรถไฟชานเมือง (สายสีแดง) ช่วงบางซื้อ-รังสิต
Visitors