Construction Supervision of Mass Transit System Project in Bangkok (Red Line) Bang Sue-Rangsit Section
Main Menu About the Project Project Development Public Relations Contact
Public Relations
Progress
Activity Photos

 

  Progress
 

 

Project Progress as of December 2016

 

Contract 1

          Accumulative progress of complete task is 54.62 % from the planned target of 98.63%, or 44.01% behind the schedule.

Details of the tasks are provided hereunder:

No. Activity Status
1 Elevated and at Grade Railway Work
  Installed 2,201 from 3,282 columns for the structure of the elevated rail track In operation
  Installed 770 from 2,749 beams for the structure of the elevated rail track In operation
  Installed 88 from 932 main precast concrete spans of the elevated rail track In operation
  Demolition of premises In operation
  Relocation of infrastructural systems, i.e. electricity posts, telegraph posts, etc. In operation
2 Stations
  Land excavation of 254,496 cu.m from the target of 293,314 cu.m for foundation works of the Bang Sue Grand Station In operation
  Installed 1,109 from 1,232 bored piles (diameter = 1,000 mm) (including piles for approach) at the Bang Sue Grand Station construction site In operation
  Lean concrete pouring of 155 from 160 footings at the Bang Sue Grand Station construction site In operation
  Concrete pouring (Type F1A) of 622 from 632 footings at the Bang Sue Grand Station construction site In operation
  Installed 758 structural columns (from the total 800) and 1,707 beams (from the total 1,907) at the Bang Sue Grand Station construction site In operation
  Installed concrete components of elevated structures (95 spans from the total 305 spans) In operation
  Ground and wall concrete pouring for the basement of the Bang Sue Grand Station construction site In operation
3 LD Train Maintenance Depot Work
  Wall masonry and plastering at the Daily Maintenance construction site In operation
  Installed steel structure at the hallway of the Daily Maintenance building In operation
  Installed 1,547 from 1,596 driven piles (0.40x0.40 m) at the Passenger Coach construction site In operation
  Installed column and roof steel structures at the Passenger Coach construction site In operation
  Concrete pouring at the Passenger Coach construction site In operation
  Wall masonry and plastering at the Passenger Coach construction site In operation
4 CT Train Maintenance Depot Work
  Installed the total 266 structural columns at the Main Workshop construction site In operation
  Installed precast beams and concrete pouring at the Main Workshop construction site In operation
  Installed column steel structures at the Main Workshop construction site In operation
  Installed culverts at the Infrastructure Workshop construction site In operation
  Installed precast slabs and wall masonry at the Infrastructure Workshop construction site Completed
  Installed 1,796 from 2,384 driven piles (0.18x0.18 m) at the Train Stabling construction site In operation
  Finished 741 from 1,168 footings at the Train Stabling construction site In operation
  Installed 1,234 from 2,384 structural columns at the Train Stabling construction site In operation
  Installed platforms at the Train Stabling construction site In operation
5 Local Road and Road Flyover Work
  Earth filling work for local road In operation
  Installed U-ditches at the construction site In operation

 

 

Summary Report of The Execution of Contract 1 for December 2016

Contract 1: Civil Works for Bang Sue Grand Station and Depots
Bill No. Description Contract Amount  (Baht) % Progress as of 25 December 2016 Status
planned actual
1 General Requirements 266,482,434 97.15% 95.12% -2.04%
2 Track Work 11,422,571,521 98.78% 66.13% -32.66%
3 Stations 14,247,067,853 98.19% 42.14% -56.05%
4 LD Train Depots and CT Train Depots 1,604,023,818 100.00% 94.88% -5.12%
5 Local Road and Road Flyover 1,410,141,074 99.96% 47.94% -52.03%
6 Provisional sums and Provisional Items 672,130,000 100.00% 26.69% -73.31%
7 Day-Work Schedule 17,823,300 92.31% 0.00% -92.31%
Total 29,640,240,000 98.63% 54.62% -44.01%

 

 

Summary Table of Construction Plan and Progress of Contract 1 for December 2016

 

 

Contract 2

         Accumulative progress of complete task is 80.05 % from the planned target of85.56 %, or 5.51 % behind the schedule

Details of the tasks are provided hereunder:

No. Activity Status
1 Elevated and at Grade Railway Work
  Installed 9,187 from 14,303 segments for elevated railway In operation
  Earth filling, sand embankment and subballast for at-grade railway track Completed
  Installation of boundary fences In operation
2 Station Work
  Installed aerated concrete walls on ticket hall floor at WatSamianNari Station In operation
  Flooring tiling work at WatSamianNari Station In operation
  Installed steel structure for entrance staircases at WatSamianNari Station In operation
  Installed elevators and escalators at WatSamianNari Station In operation
  Installed electricity and mechanical systems at WatSamianNari Station In operation
  Installed aerated concrete walls on ticket hall floor at Bang Khen Station In operation
  Flooring tiling work at Bang Khen Station In operation
  Installed elevators and escalators at Bang Khen Station In operation
  Installed electricity and mechanical systems at Bang Khen Station In operation
  Installed aerated concrete walls on ticket hall floor at Thung Song Hong Station In operation
  Flooring tiling work at Thung Song Hong Station In operation
  Installed electricity and mechanical systems at Thung Song Hong Station In operation
  Installed aerated concrete walls on ticket hall floor at Lak Si Station In operation
  Installed steel structure for entrance staircases at Lak Si Station In operation
  Installed electricity and mechanical systems at Lak Si Station In operation
  Installed aerated concrete walls on ticket hall floor at KanKheha Station In operation
  Installed steel structure for entrance staircases at KanKheha Station In operation
  Installed elevators and escalators at KanKheha Station In operation
  Concrete pouring for construction of ticket hall floor at Don Mueang Station In operation
  Installed steel roof structure at Don Mueang Station In operation
  Installed steel structure for entrance staircases at Don Mueang Temple Station In operation
  Installed elevators and escalators at Don Mueang Station In operation
  Installed steel structure for entrance staircases at LakHok Station In operation
  Installed aerated concrete walls on ticket hall floor at LakHok Station In operation
  Installed elevators and escalators at lakHok Station In operation
  Installed steel structure for entrance staircases at Rangsit Station In operation
  Installed aerated concrete walls on ticket hall floor at Rangsit Station In operation
  Installed elevators and escalators at Rangsit Station In operation
3 Local Road and Road Flyover Work
  Earth filling work for local road In operation
  Construction of drainage system for local road In operation

 

 

Summary Report of The Execution of Contract 2 for December 2016

Contract 2: Civil Works for Bang Sue-Rangsit Railway
Bill No. Description Contract Amount  (Baht) % Progress as of  25 December 2016 Status
planned actual
1 General Requirements 272,629,119 93.60% 94.20% 0.60%
2 Track work 12,431,497,987 91.48% 86.94% -4.54%
3 Stations 9,957,755,499 76.50% 70.51% -5.99%
4 Local Road and Road Flyover 1,263,337,028 96.98% 84.37% -12.61%
5 Provisional Sums and Provisional Items - - - -
Total 23,925,219,633 85.56% 80.05% -5.51%

 

 

Summary Table of Construction Plan and Progress of Contract 2 for December 2016

Contract 3

Accumulative progress of complete task is 4.21 % from the planned target of7.25 % (early plan) and of 4.47 % (late plan), or 3.04 % and 0.26 % behind the early plan and the late plan, respectively

Details of the tasks are provided hereunder:

No. Activity Status
A 3A Bang Sue-Rangsit
1 Project Management  
  Preparation and submission of project management plan Completed
Preparation and submission of contractor’s construction work plan Completed
Preparation and submission of quality assurance system work plan Completed
  Preparation and submission of security system work plan Completed
  Preparation and submission of EMCmanagement plan Completed
  Production and delivery of quality assurance software Completed
  Preparation and submission of procurement and production plan Completed
  Preparation and submission of engineering work plan Completed
  Preparation and submission of audit plan for pre-operation, operation stage and post-operation Completed
2 Financial Plan  
  Preparation and submission of financial plan In progress
3 Standard Design and Operation Procedure  
  Preparation and submission In progress
4 Electro-Magnetic Compatibility (EMC) System  
  Preparation and delivery Completed
5 Engineering Work  
5.1 Railway Track  
  Survey and confirmation of the necessity of track work in accordance with construction activities under Contract 1 and Contract 2 Completed
  Preparation and submission of information and preliminary design In progress
5.2 Design of Overhead Contact System(OCS)  
   Survey and confirmation of the necessity of OCS system in accordance with construction activities under Contract 1 and Contract 2 Completed
  Preparation and submission of information and preliminary design In progress
5.3 Design of Electrical Power System  
  Survey and confirmation of the necessity of electrical power system in accordance with construction activities under Contract 1 and Contract 2 Completed
  Preparation and submission of information and preliminary design In progress
5.4 Design of Operation Control Center (OCC) and Centralized Traffic Control (CTC) system  
  Survey and confirmation of the necessity in accordance with construction activities under Contract 1 and Contract 2 Completed
  Preparation and submission of information and preliminary design In progress
5.5 Design of Computer Based Interlocking (CBI) System  
  Survey and confirmation of the necessity in accordance with construction activities under Contract 1 and Contract 2 Completed
  Preparation and submission of information and preliminary design In progress
5.6 Design of Automatic Train Protection (ATP)/ Automatic Train Operation (ATO) System  
  Survey and confirmation of the necessity in accordance with construction activities under Contract 1 and Contract 2 Completed
  Preparation and submission of information and preliminary design In progress
5.7 Design of Wayside Equipment (Signal) System  
  Survey and confirmation of the necessity in accordance with construction activities under Contract 1 and Contract 2 Completed
  Preparation and submission of information and preliminary design In progress
5.8 Design of Data Transmission System (DTS)  
  Survey and confirmation of the necessity in accordance with construction activities under Contract 1 and Contract 2 Completed
  Preparation and submission of information and preliminary design In progress
5.9 Design of Radio System  
  Survey and confirmation of the necessity in accordance with construction activities under Contract 1 and Contract 2 Completed
  Preparation and submission of information and preliminary design In progress
5.10 Design of  Master Clock (MC) System  
  Survey and confirmation of the necessity in accordance with construction activities under Contract 1 and Contract 2 Completed
  Preparation and submission of information and preliminary design In progress
5.11 Design of CCTV System  
  Survey and confirmation of the necessity in accordance with construction activities under Contract 1 and Contract 2 Completed
  Preparation and submission of information and preliminary design In progress
5.12 Design of Passenger Information Display System (PIDS)  
  Survey and confirmation of the necessity in accordance with construction activities under Contract 1 and Contract 2 Completed
  Preparation and submission of information and preliminary design In progress
5.13 Design of Public Address (PA) System  
  Survey and confirmation of the necessity in accordance with construction activities under Contract 1 and Contract 2 Completed
  Preparation and submission of information and preliminary design In progress
5.14 Design of Station Management System (SMS)  
  Survey and confirmation of the necessity in accordance with construction activities under Contract 1 and Contract 2 Completed
  Preparation and submission of information and preliminary design In progress
5.15 Design of Train-Borne Communication System (TCS)  
  Survey and confirmation of the necessity in accordance with construction activities under Contract 1 and Contract 2 Completed
  Preparation and submission of information and preliminary design In progress
5.16 Design of telephone system  
  Survey and confirmation of the necessity in accordance with construction activities under Contract 1 and Contract 2 Completed
  Preparation and submission of information and preliminary design In progress
5.17 Design of Automatic Fare Collection (AFC) System  
  Survey and confirmation of the necessity of  Automatic Fare Collection System (AFC) in accordance with construction activities under Contract 1 and Contract 2 Completed
  Preparation and submission of information and preliminary design In progress
5.18 Design of Depot Machinery and Equipment  
  Survey and confirmation of the necessity of depot machinery and equipment in accordance with construction activities under Contract 1 and Contract 2 Completed
  Preparation and submission of information and preliminary design In progress
5.19 Design of OtherAssociated Systems, including Collision Avoidance System (CAS), Quality Assurance (QA) and Train Information (TI) system  
  Survey and confirmation of the necessity of other associated systems in accordance with construction activities under Contract 1 and Contract 2 Completed
  Preparation and submission of information and preliminary design In progress
5.20 Design of Train Car Body  
  Survey and confirmation of the necessity in accordance with construction activities under Contract 1 and Contract 2 Completed
  Preparation and submission of information and preliminary design In progress
6 Procurement of materials and manufacturers  
  Survey, data collection, negotiation and contract signing In progress
  Track fasteners, track ballast, turnouts, bumpers and concrete sleepers In progress
7 Provision of standard construction machinery and equipment and submission for approval In operation
B 3B Bang Sue-Taling Chan  
1 Survey of construction site for Bang Sue-Taling Chan railway track In operation

 
 